HMC/KMC Connecting Rod Powder Forging Localization Plan LAUNCH PLAN

HMC/KMC Connecting Rod Powder Forging Localization Plan LAUNCH PLAN. November 30, 2005. Localization Assumptions. New program awards required for localization roadmap (KIA Lambda volume, and MU2 )

ilana
Télécharger la présentation

HMC/KMC Connecting Rod Powder Forging Localization Plan LAUNCH PLAN

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HMC/KMC Connecting Rod Powder Forging Localization Plan LAUNCH PLAN November 30, 2005

  2. Localization Assumptions • New program awards required for localization roadmap (KIA Lambda volume, and MU2 ) • KIA forged connecting rod business would be the initial localization step followed by HMC Lambda machining • Install flexible machining capacity to manufacture HMC Lambda and MU2 programs • Beyond current US investment, Metaldyne is committing to approximately $45M in investment to support HMC/KMC

  3. MANUFACTURING PLAN

  4. MKL Building Expansion PHASE 2 PHASE 1 • MKL Building Expansion • Floor space requirements: • Year 1: Forge Module A= 1600m2 • Year 2: Machining Line 1 = 1100m2 • Year 3: Machining Line 2 = 2200m2 • Year 3: Forge Module B = 1600m2 • Equipment installation • 2007 SOP: Powder Forge Module A • 2008 SOP: Machining Line 1 • 2009 SOP: Machining Line 2 • 2009 SOP: Powder Forge Module B Powder Forge Manufacturing Installation (2) Modules = 4,000 m2

  5. Manufacturing Plan Forging Machining • Launch LAMBDA KIA forging at NV: • Review KIA machining line • KIA forging ISIR Approval • SOP: JULY ’06 • Transfer powder forging Module A to MKL: • ISIR Approval • Ramp down NV – Ramp up MKL • SOP; JULY ‘07 • Launch LAMBDA HMC forging and finish machining at MKL: • Install 1.8M machining capacity • Flexible line for Lambda & MU2 • LAMBDA HMC ISIR Approval • Ramp down NV-Ramp up MKL • SOP: JULY ’08 • Launch MU2 forging and finish machining at MKL: • Install Powder Forging Module B • SOP: 2009 • Install incremental machining capacity for MU2 LAMBDA KIA LAMBDA HMC

  6. Launch Timing