1 / 17

Florida Power & Light 2006 Hurricane Preparedness Plan June 5, 2006

Florida Power & Light 2006 Hurricane Preparedness Plan June 5, 2006. Presented by: Geisha Williams. Florida Power & Light 2004 - 2005 Record Breaking Storm Seasons. 2004 was unprecedented 3 back-to-back storms within 36 days Nearly 47,000 workers from 39 states and Canada

kamali
Télécharger la présentation

Florida Power & Light 2006 Hurricane Preparedness Plan June 5, 2006

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Florida Power & Light2006 Hurricane Preparedness PlanJune 5, 2006 Presented by: Geisha Williams

  2. Florida Power & Light2004 - 2005 Record Breaking Storm Seasons • 2004 was unprecedented • 3 back-to-back storms within 36 days • Nearly 47,000 workers from 39 states and Canada • 2005 is most active and destructive season on record • 4 hurricanes affected customers • Nearly 45,500 workers from 36 states and Canada • Wilma alone had the largest impact to our infrastructure • Largest workforce ever assembled • Quickest deployment to the field after a major hurricane • Significant impact on electrical infrastructure 2004 2005

  3. Florida Power & Light2005 Storm Season Review - Lessons Learned • Infrastructure “hardening” is needed in the design, construction and operation of electric systems • Evidence of more active multi-decade hurricane cycle • Growing customer base within territory • Customer expectations higher • Storm Secure Plan developed to strengthen electrical grid for future hurricanes

  4. Florida Power & LightPreparing for Storm Season 2006 and Beyond • Strengthen system infrastructure to improve resiliency to future storms and complete repairs from 2005 storm season • Prepare storm organization with the appropriate training and skills to respond to storms • Test and refine the restoration plan • Build upon current communication processes with customers and communities Infrastructure Organizational Communication Restoration

  5. Florida Power & LightInfrastructure - ~ Storm Follow-up Transmission System Infrastructure Communication Organizational • 500 kV Transmission Lines • Completed inspections on all 500 kV structures (~4,600) • Inspected 100% of structures both from ground and air • All cross-brace structural bolts present and tight • Identified work prioritized, scheduled & executed as planned • Conservation-Corbett 500 kV • Rebuilt 7 circuit miles : In-Service • Installed new vibration dampening system • Detailed follow-up on entire line • All bolts tightened • Threads peened on all cross-brace & cross-arm bolts • Post-construction visual inspections completed May 2006 • No problems reported Restoration

  6. Florida Power & LightInfrastructure ~ Storm Follow-up Transmission System Infrastructure Organizational Communication • Transmission Lines (230 kV and Below) • Completed storm repairs on Transmission & Substation facilities impacted by 2005 storms • Inspected 100% of transmission structures in storm impacted areas • Completed ground / visual inspections on all structures on critical bulk & generation transmission lines • Continued routine climbing / bucket inspections • Inspection follow-up work prioritizedand scheduled • Completed all critical structural work Restoration

  7. Infrastructure Organizational Communication Restoration Florida Power & LightInfrastructure ~ Storm Follow-up Distribution System • Patrolled 100% of feeder and lateral lines in storm affectedareas • 17,000 circuit miles patrolled • Follow-up work identified completed April 30th • Summary of Repairs • 1,500 leaning poles replaced or repaired • 1,000 conductor locations addressed • 108,300 streetlight locations repaired • 17,800 Down guys repaired • 28,000 other repairs – i.e. arrestors, insulators • 3,100 Bellsouth facility pole transfers

  8. Florida Power & LightInfrastructure ~ Vegetation Management Infrastructure Organizational Communication • Transmission System • Completed 100% vegetation patrol on entire system • Completed 100% of vegetation work identified • All identified dead and/or dying trees removed • Distribution System • Patrolled 100% of feeder lines in affected areas and removed dead or dying trees • Accelerated vegetation management and line clearance strategy • Completed clearing circuits serving top critical infrastructure • 75% of planned feeder lines to be cleared by peak of storm season Restoration

