1 / 11

E906 Spectrometer Upgrade Overview

E906 Spectrometer Upgrade Overview. Paul E. Reimer Magnet Concept Design Estimates (Money & Time). Magnet Concept. Use pieces from existing (but dismantled) SM12 Magnet This was the large dipole used by E866 and predecessors Design coils to minimize the need to cut existing iron

imala
Télécharger la présentation

E906 Spectrometer Upgrade Overview

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. E906 Spectrometer Upgrade Overview Paul E. Reimer Magnet Concept Design Estimates (Money & Time)

  2. Magnet Concept • Use pieces from existing (but dismantled) SM12 Magnet • This was the large dipole used by E866 and predecessors • Design coils to minimize the need to cut existing iron • Decrease nonBend aperture • to match downstream acceptance • Save on Amp-Turns • Tapered pole pieces • Copper Beam dump (either modified from E866/SM12 or new) • Graded hadron absorber within aperture of magnet (Copper, Carbon, Polyethylene) Paul Reimer E906 Sepctrometer Upgrade Overview

  3. 50’ (9 blocks long) 66” 2£17” 198” SM12 Removal Paul Reimer E906 Sepctrometer Upgrade Overview

  4. M1 Magnet • New coils • Reuse whole pieces of SM12 magnet yoke (1/3 or total SM12 yoke) • Beam dump either modified to fit or new (from Fermilab) • Coil Design Team • Jack Jagger—Engineering (PHY-STA) • Ken Thompson—Field, power calculations, etc (APS) • Tom O’Connor and Kevin Bailey—design and drafting (PHY) Paul Reimer E906 Sepctrometer Upgrade Overview

  5. M1 Magnet Paul Reimer E906 Sepctrometer Upgrade Overview

  6. Budgetary Estimates: Aluminum conductor • Conductor Properties • Al 1350 Alloy • 1.6 £ 1.6 inch • 0.700 inch diameter hole for cooling • Estimate From Alconex, Fort Wayne, IN • Will vary with base metal price • Investigating additional possible vendors Paul Reimer E906 Sepctrometer Upgrade Overview

  7. Budgetary Estimate: Coil Fabrication • Contacted 5 possible vendors in Fall 2004 for budgetary estimates based on preliminary designs—4 vendors responded by January 2005 • Revisited estimates with 3 of 4 vendors for this review (Oct-Nov 2006) • For budget, estimate is based on Sigma Phi total, but will use lowest bidder in which there is confidence • × 1.2 (contingency) × 1.1 (Overhead) × 1.03 (inflation) Paul Reimer E906 Sepctrometer Upgrade Overview

  8. M1 Magnet Coil Fabrication Budget • Tab. III of review document • Cost dominated by cost of conductor and coil ($1.3M of $1.6M) Paul Reimer E906 Sepctrometer Upgrade Overview

  9. Coils: Fabrication time • Schedule based on longest lead-time vendor: • Sigma Phi: 10 Months with conductor available 4 months before delivery • Everson Tesla: 18-22 week (5 months) • Alpha Magnetics: no estimate • Requested Budget—purchase coils over two years: • FY2007: • Bid and contract for coils • Purchase tooling • FY2008 (starting in Jan 2008)—this is delay is the critical path item: • Purchase conductor • Fabrication of coils Paul Reimer E906 Sepctrometer Upgrade Overview

  10. Magnet Timeline Al Conductor delayed to FY08 Coil Fabrication delayed to FY08 Paul Reimer E906 Sepctrometer Upgrade Overview

  11. Conclusions • Design of magnet is underway • Sufficiently advanced enough to obtain reasonable budgetary estimates on coil fabrication from vendors • Both budget and time line are based on conservative estimates Paul Reimer E906 Sepctrometer Upgrade Overview

More Related