1 / 45

Case Study 1: Thirty Seven Acre Reservoir Project

Case Study 1: Thirty Seven Acre Reservoir Project. Paul Keiran – R1. Course Overview. Introduction and Inspector Qualifications Pre-Inspection Preparation Construction Site Compliance Evaluation Field Monitoring at Construction Sites Compliance Inspection Reports

jody
Télécharger la présentation

Case Study 1: Thirty Seven Acre Reservoir Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Case Study 1: Thirty Seven Acre Reservoir Project Paul Keiran – R1 Course Overview • Introduction and Inspector Qualifications • Pre-Inspection Preparation • Construction Site Compliance Evaluation • Field Monitoring at Construction Sites • Compliance Inspection Reports • Compliance Inspection Data Management • Compliance Enforcement Activities • Case Study

  2. Thirty Seven Acre Reservoir Project • Began construction in summer of 2000 • Work ended in 2002 • Involved complicated fill slopes • Involved significant storm water runoff • We all learned some significant lessons about what to use and when to use it Case Study 1: Thirty Seven Acre Reservoir Project

  3. Case Study 1: Thirty Seven Acre Reservoir Project

  4. Regulatory Realities Owner obtained appropriate storm water permit September 2000 storm event produced a warning about the need for significantly increase Erosion and Sediment Control (ESC) efforts The following two months revealed minimal ESC efforts Subsequent winter rains then created havoc Case Study 1: Thirty Seven Acre Reservoir Project

  5. Case Study 1: Thirty Seven Acre Reservoir Project

  6. Case Study 1: Thirty Seven Acre Reservoir Project

  7. Case Study 1: Thirty Seven Acre Reservoir Project

  8. Case Study 1: Thirty Seven Acre Reservoir Project

  9. Case Study 1: Thirty Seven Acre Reservoir Project

  10. Case Study 1: Thirty Seven Acre Reservoir Project

  11. Case Study 1: Thirty Seven Acre Reservoir Project

  12. Case Study 1: Thirty Seven Acre Reservoir Project

  13. Case Study 1: Thirty Seven Acre Reservoir Project

  14. Something Must Be Done Let’s Put Jute (Burlap) Matting On the Slopes Case Study 1: Thirty Seven Acre Reservoir Project

  15. Case Study 1: Thirty Seven Acre Reservoir Project

  16. Case Study 1: Thirty Seven Acre Reservoir Project

  17. Never Put Matting On Deeply Rutted Slopes • Runoff will find those gullies and continue to erode the soil • Slopes must be smooth prior to applying matting • Obviously re-grading was not going to occur in January Case Study 1: Thirty Seven Acre Reservoir Project

  18. Case Study 1: Thirty Seven Acre Reservoir Project

  19. Rainy Season #2 Let’s Try Hydroseeding Those Hills Case Study 1: Thirty Seven Acre Reservoir Project

  20. Case Study 1: Thirty Seven Acre Reservoir Project

  21. Case Study 1: Thirty Seven Acre Reservoir Project

  22. Don’t Use Hydroseed Alone on Long Steep Slopes! It’s Risky! • Must be used in conjunction with other BMPs • What BMPs work best with hydroseed on steep slopes? Case Study 1: Thirty Seven Acre Reservoir Project

  23. Case Study 1: Thirty Seven Acre Reservoir Project

  24. July 2001 ACLC $60K (6 days of observed discharge violations, no estimate of volume discharged) Discharger wished to perform supplemental environmental project (SEP) in lieu of a portion of the fine May 2002 - ACLC re-issued with SEP language Fines bumped to $70K due to another observed discharge Case Study 1: Thirty Seven Acre Reservoir Project

  25. Late Spring 2002 Everyone Gets Religion Case Study 1: Thirty Seven Acre Reservoir Project

  26. Case Study 1: Thirty Seven Acre Reservoir Project

  27. Case Study 1: Thirty Seven Acre Reservoir Project

  28. Case Study 1: Thirty Seven Acre Reservoir Project

  29. Case Study 1: Thirty Seven Acre Reservoir Project

  30. Case Study 1: Thirty Seven Acre Reservoir Project

  31. Case Study 1: Thirty Seven Acre Reservoir Project

  32. Case Study 1: Thirty Seven Acre Reservoir Project

  33. Case Study 1: Thirty Seven Acre Reservoir Project

  34. Case Study 1: Thirty Seven Acre Reservoir Project

  35. Case Study 1: Thirty Seven Acre Reservoir Project

  36. High Flow Drainage Ditches • Cannot be left unprotected • Cannot be controlled with haybales • Must be armored before the start of the rainy season • Should be a top construction priority Case Study 1: Thirty Seven Acre Reservoir Project

  37. Case Study 1: Thirty Seven Acre Reservoir Project

  38. What Lessons are to be Learned Regarding this Site? • Owner employed all the right controls for a steep sloped fill site • Matting • Wattles • Hydroseed • Unfortunately they were all employed at different times! • Using all three methods together, at the beginning of the first rainy season, may well have prevented, or at least greatly minimized, the mental anguish, money, environmental damage and frustration that this site brought Case Study 1: Thirty Seven Acre Reservoir Project

More Related