1 / 9

Review VVER-1000 LBLOCA Report

Review VVER-1000 LBLOCA Report. Vietnam trainees. Sequence of events and operation of systems. Assumption: Location of break: reactor inlet (850 mm diameter pipe) Break type: double-ended guillotine break Loss of the primary coolant is maximal

indiya
Télécharger la présentation

Review VVER-1000 LBLOCA Report

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Review VVER-1000 LBLOCA Report Vietnam trainees

  2. Sequence of events and operation of systems • Assumption: • Location of break: reactor inlet (850 mm diameter pipe) • Break type: double-ended guillotine break • Loss of the primary coolant is maximal • Comment: ( OK the mots conservative case with maximal loss of coolant ) • Purpose of analysis: • Trace the change of some main parameters of RCS • Check of meeting the acceptance criteria • Comment: ( OK )

  3. Sequence of events and operation of systems • Phenomena: • Large of coolant inventory discharge through the break • Sharp decrease in the primary pressure occurs • Core may be uncovered and reduction in heat removal from the core • Sharp increase in temperature of fuel rod claddings • Sequence Events • LB LOCA occurs • Trip reactor when pressure decrease to 14.7 Mpa (1.5 s delay) • Pumps trip and coast down • Termination of steam bleeding from SG to the turbine • ECCS inject water into RX • Steam pressure in SG increases (Why?) • Comment: ( Assumption power at 100% of nominal?)

  4. Sequence of events and operation of systems • Additional condition together with the accidents: • LOOP (loss of offsite power) • Comment: (OK more conservative study ) • ECCS injection: • High-pressure safety injection system (JND) inject at high pressure • The ECCS passive part (JNG2) inject when pressure reach the set point • The low-pressure safety injection system (JNG1) inject when pressure decrease to 2.5 MPa • Delay for starting pump for JND and JND1 around 40 s • After around 120 s EFWP feed the SG level • Comment: ECCS passive part (acc) will inject first then HPSI and LPSI working later due to delay for DG start.

  5. Safety assessment criteria • Acceptance Criteria: • PCT less than 1200 oC • Oxidation depth not exceed 18% • Total amount of oxidized zirconium does not exceed 1% • Comment: (Oxidation depth need to be less than 17%) • Single failure assumption: • Filure of one diesel-generator then failure of one JND pump and one JNG1 pump • Failure of one accumulator • The most effective control rod remains in upper position upon the scram signal • Comment (OK)

  6. Calculation results • Blow down phase (Pressure decrease and Flow rate at break):

  7. Calculation results • Refill and reflood phases:

  8. Calculation results • Long term cooling phase:

  9. Calculation results • PCT: