1 / 7

X-Ray Calorimeter Mission Study Summary

X-Ray Calorimeter Mission Study Summary. Team Lead Mark Steiner 2 – 6 April 2012. X-ray Cal Presentation Timeline. MDL Mission Study Summary. MDL developed mission concept for calorimeter configuration, based on customer inputs

henrik
Télécharger la présentation

X-Ray Calorimeter Mission Study Summary

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. X-Ray Calorimeter MissionStudy Summary Team Lead Mark Steiner 2 – 6 April 2012

  2. X-ray Cal Presentation Timeline

  3. MDL Mission Study Summary • MDL developed mission concept for calorimeter configuration, based on customer inputs • MDL team presented formal, final report out to customer team • Presentations were reviewed by MDL team for internal consistency on Thursday • Delta options identified for last X-ray mission study (“Delta” week) • TBD - Decision to be made at later date by customer team

  4. Mission Summary – Final (same as Monday) Orbit parameters – L2, 800,000 km Lissajous LV – Falcon 9 Launch date – March 25, 2022 Mission Lifetime – 3 year minium / 5 year goal Mass estimate – payload: 221 kg (Instrument) 319 kg (X-Ray Mirror) – 540 kg total Power estimate – payload: 686W (Instrument) , 320 W (X-Ray Mirror) – 1006 W total Mission class –B Disposal plans – Same as Grating Mission ( 1 m/s delta-V at EOL) Study name: MDL X-ray Grating WBS: 244904.04.10.01.02 ”MDL X-ray Cal” in remarks

  5. MDL Areas of Concentration/Study Drivers • Use of Solar Panels to balance CP-CG offset • Adapt AXSIO inner Mirror purge cover for this SC concept • Need for heater power on the SC structure adjacent to FMA to maintain FMA thermal requirements If possible… • Increase pitch to +/-45 trade for articulated solar panel

  6. Study Plan for the week • Monday AM: review study expectations and identify key issues PM: 1) define ConOps 2) discuss derived subsystem requirements and ask questions • Tuesday AM: System drivers – TBD subsystems PM: Rest of subsystems • Wednesday AM: I&T Flow, Mission Ops PM: Presentation preparation • Thursday AM: Check presentations for consistency PM: Finish presentations • Friday Presentation with customers, including remote customer team • Monday following 1) Lessons learned, process improvements, lab status, etc. 2) Finalize presentations and wrap up the study

  7. X-Ray Calorimeter Program flow Mission Critical Design Review (CDR) 2/13/2019 ATP - Phase B Start S/C Bus 9/1/2016 Preliminary Design Review (PDR) 11/22/2017 S/C Bus Contract Award System Definition Review (SDR) Project Start ~ 8/8/2014 Phase A Preliminary Analysis Phase B Definition and Prelim Design Phase C Final Design Preliminary Design Mission Definition System Definition Final Design 16 “months” 24“months” 16“months” End of Extended Mission 6/25/2027 End of Primary Mission 6/25/2025 Instrument Delivery FMA: 12/8/2020 XMS: 2.26/2021 Launch 3/25/2022 Transition To Nominal Ops 6/25/2022 Ready to Ship 10/8/2021 Phase D-1 Subsystem Development, S/C Integration & Test, Launch Prep Phase D-2 Launch & Checkout Total Funded Reserve Phase E/F Operations Fab., S/C Assy & Func. I&T 19mo’s Prep for Launch 3mo’s Obser. I&T 11mo’s Cruise, Orbit Insertion & Checkout PrimaryMission Extended Mission ? 7.5 months Launch (Spread through Phases C & D) 33 “months” 36 months 24 months 3months Notes: Timeline not to scale; 1 “month” = 28 days.

More Related