1 / 41

Equipment design Ethylbenzene production by liquid phase

KUWAIT UNIVERSITYCOLLEGE OF ENGINEERING & PETROLEUMCHEMICAL ENGINEERING DEPARTMENT. Equipment design Ethylbenzene production by liquid phase. Done by: Mohammed Almohsen Supervised By: Prof. M. A. Fahim Eng. Yusuf Ismail. Distillation column:. Distillation T-101

Télécharger la présentation

Equipment design Ethylbenzene production by liquid phase

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. KUWAIT UNIVERSITYCOLLEGE OF ENGINEERING & PETROLEUMCHEMICAL ENGINEERING DEPARTMENT Equipment designEthylbenzene production by liquid phase • Done by: Mohammed Almohsen • Supervised By: • Prof. M. A. Fahim • Eng. Yusuf Ismail

  2. Distillation column: • Distillation T-101 • Separate and recycle Ethylbenzene

  3. COLUMN DIAMETER: LIQUID VAPOR FLOW FACTOR FOR TOP FOR BOTTOMS TAKE PLATE SPACING AS 0.6 M FROM FIGURE BASE K1 = 0.08TOP K1 = 0.12 CORRECTION FOR SURFACE TENSIONS BASE K1 = 0.066TOP K1 = 0.1078

  4. FLOODING VELOCITY: DESIGN FOR 85% FLOODING AT MAXIMUM FLOW RATE BASE TOP

  5. MAXIMUM VOLUMETRIC FLOW RATE BOTTOM TOP NET AREA REQUIRED: TAKING DOWNCOMER AREA AS 12 per cent OF TOTAL AREA COLUMN CROSS-SECTIONAL AREA COLUMN DIAMETER: USE SAME DIAMETER ABOVE AND BELOW FEED =6.328M=20.76FT

  6. COLUMN HEIGHT: Column height = (Number of stage * Plate spacing) + Column Diameter H = 27.9m =91.6 FT

  7. LIQUID FLOW PATTERN: MAXIMUM VOLUMETRIC LIQUID RATE FROM FIGURE DOUBLE PASS PLATE IS USED

  8. Column diameter = Column area = Downcomer area = Net area = Active area = Hole area = PROVISIONAL PLATE DESIGN:

  9. Take weir height = Hole diameter = Plate thickness = FROM FIGURE WEIR LENGTH ASSUME

  10. CHECK WEEPING: MAXIMUM LIQUID RATE TURNDOWN PERCENTAGE = 0.80 MINIMUM LIQUID RATE MAXIMUM WEIR CREST: MINIMUM WEIR CREST:

  11. AT MINIMUM RATE FROM FIGURE MINIMUM VAPOR VELOCITY THROUGH HOLE: ACTUAL MINIMUM VAPOR VELOCITY SO MINIMUM OPERATING RATE WILL BE ABOVE WEEP POINT.

  12. PLATE PRESSURE DROP: MAXIMUM VAPOR VELOCITY THROUGH HOLES Plate thickness / hole dia. = 1.25 FROM FIGURE DRY PLATE DROP RESIDUAL DROP TOTAL PLATE PRESSURE DROP

  13. DOWN COMER LIQUID BACK-UP: DOWNCOMER PRESSURE LOSS TAKE AREA UNDER APRON HEAD LOSS IN THE DOWNCOMER BACK-UP IN DOWNCOMER CHECK RESIDENCE TIME SATISFACTORY

  14. CHECK ENTRAINMENT FROM FIGURE ψ =0.013 , well below 0.1

  15. Angle subtended by the edge of the plate = 85 Mean length, unperforated edge strips =9.3136 Area of unperforated edge strips=0.4191 m Mean length of calming zone,approx =4.7738 Area of calming zones =0.4296 m Total area for perforations, Ap =23.0532 PERFORATED AREA: FROM FIGURE

