1 / 13

Project Management OPER 576

Project Management OPER 576. Project Networks Greg Magnan, Ph.D. April 29, 2004. Project Life Cycle Stages. II. Project Planning. Sequence Deliverables To help schedule work efficiently Consider all WBS elements Estimate calendar duration for each List precedence for each task

gigi
Télécharger la présentation

Project Management OPER 576

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Management OPER 576 Project Networks Greg Magnan, Ph.D. April 29, 2004

  2. Project Life Cycle Stages

  3. II. Project Planning • Sequence Deliverables • To help schedule work efficiently • Consider all WBS elements • Estimate calendar duration for each • List precedence for each task • May construct network diagram • CRITICAL PATH: longest path through the network showingminimumtime needed • Delays to elements on the critical path delay the entire project! • Mascitelli: Critical Core

  4. Activity Time Estimates • PERT-based • Assumptions: • “normal” operations • independent estimates for activities • Optimistic / Most-likely / Pessimistic • Formula (O + 4M + P)/6 • Example (10 + 4*15 + 26)/6 = 16

  5. Project Networks • Developed from WBS • WBS must be deliverables-oriented! • Activity Labeling: use WBS outline as basis • Used for Planning, scheduling, controlling • Activities, sequences, precedence rel’ps • Critical Path / “Crashing” network • Basis for Resource Scheduling • Communication to stakeholders • Estimate of project duration

  6. Network Terms • Activity • An element in the project that consumes time, but doesn’t necessarily require resources (e.g., approvals, contract signing) • “Events” do not consume time • Can include one or more Work Packages • Verb/noun format • Critical path • Path: a sequence of connected, dependent activities • CP: Longest path through the network • Activity-on-Node (AON) vs. Activity-on-Arc (AOA) • AON is most commonly used (software packages) • Nodes reflect activities

  7. AON Network Development Rules • Arrows indicate precedence and flow • Flow from left to right • Precedence determined after WBS complete • Predecessor and Successor activities • Preceding activities must be complete before beginning successor activities • Activities need labels • Larger numbers than preceding activities • No Looping! • No conditional (if/then) statements • Single Start and End nodes

  8. Project Scheduling: Node Elements

  9. PERT Diagram(Activity on Node)

  10. Sample Problem Activity Duration Predecessor A 5 none B 10 none C 15 A D 10 A E 5 B F 20 C G 20 E H 5 D, F, G I 15 H

  11. Forward & Backward Pass • Determine: • Early Start (ES) and Early Finish (EF) • Late Start (LS) and Late Finish (LF)…and then Slack • Forward Pass (EF and ES) • For each path in the network, add activity times (duration) to each ES to get EF (ES + Dur = EF) • EF of preceding activity becomes ES of successor, unless • Succeeding activity is a merge activity (>1 predecessor) • Then select LARGEST EF time from all predecessor EF times to become ES for successor activity

  12. Forward & Backward Pass • Backward Pass (LF and LS) • Must have already completed Forward Pass • Start with the latest EF of last activity in the network • For each path in the network, subtract activity times (duration) from each LF to get LS (LF - Dur = LS) • LS of successor activity becomes LF of preceding, unless • The next preceding activity is a burst activity (>1 successor) • Then select SMALLEST LS time from all immediate successor activities to determine LF time

  13. Conclusion… • Projects are everywhere • Can be actively managed • Science AND art

More Related