Instrument models and test campaigns

Instrument models and test campaigns. Overview of tests and test campaigns: CQM-ILT, CQM-IMT , FM 1, and FM 2 SVR 20 – 21 April 2006, Groningen W. Luinge. Introduction. DM-ILT program finished (band 1, 5, partial warm units) Validation of test equipment & EGSE “finished”

hailey
Télécharger la présentation

Instrument models and test campaigns

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Instrument models and test campaigns Overview of tests and test campaigns:CQM-ILT, CQM-IMT , FM 1, and FM 2 SVR 20 – 21 April 2006, Groningen W. Luinge

  2. Introduction • DM-ILT program finished (band 1, 5, partial warm units) • Validation of test equipment & EGSE “finished” • Testing as much as possible via CUS scripts, configuration files, MIB • Analysis of results partly via database/IA

  3. CQM (EQM)-ILT • Early October 2004 – 12 December 2004 • Configuration: • FP Band 3 (H/V) • WBS one polarization • HRS one polarization • ICU no redundancy (AVM) • OBS … - 2.22 • LO (band 3A/B, few frequencies); LSU simulator • Goal: Preparation for IMT (no external stimulator) • Tests: Functional test (no tuning); stability (; standing waves) • Conclusions on ripples, diplexer behavior (together with 2 side bands and standing waves), calibration source, noise temperature, LO reproducibility, chopper & OBS (non-)behavior • Start of understanding HIFI

  4. CQM-IMT • At ‘satellite’ level • In old ISO cryostat, with PACS and SPIRE • Control via CCS, Herschel PDU simulator • With LSU simulator • ICU CFM 2 for EMC test • October (IMT), November/December 2005(EMC, thermal behavior) • Results: see presentation of Nick Whyborn • Also results regarding integration procedures, use of IEGSE, etc

  5. FM 1 • FM1 refers to FPU tests with MSA’s 1, 2, 3, 5 • November/December 2005 • To test FPU performance (presentation of P. Dieleman) • To measure the beams (presentation of M. Jochemsen) • Feedback (new grids in band 1, polarization correction in band 5, chopper magnets): implemented • In this period also the start of the WBS integration with ICU/EGSE/HCSS • inrush current reduction, OBSW debugging, new HCSS release, new OBSW version, temperature stability of environment, … : not yet finished completely --------------------- • After FM1: completion of the FPU and modifications

  6. FM 2 • Now going on • FPU performance of all bands and beam measurements • Check improvements • Continuation of WBS integration • ICU (AVM2, OBS 3.5), GSE and tested with scripts: KOSMA performance not fully reproduced • Start of ICU - HRS integration • HRS integrated with ICU, WBS (AVM2, OBS 3.5), GSE and tested with scripts: CESR performance reproduced (TBC) • Test equipment is being upgraded (// set up, re-imager controlled by scripts, etc.) • Next: Integration with ICU ..; preparation for cold vibration