General Machine Timing System @ FAIR

General Machine Timing System @ FAIR. Just a few slides…. Timing Systems @ FAIR. Bunch phase Timing System (BuTiS) invest € 15k per receiver station ps precision (100ps/km accuracy) distribution of clocks!!! NO time-stamps at FAIR NO timing-events HF group

jovan
Télécharger la présentation

General Machine Timing System @ FAIR

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. General Machine Timing System @ FAIR Just a few slides…. Dietrich Beck - BEL

  2. Timing Systems @ FAIR Bunch phase Timing System (BuTiS) • invest € 15k per receiver station • ps precision (100ps/km accuracy) • distribution of • clocks!!! • NO time-stamps at FAIR • NO timing-events • HF group • one global BuTiS center Talk P. Moritz, FAIR Technikforum General Machine Timing System • based on White Rabbit • fairly cheap: € 800,- SPEC board • sub-ns synchronization • distribution of • (clock) • time-stamps • timing-events • BEL group • one global timing master • clock derived from BuTiS Talk T. Fleck, FAIR Technikforum Remark: If you are interested time-stamps, you need White Rabbit. If you are interested in the most accurate clocks, you need BuTiS. If you are interested in both, you need both. Dietrich Beck - BEL

  3. General Machine Timing System (GMT) @ FAIR parallel execution of beam production chains cycles: 20ms to hours trigger and sync. equipment actions 1 µs precision in 99% of all cases few ns precision for kickers (few ps for rf-systems: BuTiS) many rings > 2000 devices connected to timing system large distances robustness: lose at most one message per year Dietrich Beck - BEL

  4. GMT – Idea set value (schedule) LSA timing events set values (ramp) • SM transmits set values • DM executes schedule by broadcasting timing events • FTRN schedule actions • timely execution of action (here: send IRQ to CPU) • Generate ramp via equipment interface Dietrich Beck - BEL

  5. GMT – Interfaces FrEC Dietrich Beck - BEL

  6. GMT – Data Master SIS18 SIS100 HESR UNILAC beamline Dietrich Beck - BEL

  7. SM generates set value for DM: schedule and alternatives (decision tree, domain specific language) SM sends set value to FESA class of DM FESA class uses a library for on-the-fly source-code generation for soft-CPUs cross-compilation of soft-CPU codes uploading codes to soft-CPUs codes specific to schedule rather simple code Settings Management – Data Master Dietrich Beck - BEL

  8. Simple Machine Specific Soft-CPU Code SIS100: while (state == PRODUCTION) { /* one cycle: BPC1 */ if (IL(BPC1) != OK) cycle1_planB(); else { waitsync(BPC1, INJ_SIS100, timeout); cycle1(); } /* one cycle: BPC2 */ if (IL(BPC2) != OK) cycle2_planB(); else { waitsync(BPC2, INJ_SIS100, timeout); cycle2(); } /* repeat cycle: BPC2 */ if (IL(BPC2) != OK) cycle2_planB(); else { waitsync(BPC2, INJ_SIS100, timeout); cycle2(); } } not shown: • beam processes • error handling • beam request on/off • IL check during cycle execution Dietrich Beck - BEL

  9. 2012 2014 2017 no loosely coupled machines 1 timing master 2 switch layers at TM 4 cables to each building then: distribution to floors then: distribution to rooms 70 m redundant links between switches optical or copper links to nodes 2000-3000 nodes 5 layers of switches (18 ports) in total Dietrich Beck - BEL

  10. Timing-Events – synchronizing actions Info-Telegrams – transmission of (float)-values, e.g. beam-intensity “Action-Events” Commit – switching between FrEC registers containing different set values. Post-Mortem – “freeze” or “unfreeze” ring buffers in FrECs Reset – reset a crashed FrEC Rollback – “undo”? Timing Master to Nodes – Message Types Dietrich Beck - BEL

  11. Forbidden! … except a few specific cases… Fast beam request from local areas (experiments…) via dedicated local interface units managed by BEL Bunch-to-bucket transfer (transfer between ring machines) Nodes to Timing Master – Message Types Dietrich Beck - BEL

  12. Network: Talk by Maciej and Cesar Nodes: In-Kind contribution by Slovenia Network and Nodes Dietrich Beck - BEL

  13. Finalize “WR Starter Kit” Timing System v0.0 – experimental, but 24/7 (2012) Timing System for p-Linac test in Saclay (Beginning 2013) Test: replacing MIL-timing of SIS18 + ESR ( 2014) … The Plan Dietrich Beck - BEL