An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The Calvert Hall High School College Project John Graef Architectural Engineering Senior Thesis – Construction Management

  2. Project Outline Project Description Project Overview Primary Project Team Architecture 4D modeling Introduction Methodology Summary Safety plan Introduction Methodology Summary LEED Design What is LEED Point Selection Results Conclusion Question Project Overview • Location: Baltimore Maryland • Building Function: High School • Size 40,000 SQ FT • Construction Dates: July 2003-September 2004 • Construction Method – Design-Bid-Build

  3. Project Outline Project Description Project Overview Primary Project Team Architecture 4D modeling Introduction Methodology Summary Safety plan Introduction Methodology Summary LEED Design What is LEED Point Selection Results Conclusion Questions Primary Project Team • Construction Manager – Struever Bros. Eccles & Rouse • Architect – Gaudreau Inc • Engineers – Century Engineering • Owner – The Calvert Hall College

  4. Project Outline Project Description Project Overview Primary Project Team Architecture 4D modeling Introduction Methodology Summary Safety plan Introduction Methodology Summary LEED Design What is LEED Point Selection Results Conclusion Questions Architecture The New Academic Building is an new addition to The Calvert Hall High School. This building has an unusual shape which will create a unique construction project. The new addition brings the high school campus together

  5. Project Outline Project Description Project Overview Primary Project Team Architecture 4D modeling Introduction Methodology Summary Safety plan Introduction Methodology Summary LEED Design What is LEED Point Selection Results Conclusion Questions 3D & 4D Modeling Depth 3D AutoCAD and 4D-modeling

  6. Project Outline Project Description Project Overview Primary Project Team Architecture 4D modeling Introduction Methodology Summary Safety plan Introduction Methodology Summary LEED Design What is LEED Point Selection Results Conclusion Questions 3D & 4D Modeling Research The effectiveness of 3D AutoCAD and 4D modeling Application Create a 4D model of the Calvert Hall Project

  7. Project Outline Project Description Project Overview Primary Project Team Architecture 4D modeling Introduction Methodology Summary Safety plan Introduction Methodology Summary LEED Design What is LEED Point Selection Results Conclusion Questions 4D Modeling Methodology 3D Model Calvert Hall model based on • Foundation • Column • I-Beam • Concrete Floor • Outside Wall • Roof

  8. Project Outline Project Description Project Overview Primary Project Team Architecture 4D modeling Introduction Methodology Summary Safety plan Introduction Methodology Summary LEED Design What is LEED Point Selection Results Conclusion Questions 4D Modeling Methodology Creating the Schedule • The schedule is based on 64 different construction activities • Creating a schedule can be a back and fourth process • A top priority is to control dangerous activities so that they do not overlap • Any mistakes in the schedule is easily seen with a 4D model

  9. Project Outline Project Description Project Overview Primary Project Team Architecture 4D modeling Introduction Methodology Summary Safety plan Introduction Methodology Summary LEED Design What is LEED Point Selection Results Conclusion Questions 4D Modeling Methodology

  10. X Project Outline Project Description Project Overview Primary Project Team Architecture 4D modeling Introduction Methodology Summary Safety plan Introduction Methodology Summary LEED Design What is LEED Point Selection Results Conclusion Questions 4D Modeling Methodology Hard to Read Even Harder to Check

  11. Project Outline Project Description Project Overview Primary Project Team Architecture 4D modeling Introduction Methodology Summary Safety plan Introduction Methodology Summary LEED Design What is LEED Point Selection Results Conclusion Questions 4D Modeling Methodology Construction a 4D model Using the program Common Point

  12. Project Outline Project Description Project Overview Primary Project Team Architecture 4D modeling Introduction Methodology Summary Safety plan Introduction Methodology Summary LEED Design What is LEED Point Selection Results Conclusion Questions 4D Modeling Methodology Construction a 4D model Using the program Common Point

  13. Project Outline Project Description Project Overview Primary Project Team Architecture 4D modeling Introduction Methodology Summary Safety plan Introduction Methodology Summary LEED Design What is LEED Point Selection Results Conclusion Questions 4D Modeling - Summary Lessons Learned • A 3-D model can be time consuming to create • With Common Point a 4D model can be produced quickly • A 4D model can ‘point-out’ mistakes in the schedule • Construction safety coordination issues will pop-out in a 4D model

  14. Project Outline Project Description Project Overview Primary Project Team Architecture 4D modeling Introduction Methodology Summary Safety plan Introduction Methodology Summary LEED Design What is LEED Point Selection Results Conclusion Questions Safety Plan Introduction Breath Calvert Hall Safety Program

  15. Project Outline Project Description Project Overview Primary Project Team Architecture 4D modeling Introduction Methodology Summary Safety plan Introduction Methodology Summary LEED Design What is LEED Point Selection Results Conclusion Questions Safety Plan Introduction Research Common dangers related to construction Application Create a Safety program out-line based on findings

  16. Project Outline Project Description Project Overview Primary Project Team Architecture 4D modeling Introduction Methodology Summary Safety plan Introduction Methodology Summary LEED Design What is LEED Point Selection Results Conclusion Questions Safety Plan Methodology The four main causes of construction injuries • Falling • Stuck by • Caught in/between • Electrocuted

