FEE Installation & Commissioning TPC Meeting, 17 February 2006 L. Musa

FEE Installation & Commissioning TPC Meeting, 17 February 2006 L. Musa. Content Status of FEE Installation Installation and Commissioning Schedule. FE Cards Installation 1/4. Installation Team & Schedule Roberto Campagnolo, Antoine Junique, Luciano Musa, Lennart Osterman,

gpringle
Télécharger la présentation

FEE Installation & Commissioning TPC Meeting, 17 February 2006 L. Musa

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FEE Installation & Commissioning TPC Meeting, 17 February 2006 L. Musa • Content • Status of FEE Installation • Installation and Commissioning Schedule

  2. FE Cards Installation 1/4 • Installation Team & Schedule • Roberto Campagnolo,Antoine Junique, Luciano Musa, Lennart Osterman, • Bjorn Halvor Straume (→Gunnar Lovhoiden) • 2 x 7-hours shifts per day, 6 days / week • Installation started on the 30th January (17 working days) • Status • 16 Sectors of A side are complete, 17th Sector almost complete (12 cards to be installed)  2043 FECs installed • the 18th sector (Sector #13) can only be installed on next Wednesday after the installation of the new I-bars on the A side

  3. FE Cards Installation 2/4 #4 #0 #8 #12 #14 TPC A Side (17th February ’06)

  4. FE Cards Installation 3/4 17th February ‘06 #10 #11 #12

  5. FE Cards Installation 4/4 During the installation, the FECs are tested individually (stand-alone) by means of a dedicated “mounting test tool”, U2F (USB to FEC interface) • Readout of trigger related data (pulser) • Connection to the pad plane • Measurement of VCCA, VCCD, IA, ID and T • Test of all CSRs, Control & Readout path U2F Card

  6. Installation Test Software 1/2

  7. Installation Test Software 2/2

  8. Installation Summary Results List of pads that do not have a proper connection to the transfer connector

  9. Installation and Commissioning Schedule 1/2 • FECs Mass test • completed inJanuary ‘06 • RCU Production (240 units including 10% spares) • completed in November ‘05 • RCU Mass Test • completed inDecember ’05 • Delivery of tested DCS cards: January ‘06 • Delivery of tested SIU cards: April ‘06 • Assembly and final test of RCU + SIU + DCS: May ‘06

  10. Installation and Commissioning Schedule 2/2 PHASE I • Installation of FECs and Backplanes Jan ’05 - Mar ’06 • functional and electrical test of each FEC • test of the connection between FECs and pad plane • test of the connection between FECs and readout backplane PHASE II • Inspection of the system with RCUs Mar – Sep ’06 • Inspection of up to 12 readout partitions (2 Sectors) concurrently • Comprehensive test: FEE, DAQ, DCS, TRIGGER, HLT, ECS (power bars and cooling required) PHASE III • Installation of RCUs May – Jun ’06 • thorough test of all (216) readout partitions