1 / 19

PJM/MISO Update on CO-114

PJM/MISO Update on CO-114. Frank Koza – PJM Dave Zwergel – Midwest ISO. CO 114 Behavior. TLR results on PJM Coordinated Flowgates have been questionable since AEP and DPL joined PJM

kamal
Télécharger la présentation

PJM/MISO Update on CO-114

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PJM/MISO Update on CO-114 Frank Koza – PJM Dave Zwergel – Midwest ISO 1

  2. CO 114 Behavior • TLR results on PJM Coordinated Flowgates have been questionable since AEP and DPL joined PJM • Calculations produce “unrealistically excessive flow” across all priorities (7-Firm, 6-Non-Firm Network, and 2-Hourly) • PJM flows have often increased tenfold • Results add uncertainty to operations • How much is relief should I ask for? • How much is relief will I get? 2

  3. Examples PJM Impact Based on Distribution Factors calculated with PSS/e MUST and Generator Output from Jan 5, 2005 101 Kammer #8 xfmr l/o Kammer-South Canton 765 kV line Flowgate Limit is 3695 3

  4. Examples PJM Impact Based on Distribution Factors calculated with PSS/e MUST and Generator Output from Jan 5, 2005 1719 Mt. Storm-Doubs 500/Mt. Storm-Meadow Brook 500 Flowgate Limit is 2598 4

  5. Examples PJM Impact Based on Distribution Factors calculated with PSS/e MUST and Generator Output from Jan 5, 2005 2337 Cook-Palisades345/BentnHrbr-Palisades345 Flowgate Limit is 2094 5

  6. Results and Consequences RCs may have to request much more relief than is actually necessary to effect curtailments RCs may believe flows represent available relief, when in fact, the flows are reported erroneously and no relief is available Operator Flow Change Request: -1500 MW 6

  7. Analysis • Since the RTO is responsible for calculating Market Flow, PJM and MISO jointly investigated the discrepancies to find the cause • Assumptions hid an inequality in the basic calculation mechanism • Testing was done with generators at the same output levels, but shifts in output levels would have demonstrated the inequality • Load Shift Factor aggregations must be consistent between pre- and post-expansion models • Since CE joined PJM as a separate Control Area, problem remained hidden until AEP and DPL joined and the LSFs were merged 7

  8. Historic Footprint Gen 1 1100 MW Output GSF = 0.10 Gen 2 900 MW Output GSF = -0.20 Load 2 1000 MW Demand LSF = -0.30 Load 1 1000 MW Demand LSF = -0.20 Control Area 1 Control Area 2 Flowgate X PTP Tag would be 100MW * (.10 – (-.20)) = 30MW 8

  9. Merged Gen 1 1100 MW Output GSF = 0.10 Gen 2 900 MW Output GSF = -0.20 Load 2 1000 MW Demand LSF = -0.30 Load 1 1000 MW Demand LSF = -0.20 Control Zone 1 New Control Area Control Zone 2 Flowgate X No Point to Point Tag (becomes internalized) 9

  10. Comparison Plus Point to Point Impact 10

  11. Solution • Considered multiple solutions • Threshold change • Netting • Partial netting • Best Solution Found • RTOs use load shift factors similar to those used in the firm usage calculation • Control Zone impacts will be determined as if Historic CAs remain in place (GLDF = GSF – Historic LSF) • Inter-Zone Transfer Impacts will be determined as if Historic CAs remain in place (Xfer TDF = Historic TDF – Historic TDF) • Generation in a Zone in excess of Zone Load will be considered transfer MW (but sum of all Zonal Gen + Transfer Gen will not exceed RTO Load) • Market flow values will regain accuracy consistent with firm usage 11

  12. Solution Step 1 Gen 1 1100 MW Output GSF = 0.10 Gen 2 900 MW Output GSF = -0.20 Load 2 1000 MW Demand LSF = -0.30 Load 1 1000 MW Demand LSF = -0.20 Control Area 1 New Control Area Control Area 2 Flowgate X Calculate GTL Impacts as if Historic Footprint still existed 12

  13. Solution Step 2 Gen 1 1100 MW Output GSF = 0.10 Gen 2 900 MW Output GSF = -0.20 Load 2 1000 MW Demand LSF = -0.30 Load 1 1000 MW Demand LSF = -0.20 Control Area 1 New Control Area Control Area 2 Flowgate X Calculate PTP Impacts of Transferring Excess MW 13

  14. Comparison Plus Point to Point Impact 14

  15. New vs. Old Process PJM Impact Based on Distribution Factors calculated with PSS/e MUST and Generator Output from Jan 5, 2005 101 Kammer #8 xfmr l/o Kammer-South Canton 765 kV line Moderate Increase in Flows 15

  16. New vs. Old Process PJM Impact Based on Distribution Factors calculated with PSS/e MUST and Generator Output from Jan 5, 2005 1719 Mt. Storm-Doubs 500/Mt. Storm-Meadow Brook 500 Mild Increase in Flows Some Firm became Non-Firm 16

  17. New vs. Old Process PJM Impact Based on Distribution Factors calculated with PSS/e MUST and Generator Output from Jan 5, 2005 2337 Cook-Palisades345/BentnHrbr-Palisades345 Moderate Increase in Flows 17

  18. Questions? 18

  19. ReferenceMathematical Explanation of Inequality 19

More Related