Session 9 Guardrail Connections to Bridge Ends

Session 9 Guardrail Connections to Bridge Ends. Common Deficiencies in Bridge Railings. Inadequate Dynamic Strength Potential for Snagging Use of “Safety” Walk Inadequate Transition. Transitions. Guardrail Deflects – Bridge Ends DONOT!!

indiya
Télécharger la présentation

Session 9 Guardrail Connections to Bridge Ends

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Session 9Guardrail Connections to Bridge Ends

  2. Common Deficiencies in Bridge Railings • Inadequate Dynamic Strength • Potential for Snagging • Use of “Safety” Walk • Inadequate Transition

  3. Transitions • Guardrail Deflects – Bridge Ends DONOT!! • Bridge End Connections are an example of a change in the type of Barrier Deflection Characteristics • Must Reduce the Deflection of the Guardrail before you reach the Bridge End from 3’ to Zero • Must have adequate Structural Connection

  4. Transition Considerations • Adequate structural connection to the bridge railing • Reduced post spacing and nested rail to increase stiffness gradually • Block outs and rub rails used to minimize snagging

  5. How can you REDUCE DEFLECTION of Standard Strong Post W-Beam Guardrail • Normal Guardrail Post Spacing is 6’3” • Reduce Post Spacing to 3’ 1½” and reduce deflection by 50% • Nest the Guardrail (double thickness) and reduce deflection by 50% • Add a Guardrail panel to the back of the Post and reduce deflection by 50% • Add a Rub Rail and reduce deflection by nearly 50% & reduce snagging potential • Combine 2 of the above and reduce deflection by 75%

  6. How can you REDUCE DEFLECTION of Standard Strong Post W-Beam Guardrail Reduced Post Spacing Nested

  7. Gradually Increase Stiffness by Increasing the number of Post

  8. Rub Rail Components - Std Draw RBC-001 002 & 003 “Guardrail Connection to Bridge End Type A and A-1 Components” Rub Rail Not Island Curb Rub Rail

  9. Standard Drawing RBC-001Guardrail Connector to Bridge End Type A and A-1

  10. Inadequate Structural Connection or Stiffening of Approach Rail

  11. Adequate Structural Connection Terminal Sect No 2 Plate A & BStd Draw RBC-002 & 003

  12. Inadequate Reduction in Deflection and Structural Connection

  13. Transition of Curb and Rub Rail to Bridge’s Safety Shape

  14. Addition of a Spacer Tube

  15. Combination of all of the Proceeding for a Successful Transition

  16. Std Draw RBC-001 Guardrail Connection to Bridge End Type A and A-1

  17. Curb Inlet Type BShould have Island Curb in Throat of the Inlet • Std Draw RBC-001 Note 5 “Island Curb” • Std Draw RBD-280 “Match Adjacent Curb”

  18. Curb Inlet Type BShould have Island Curb in Throat of the Inlet • Lt Std Draw old RBD-280 Curb Box Inlet Type B (Detail Drawing) “Match Adjacent Curb” • Rt Std Draw RBD-281 Curb Box Inlet Type B (Steel Drawing) "Island Curb Detail”

  19. Type B Drainage Box As-Builts vs. Std Draw Construction memo No 5-11July 6, 2011 • Have not been getting Island Curb on Type B Inlet therefore a Const Memo was Issued • See Std Draw RBC-001, RBD-280, RBD-281 Previous Slides • Corrective Actions: • Retrofit by extending the double ply rail from 25 linear feet to 50 linear feet • Replace the drain box top with the correct one

  20. Std Draw RDB-280 Curb Box Inlet Type B 2012 Design Changed Detail to Show Island Curb instead of Std Curb Changed to Island Curb

  21. Normally getting Standard Curb instead of Island Curb

  22. Rub Rail Components - Std Draw RBC-001 002 & 003 “Guardrail Connection to Bridge End Type A and A-1 Components” Rub Rail Not Island Curb Rub Rail

  23. What is the Difference in Type A and A-1 Connection to Bridge EndStd Drawing RBC-001 ??? Std Draw RBC-001 Note 1. c. Std Draw RBC-001 Note 3. d.

  24. Type A Curb is needed even if there is not a Drop Box – WHY?? Helps prevent the vehicle’s wheel from coming in contact with the Bridge End. Works in combination with the rub rail in the Transition to Safety Shape on Bridge. The Curb is not just for drainage. Curb is sometimes left off in error.

  25. What makes this a good Guardrail Connection to Bridge End? Q & A Time