1 / 10

Chapter 8: PERT, CPM, GERT

Chapter 8: PERT, CPM, GERT. Originated from Govern./Research (Navy/Lockheed) Focus on time Optimistic, most likely and pessimistic time . Originated from private Industry Focus on cost Crash Time and Crash cost. PERT x CPM (both 1950s). PERT Formulas p.231-232.

graceland
Télécharger la présentation

Chapter 8: PERT, CPM, GERT

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Chapter 8: PERT, CPM, GERT

  2. Originated from Govern./Research (Navy/Lockheed) Focus on time Optimistic, most likely and pessimistic time Originated from private Industry Focus on cost Crash Time and Crash cost PERT x CPM (both 1950s)

  3. PERT Formulas p.231-232 Optimistic, most likely, and pessimistic time Estimated time of task Estimate Variance of task Estimated time of project Estimated variance of project Z

  4. CPM Based on idea that a project has a Normal Time to complete a job. Normal time is the cheapest. If it takes longer or shorter, it will usually be more expensive. Why ?

  5. To crash a project , PM may need one or more of the below, resulting in great cost • Overtime workers • Use breakthrough equipment • Start a phase of the project (Design, for example) before a pre-requisite phase is completed (Analysis, for example) • Hire consultants.

  6. Which Task to Crash ? • Not a steep slope (big decrease in time with only little increase in cost) • Task that is part of the CP. • Crashing the task will not have a negative colateral result to the rest of the company’s activities or projects (for example, need to stop something else to crash that task).

  7. GERT, different from others because: • Not all immediate predecessor activities must be completed before activity is started • Looping back is permitted. • Percentage probability

  8. Tasks not completed Q: Example of a project where not all tasks need to be completed for the project to be completed ? A2: You research three different possible solutions to cure cancer (three different groups). Once one group solves the problem, other group (tasks) can be disactivated. A1: To decide if you give credit or not to somebody you do three types of credit check. If any two comes through with success, credit is conceived.

More Related