Project objectives

Project objectives. 4 main objectives Increase MV/LV PV integration thanks to a “Network Energy Manager” Study and model customers response Operate a pocket of LV network on an Islanding mode Study business models 2 key features Project based on ERDF Linky smart meter architecture

kameko-mack
Télécharger la présentation

Project objectives

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project objectives • 4 main objectives • Increase MV/LV PV integration thanks to a “Network Energy Manager” • Study and model customers response • Operate a pocket of LV network on an Islanding mode • Study business models • 2 key features • Project based on ERDF Linky smart meter architecture • 3 levels of electricity storage

  2. Nice Grid Facts and Figures AVIGNON CARROS NICE 400 kV line MARSEILLE Site description TOULON • Carros located in SouthernFrance, in an“electricalpeninsula” • 10 500 inhabitants, with residential and industrial areas • Already1,8MWpof solar PV • Single400kVlinesupplying the area • 88secondary substations • 20MWpeak load Use cases • Optimize massive PV integration in the distribution grid • Testislandingwithin a low voltage district • Test 3.5MWload shedding within the city of Carros • Incentivizeprosumerbehavior

  3. Nice Grid Use Cases on a map PV Area 550 Linkyclients 150 kWp installed Cailletiers Islanding area 12 Industrial clients 420 kWp installed Pesquier Colombie Customer Behavior : 2600 Linkyclients Rosemarines Battery locations Lou Souleou Plaine 1 Docks Trachel

  4. Flexible Load Management Power Consumption PV generation • Traditional Generation / Consumption curves • Generation / Consumption curves with flexible load management Time Load shifting Power Flexibilities - + Time

  5. Nice Grid Batteries Sept. 2014 4 kW / 4 kWh 1 MW / 560 kWh Dec. 2013 250 kW / 620 kWh 33 kW / 106kWh Nov. 2014 Oct. 2014

  6. Nice Grid Architecture AGREGATOR B2B Flexibility requests Bids Optimization and management TRANSMISSION SYSTEM OPERATOR DEMAND RESPONSE REQUESTS NETWORK ENERGY MANAGER (NEM) AGREGATOR B2C CONSUMPTION FORECASTS D-1 NETWORK AGREGATOR GENERATION FORECASTS D-1 www.grid4eu.eu

  7. Load shifting Average power consumption and generation in Watts • +2300 Whconsumption per client between 12 PM and 4 PM • - 1000 Whconsumption per client on previous off-peak block (no electrical boiler start) • -1100Wh consumption during on-peak time (appliances shifting) • +200Wh consumption in total per client Average power consumption on 21 clients with solar off-peak hours Average reference power consumption for the 21 clients Average PV generation for 40 PV generators Source: ERDF, EDF R&D www.grid4eu.eu

  8. The Nice Grid Consortium • Leaders • Participants • Academics, R&D • Sponsors, Local Authorities