  16. FROM FIGURE NUMBER OF HOLES: AREA OF ONE HOLE: NUMBER OF HOLES:

  17. AREA OF CONDENSER AREA OF REBOILER

  18. THICKNESS CALCULATIONS:

  19. SPECIFICATION SHEET OF BENZENE COLUMN T-101

  20. Column cost: Cost of tray =1,100$/trays Cost of trays = 52,800$ Cost of Vessel: Diameter outside=6m Volume outside=895 Volume inside=878 Volume of metal=17 Weight of metal=296,080lb Cost of vessel 2007 =547,200$ Vessel type: Large ,No Internals , Medium Cost of reboiler: Cost 2007 = 39,300$ Cost of condenser: Cost 2007 =19,800$ Total cost of without insulation=659,100$ Insulation cost = 52,728$ Total cost of T-101=711,828$ COST CALCULATIONS: FROM: WWW.MATCHE.COM

  21. Heat exchanger: • 3 heat exchanger has been designE-102 ,E103 and e-105. • The type of the 3 heat exchanger are shell and tube.

  22. TRY AND ERROR ASSUME BECAUSE THERE IS PHASE CHANGE Cooler E-102 detailed calculation: • Heat load: COOLING FLOW:

  23. TEMPERATURE CORRECTION FACTOR: CALCULATION: USING ONE SHELL PASS AND TWO TUBE PASSES FROM FIGURE

  24. ASSUME PROVISIONAL AREA: CHOOSE TUBE MATERIAL TO BE carbon steel WITH THE FOLLOWING PROPERTY OUTER DIAMETER Do = 25 MMINNER DIAMETER Di = 20 MMTUBE LENGTH = 4.88 M

  25. AREA OF ONE TUBE NUMBER OF TUBES Nt = provisinal area / area of one tube = 792.36 = 793 USING 1.25 TRIANGULAR PITCH

  26. TUBE BUNDLE DIAMETER: CONSTANT USING SPLIT RING FLOATING HEAD TYPE FROM FIGURE Bundle diametrical clearance = 71 mm Shell diameter =Bundle diameter+Bundle diametrical clearance =1037.13 mm=1.037

  27. TUBE-SIDE COEFFICIENT: METHOD 1 • Mean water temperature = • Tube cross sectional area = • Total flow area=Tubes per pass x Cross sectional area=

  28. Water mass velocity=mass flow rate/total flow area= • Water linear velocity Ut = mass velocity / density = • Inside coefficient for water hi:

  29. REYNALDO NUMBER • PRANDTL NUMBER TUBE-SIDE COEFFICIENT: METHOD 1I FROM FIGURE HEAT TRANSFER FACTOR

  30. INSIDE COEFFICIENT FOR WATER Hs:

  31. SHELL-SIDE COEFFICIENT: • Choose baffle spacing = • Tube pitch = • Cross flow area= • Mass velocity Gs= mass flow rate/cross flow area =

  32. Equivalent diameter for triangular arrangement • Mean shell side diameter temperature: • Reynaldo number • Prandtl number

  33. CHOOSE 25% BAFFLE CUT HEAT TRANSFER FACTOR FROM FIGURE

  34. OVERALL HEAT TRANSFER COEFFICIENT: • Thermal conductivity of steel = • Outside coefficient (fouling factor) = • Inside coefficient (fouling factor) = CLOSE TO INITIAL VALUE ASSUMED

  35. PRESSURE DROP: TUBE SIDE: FROM FIGURE HEAT TRANSFER FACTOR

  36. SHELL SIDE: Linear velocity = FROM FIGURE

  37. SHELL THICKNESS CALCULATIONS:

  38. Cost Calculations: • From www.matche.com • Heat transfer area = 3,269ft2 • Exchanger Type: Carbon steel • Internal Pressure: 450 psi • Cost with out insulation: 110,900$ • Insulation cost: 8,872$ • Final cost 2007:119,772$

More Related