1 / 14

All Experimenters Meeting PIP Report

All Experimenters Meeting PIP Report. Fernanda G. Garcia on behalf of PIP team 07/01/2013. RFQ Injector Line ( RIL). RIL Highlights – Thin corrector . Thin corrector. Large exit angle

kalkin
Télécharger la présentation

All Experimenters Meeting PIP Report

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. All Experimenters MeetingPIP Report Fernanda G. Garcia on behalf of PIP team 07/01/2013

  2. RFQ Injector Line (RIL)

  3. RILHighlights – Thin corrector Thin corrector • Large exit angle • Correctors are running with high current, predominant vertically, at the downstream end of RFQ in order to maximize beam transmission • Thanks to BNL for the design and FNAL/TD for building the correctors • Corrector installed early June • Modest gain in beam current • Increased extractor voltage by 1.5kV • Yielded 11% more beam at entrance of Linac Contribution: C.Y. Tan F.G. Garcia AEM - PIP Report 07/01/2013

  4. RILHighlights – Source Swap • FNAL/RIL design posses two sources located side-by-side on a slide platform to allow for easy and quick swap • First swap: June 17 • Duration: ~ 7 hrs • Second swap: June 26 • Duration: ~1hr Contribution: D. Bollinger F.G. Garcia AEM - PIP Report 07/01/2013

  5. PIP – Linac Activities

  6. Linac200 MHz RF Power System • Modulator Upgrade • 35kV, Marx-topology modulator to drive triode (or MBK) • SLAC – Two cell test stand • Simulate the ripple due for 2 cells both in phase (11%) and out of phase (0.9%) • Compare 2 cell out-of-phase simulated to measured ripple (1.1%) • Determine via simulation the ripple for 5 vernier cells (0.23%) F.G. Garcia AEM - PIP Report 07/01/2013

  7. Linac200 MHz RF Power System • Modulator Upgrade (cont.) • 35kV, Marx-topology modulator to drive triode (or MBK) • AD/EE – Working on building 9 cell Marx Modulator • Able to create any arbitrary wave shape, from trapezoid to square • In the future: determine rising and falling edge ripple • Built prototype discrete control system • Testing second prototype Marx cell • under normal load conditions (350 Amps) • under short circuit (2000 Amps) • Continue fabrication of 9 cell Marx Modulator F.G. Garcia AEM - PIP Report 07/01/2013

  8. Linac200 MHz RF Power System • MBK201FERMI • 7MW pulsed klystron to operate at 200 MHz for use as a power source for the DTL Linac • Procurement • Received approval from directorate to proceed with the MBK201 prototype • New cost/schedule was developed between Fermi and seller • Current awaiting PO to be accepted • Estimate to be complete this week • Activities • Initiate gallery floor plan layout in collaboration with AD/MSD Drafter Dept. Courtesy: D. Hurd F.G. Garcia AEM - PIP Report 07/01/2013

  9. LinacUtilities • Power Distribution • L1 transformer • Continue with prep work for the installation of L1 transformer. • Electrical conduit relocation complete • Lead abatement & relocation steel beam complete Hatch location Tentative delivery date: Week July 15th. F.G. Garcia AEM - PIP Report 07/01/2013

  10. LinacLaser Notcher • Reduce losses in Booster generated by the creation of the notch • 3D printer model of the vacuum interface and the optical cavity • Good progress with beam shaping optics Design beam size 1 mm x 6 mm Horizontal Beam size as shown ~ ¾ mm x 5 mm Vertical F.G. Garcia AEM - PIP Report 07/01/2013

  11. PIP – Booster Activities

  12. BoosterUtilities Old Y-BE2 40+years old – beyond expected lifetime Oil-cooled transformer Questionable operation conditions for quite a while May/2012 investigation revealed noisy current output, over temperature operation conditions… Replaced with “old spare” ~ 1 year ago New Y-BE2 Installed May 17-18, 2013 Air-cooled transformer Remotely monitor & control Breakers are modular (smaller spare inventory) Improved monitoring (access to currents, voltages, harmonics ) F.G. Garcia AEM - PIP Report 07/01/2013

  13. Booster • Booster shielding assessment • Studies concerning beam loss profile and radiation measurement through penetrations were done • Discussions and data analysis underway • Booster Notcher • Progress with time in and commissioning 6 4.5 3 1.5 0 6 4.5 3 1.5 0 12T - $17 12T - $17 E12 E12 F.G. Garcia AEM - PIP Report 07/01/2013

  14. BoosterRF system • Cavities Refurbishment • 7of 19 cavities have been refurbished BRF 1,3,5,6,7,8,15 • BRF11 has issues with heating on the tuners • Need to be re-addressed for 15 Hz operations Booster Cavity Work Refurbished (15Hz) SS Prototype SS Upgraded Cavity Removed Stats: Last refurbishment :9.4 weeks <refurb.>last 3 cav. : 10.5 weeks Courtesy: K. Gollwitzer F.G. Garcia AEM - PIP Report 07/01/2013

More Related