  17. Project Outline Project Description Project Overview Primary Project Team Architecture 4D modeling Introduction Methodology Summary Safety plan Introduction Methodology Summary LEED Design What is LEED Point Selection Results Conclusion Questions Safety Plan Methodology Safety Out-Line based on • Safety Management • Cranes • Electrical Safety • Excavation • Fall Protection • Construction Equipment • Scaffolds • Stairways

  18. Project Outline Project Description Project Overview Primary Project Team Architecture 4D modeling Introduction Methodology Summary Safety plan Introduction Methodology Summary LEED Design What is LEED Point Selection Results Conclusion Questions Safety Plan Methodology • The most important aspect to a successful safety program is good management • Engineering controls can be put in place to insure safety on the work-site • The price of a direct cost can be small compared to the indirect cost

  19. Project Outline Project Description Project Overview Primary Project Team Architecture 4D modeling Introduction Methodology Summary Safety plan Introduction Methodology Summary LEED Design What is LEED Point Selection Results Conclusion Questions Safety Plan Methodology Direct cost vs. Indirect cost OSHA's Ratio of Indirect to Direct

  20. Project Outline Project Description Project Overview Primary Project Team Architecture 4D modeling Introduction Methodology Summary Safety plan Introduction Methodology Summary LEED Design What is LEED Point Selection Results Conclusion Questions Safety Plan - Summary • Construction is an hazardous occupation • Proper safety programs can strongly reduce work-related injuries • A good safety program requires proper leadership and a good management team • The most important thing is that everyone gets to go home

  21. Project Outline Project Description Project Overview Primary Project Team Architecture 4D modeling Introduction Methodology Summary Safety plan Introduction Methodology Summary LEED Design What is LEED Point Selection Results Conclusion Questions Safety Plan - Summary Breath LEED Design

  22. Project Outline Project Description Project Overview Primary Project Team Architecture 4D modeling Introduction Methodology Summary Safety plan Introduction Methodology Summary LEED Design What is LEED Point Selection Results Conclusion Questions LEEDDesignWhat is LEED LEED (Leadership in Energy and Environmental Design) • LEED is a organization that set standards or regulations for building a sustainable design LEED focuses on Sustainable Design Water Efficiency Energy & Atmosphere Materials & Resources Indoor Environment Quality Innovation & Design Process

  23. Project Outline Project Description Project Overview Primary Project Team Architecture 4D modeling Introduction Methodology Summary Safety plan Introduction Methodology Summary LEED Design What is LEED Point Selection Results Conclusion Questions LEED DesignPoint Selection LEED rated point system LEED Certified: 26-32 Silver: 33-38 Gold: 39-51 Platinum: 52-69

  24. Project Outline Project Description Project Overview Primary Project Team Architecture 4D modeling Introduction Methodology Summary Safety plan Introduction Methodology Summary LEED Design What is LEED Point Selection Results Conclusion Questions LEED DesignPoint Selection LEED rated point system LEED Certified: 26-32 Silver: 33-38 Gold: 39-51 Platinum: 52-69

  25. Project Outline Project Description Project Overview Primary Project Team Architecture 4D modeling Introduction Methodology Summary Safety plan Introduction Methodology Summary LEED Design What is LEED Point Selection Results Conclusion Questions LEED DesignPoint Selection LEED rated point system LEED analysis Yes 31 ? 24 No 14

  26. Project Outline Project Description Project Overview Primary Project Team Architecture 4D modeling Introduction Methodology Summary Safety plan Introduction Methodology Summary LEED Design What is LEED Point Selection Results Conclusion Questions LEED DesignPoint Selection LEED rated point system 31 points are possible points for the Calvert Hall Project. Either because the original design qualified for a point or the point was cheap to attain 24 points that I am unable to determine. Either because measurements are needed or research is required that is outside my expertise 14 points I considered to expense to obtain due to the current design and function

  27. Project Outline Project Description Project Overview Primary Project Team Architecture 4D modeling Introduction Methodology Summary Safety plan Introduction Methodology Summary LEED Design What is LEED Point Selection Results Conclusion Questions LEED DesignResults • 31 points will qualify the Calvert Hall project to become a LEED certified building • A total of 17 out of 69 points are due directly to construction

  28. Project Outline Project Description Project Overview Primary Project Team Architecture 4D modeling Introduction Methodology Summary Safety plan Introduction Methodology Summary LEED Design What is LEED Point Selection Results Conclusion Questions LEED DesignResults Summary • The Calvert Hall Project could become a LEED certified building • The construction company is a important aspect to LEED rated design

  29. Project Outline Project Description Project Overview Primary Project Team Architecture 4D modeling Introduction Methodology Summary Safety plan Introduction Methodology Summary LEED Design What is LEED Point Selection Results Conclusion Questions Conclusion 4D modeling • Is an effective tool for many different aspects of construction Safety plan • A proper safety plan is essential for the well-being of the occupants at the jobsite LEED design • Calvert Hall Project could become LEED certified

  30. Project Outline Project Description Project Overview Primary Project Team Architecture 4D modeling Introduction Methodology Summary Safety plan Introduction Methodology Summary LEED Design What is LEED Point Selection Results Conclusion Questions Questions