  9. Infrastructure Organizational Communication Restoration Florida Power & LightInfrastructure ~ Build to Extreme Wind Standards • Proposed adoption of NESC extreme wind criteria • Apply zonal extreme wind criteria within territory • Develop new distribution and construction standards and guidelines • Targeted hardening projects have begun and will be completed in time for 2006 storm season • Focus on Critical Infrastructure Functions (CIF’s) 130 140 150 NESC Extreme Wind Map

  10. Infrastructure Organizational Communication Restoration Florida Power & LightInfrastructure ~ 2006 Distribution Hardening Projects • Critical Infrastructure Functions (CIF) provide for public health, safety, welfare and security • Two South Florida ports • Port Everglades • Port of Palm Beach • Several South Florida hospitals • Jackson / UM Hospital Complex • Mt Sinai / Miami Heart • Saint Mary’s Medical Center FPL supplies Port Everglades with electricity to distribute the petroleum that supplies nearly one-fifth of Florida’s energy requirements Jackson/University of Miami Hospital Complex St. Mary’s Medical Center Mt. Sinai and Miami Heart Institute Port of Palm Beach

  11. Florida Power & LightInfrastructure ~ 2006 Transmission Hardening Projects Infrastructure Organizational Communication • Hardened Transmission infrastructure in conjunctionwith Distribution CIF Hardening Projects • Accelerated planned single pole un-guyed wood pole replacements • ~230 structures replaced in time for 2006 storm season • Completed ceramic post insulator replacements on 8 line sections Restoration

  12. Florida Power & LightInfrastructure ~ Pole Inspections Infrastructure Organizational Communication • Transmission System • ~64,000 transmission structures • Enhancing current Climbing Inspection Program • Six Year Inspection Cycle • Approx. 10,700 structures annually • Distribution • 1.1 million distribution poles • Building on current three-pronged inspection approach • Eight year cycle • Approx. 130,000 poles annually • Working in all areas each year • Collaborating with joint use poleowners for efficiency Restoration Zone 1 Zone 2 Zone 3 Zone 9 Zone 4 Zone 5 Zone 8 Zone 6 Zone 7

  13. Infrastructure Communication Organizational Restoration Florida Power & LightStorm Organization • Modular Storm Organization Structure developed to adapt to specific needs required for different storm scenarios • Storm roles and key personnel are identified to staff the storm organization • Storm training programs have been completed • Dry Run held to exercise restoration process and test enhancements

  14. Florida Power & LightRestoration Plan Infrastructure Organizational Communication • Safely restore power to top Critical Infrastructure Functions while also restoring the greatest number of customers in the shortest time • Plans and process scaledto match the storm • Logistical Support and resources secured and ready • 66 staging site agreements • Selected sites pre-wired with T-1 • Material inventory increasedpre-storm • Nearly 2 million gallons of fuel at hand • 19 dedicated fuel Supply/Servicecontracts Restoration

  15. Florida Power & LightRestoration Plan Infrastructure Organizational Communication • Mutual assistance agreements and vendor contracts and commitments secured • Utility restoration support agreements through EEI and SEE • Agreements with line and vegetationcontractors throughout the US • Critical Infrastructure Functions identified • Top restoration priorities within eachcommunity identified • System capabilities to support restoration efforts enhanced • Damage assessment modeling tool updatedwith additional information • Outage management support systems integrated with customer communications systems Restoration

  16. Florida Power & LightCommunication Infrastructure Organizational Communication • EOC Partners • Personnel assigned to County EOC’s • Dedicated web page • Customer Communications • Increased customer call capacity • Added Care Center redundancy • El Paso, Texas Call Center • Outbound calls to customers • Capability to report and checkstatus of outages on-line • Crisis Information Team • Consistent and timely information regarding restoration efforts centrally overseen • Emerging customer and community issues proactively addressed • Estimated Times of Restoration • System • County • Sub-County Restoration

  17. Florida Power & Light CompanyPrepared for Storm Season 2006 & Beyond • Infrastructure repaired; strengthened for future storms • Improves resiliency • Reduces outages during storms • Storm organization prepared • Training complete • Personnel knowledgeable and experienced • Resources ready to deploy • Restoration plan ready • Logistical Support and resources secured and ready • Material and Fuel Inventory on hand • Mutual Assistance agreements in place • Communication processes in place • Better accessibility of information • Quicker communication of information

More Related