ME1/1 OTMB Production Readiness Review: Schedule and Budget

ME1/1 OTMB Production Readiness Review: Schedule and Budget. Darien Wood Northeastern University For the ME1/1 Electronics Project. Categories. On-chamber electronics DCFEBs (504 + spares) LVDB (72+) LVMB (72+) ALCT mezz (72+) Peripheral crate electronics OTMB mezz (72+)

jara
Télécharger la présentation

ME1/1 OTMB Production Readiness Review: Schedule and Budget

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ME1/1 OTMB Production Readiness Review: Schedule and Budget Darien Wood Northeastern University For the ME1/1 Electronics Project

  2. Categories • On-chamber electronics • DCFEBs (504 + spares) • LVDB (72+) • LVMB (72+) • ALCT mezz (72+) • Peripheral crate electronics • OTMB mezz (72+) • OTMB base boards (72+) • ODMB (72+) • Infrastructure • New LV supplies, junction boxes, cables supply to JB • Patch panels • Peripheral crate modification • Optical cables • Signal cables (pads to DCFEB – 40% new)

  3. Groups • In addition, integration testing involved many groups: OSU, UCSB, TAMU, NEU, Rice, JINR and NCPHEP

  4. Schedule Milestones • TC1 schedule (17-May-2013) • ME1/1 Milestones

  5. Where we are today • DCFEB: • Production underway • 10 preproduction boards in hand • 2 production boards in hand • Another 92 production boards expected in ~1 week • OTMB mezzanine • R&D prototype (2010-11) – used for design choices and radiation testing • Preproduction (2012) – nearly final design, used with DCFEBs in B904 • Firmware developed to implement current trigger algorithm with optical iput from 7 DCFEBs • 8 boards in hand • ODMB • First prototype (2012) • Only designed for optical TTC (anticipating FF_EMU ASIC, which was abandoned after the prototype design) • Limited capability for interfacing with DCFEB, but able to read out optical data path • Second prototype (April 2013) • Fully functional design • Boards at UCSB, OSU, Rice and CERN

  6. Schedule Roll-up • OTMB and ODMB production overlap installation of on-chamber electronics and installation of chambers

  7. OTMB mezz: production and testing • Have a total of 8 pre-production Mezz already in hand • 8 tested production boards to CERN: • 18 July 2013 • All boards tested: • 17 Oct 2013

  8. ME1/1 Electronics Project M&S summary *originally in ME4/2 budget

  9. OTMB mezzanine cost details 72 boards + 15 spares = 87 boards Single costs (setup, testing, shipping): $25.5 k Total production cost estimate: $301k Already procured: SNAP-12 receivers

  10. Backup Slides

  11. Draft Schedule for OTMB base board • To be done by Texas A & M • First pass at schedule

  12. TMB base board costs Estimated total cost (72+18 boards): $161k Estimated contingency: $17k