1 / 15

Gas system controls for LHC experiments

Gas system controls for LHC experiments. Outline. Introduction to the common gas system approach of the four experiments. Gas Control Project [soft+hardware] Prototypes of gas hardware and gas control systems Conclusions. Introduction.

Télécharger la présentation

Gas system controls for LHC experiments

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Gas systemcontrols for LHC experiments S. Haider / GWG

  2. Outline Introduction to the common gas system approach of the four experiments. Gas Control Project [soft+hardware] Prototypes of gas hardware and gas control systems Conclusions S. Haider / GWG

  3. Introduction • The Gas Working Group (GWG) was founded 1995 with the mandate of providing the four LHC experiments with scalable standard designs as far as possible and to bring forward proven and costed solutions. • In the CERN hierarchy, the GWG is based in EP - TA1 - Gas section (F.Hahn). • Each experiment is represented via a contact person. For ALICE Ray Gregory. • He brings all user requirements to the GWG • he organizes meetings between GWG and sub-detector experts • he organizes the collection of all relevant data for the TDR S. Haider / GWG

  4. Working philosophy of GWG • meet the sub-detector experts and capture as many requirements as possible • propose a gas system layout with an initial cost estimate • re-iterate (several times if necessary) with experts and write the Technical Design Report • repeat the exercise after some time with much more depth and proceed to Engineering Design Report. S. Haider / GWG

  5. Status TDR: Technical Design Report EDR: Engineering Design Report S. Haider / GWG

  6. Advantages of a common approach for ALICE • With the large similarities of the gas hardware and software design, one saves enormously resources: • by lack of duplication, • by standardized construction and implementation procedures, • and most importantly bylong-term maintainability of ALL gas systems at LHC. • Due to the larger amount of equipment that has to be ordered, manufacturers often agree to substantial price reductions which, overall, brings the total costs of all gas system down. S. Haider / GWG

  7. Gas Controls • Gas control will be handled by the GWG since detector security crucially depends on smooth interaction between gas hardware and control software. • The GWG fully complies to the Joint COntrol Project (JCOP) of the four LHC experiment, in particular to the: • basic idea of ONE common SCADA product, • the working philosophy of User Requirement Document (URD) before writing code • and the so-called “Framework”, which provides similar control philosophies throughout the LHC experiments. S. Haider / GWG

  8. The GWG has finished the first URD analysis in collaboration with IT/CO. Version 1.0 available. The final version will include also the Human Machine Interface (panels etc..) • this URD follows the industrial software production standard PSS05 (ESA) • split the gas systems in functional modules: mixer, purifier, pump, distribution etc.. • Capture as many functional requirements as possible: States, commands, interlocks, events, alarms, messages etc.. S. Haider / GWG

  9. Software development User Requirement Document Engineering Phase Implementation phase Testing phase Commissioning Phase S. Haider / GWG

  10. Software development (cont.) • Reuse a Software Library from the LHC Cryogenics Group, the UNICOSlibrary: • cryogenics has VERY similar requirements towards equipment: • ie. Analog and On/Off valves • PID loop controllers • flow meters and pressure transmitters • etc... • We can use this library free of charge (costs the cryo group some 2-3 Man-years of software development) • First used for NA60 Gas system (later more). S. Haider / GWG

  11. Control Hardware Architecture ALICE gas systems PC TOF HMPID TPC TRD CPC TRD TOP gas control PLC Pump Distribution Analysis Purifier Mixer Rack 1 Rack 2 ProfiBUS Rack 10 Valve MFC Flowmeter Gas equipment Manometer S. Haider / GWG

  12. Parameters for rack #10 (i.e.) Input pressure: HIHI=+10mbar HI = +9 mbar LO = +4 mbar LOLO = +3 mbar Output pressure: HIHI = +5mbar HI = +4 mbar LO = +0.5 mbar LOLO = -0.5 mbar Leakrate measurement: HIHI = 20% output - input flow HI = 18% Pressure regulation : setpoint = +3.5 mbar PID parameter : P = 300 I = 0.12 D = 0.0 etc. etc Buttons on screen: RUN state: Upload Recipe Make Recipe def. Change Recipe Save Recipe Load Recipe Download Recipe The parameter list in a module is called “Recipe” !! S. Haider / GWG

  13. Prototypes • Distribution prototype for closed loop systems with several distribution racks • ALICE CPC mixer with digital mass flow controllers (FlowBUS from Bronkhorst) • LHCb 2 mixer stations with digital MFCs on ProfiBUS • ATLAS TRT, MDT • CMS MSGC, CSC... S. Haider / GWG

  14. NA60 Gas system • Final control hardware and software: • Schneider PLC used • PLC program utilizes the UNICOS library • Mixer URD used to produce PLC program. • 3 gasses and 1 liquid are mixed. Mixture is flammable • distribution rack features: • final gas distribution manifold with integrated needle valve, flow-meter and quick-connector for each channel • input and output flows are measured. • Flow-meters are read by micro-PLC from Wago S. Haider / GWG

  15. Conclusions • The analysis of the gas systems for LHC experiments has shown that a common approach is possible • The first step of the software development cycle, the User Requirement Document, is finished. First version is available. • With NA60 we have gone through the entire development cycle and produced a full gas control system for a mixer and a distribution system. The final control hardware and the PSS05 software production standard were tested and gave adequate results in view of the production of the LHC gas systems. S. Haider / GWG

More Related