PSI Large Research Facilities Status

PSI Large Research Facilities Status. SLS, Proton Facility, PROSCAN, PSI-XFEL. In use. In transition. Planned. EPICS Usage at PSI. XFEL 250 MeV Injector Test. XFEL Low Emittance Gun Test. PSI-XFEL. PROSCAN. Proton Superbuncher. UCN Timing. He Liquefaction. SLS.

helga
Télécharger la présentation

PSI Large Research Facilities Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PSI Large Research Facilities Status SLS, Proton Facility, PROSCAN, PSI-XFEL Dirk Zimoch, EPICS Collaboration Meeting October 2008

  2. In use In transition Planned EPICS Usage at PSI XFEL 250 MeV Injector Test XFEL LowEmittanceGun Test PSI-XFEL PROSCAN Proton Superbuncher UCN Timing He Liquefaction SLS Operations Building Dirk Zimoch, EPICS Collaboration Meeting October 2008

  3. New Operations Building • New "combined function" control room • SLS • Proton facility • PROSCAN • XFEL • New server room • New offices • New cafeteria Dirk Zimoch, EPICS Collaboration Meeting October 2008

  4. SLS Filling Pattern Feedback • Better charge distribution • Improved beam stability • Separate talk Dirk Zimoch, EPICS Collaboration Meeting October 2008

  5. SLS Beamline IT Infrastructure Upgrade • Old SLS control room became new server room for beamlines • New data storage • Up to 30 TB per beamline • New network topology • Separate talk Dirk Zimoch, EPICS Collaboration Meeting October 2008

  6. Other SLS (PX) Beamline Improvements • High precision rotation stage • separate talk • Sample mounting robot • separate talk • Pilatus 6M detector Dirk Zimoch, EPICS Collaboration Meeting October 2008

  7. ProtonFacility Optis Eye Cancer Therapy SINQ Spallation Neutron Source Ring Cyclotron UCN Ultra Cold Neutrons Gantry 1 PROSCAN Proton Therapy Optis 2 Gantry 2 Dirk Zimoch, EPICS Collaboration Meeting October 2008

  8. Cyclotron Upgrade • New cavities for beam current upgrade to 3 mA • Replace old CAMAC with new VME hardware • New superbuncher runs with EPICS • Long term future plans: • Replace complete control system with EPICS • Integrate pion/muon beamlines • Upgrade network infrastructure Dirk Zimoch, EPICS Collaboration Meeting October 2008

  9. UCN (Ultra Cold Neutrons) • Spallation source under construction (start ~2009) • 5K cold deuterium moderator • neutrons <1µeV, 7m/s, 25km/h • Proton beam time structure is controlled with EPICS • Lead target • D2O moderator • Solid D2 moderator • UCN guide • Valve • To experiments • Storage tank Dirk Zimoch, EPICS Collaboration Meeting October 2008

  10. PROSCAN • Dedicated accelerator for cancer treatment with protons • Over one year in operation • At the moment: Trying to replace accelerator control system with EPICS • Problem: Can test only on weekends • Early 2009: Optis 2 • Partially EPICS • Patient treatment system is not EPICS • Late 2009: Gantry 2 Dirk Zimoch, EPICS Collaboration Meeting October 2008

  11. PSI-XFEL Experiment Building Tunnel is a bridge here ! Low Emittance Gun Aare SLS 800 m tunnel 400 m Linac 80 m Undulators farm land Dirk Zimoch, EPICS Collaboration Meeting October 2008

  12. PSI-XFEL Schedule • 500 keV gun test dismantled • Setup of 4 MeV test • Building for 250 MeV test linac under construction • Milestone: Proof of principle in October 2010 • XFEL construction start in 2011 • XFEL operation start in 2016 Dirk Zimoch, EPICS Collaboration Meeting October 2008

  13. /dev/video EPICS server PC WWW server Firewire Camera Server • Linux IOC with embedded HTTP server • Used for beam diagnostics at SLS, XFEL, … • See Mirosław Dach's talk at PCaPAC Dirk Zimoch, EPICS Collaboration Meeting October 2008

  14. Other controls activities • Upgrade of PCs to Scientific Linux 5 • Many unexpected problems • Adaption of SLS controls tools for XFEL • Build up IT infrastructure for XFEL • Evaluation of embedded Linux IOCs • Evaluation of remote control (web access) for SLS beamlines • Planned: Upgrade of SLS IOCs to EPICS 3.14 Dirk Zimoch, EPICS Collaboration Meeting October 2008