1 / 17

Impact of on energy saving

T echnical S ustainable M anagement Egyptian Approach to Raising Management Standards in the Water Sector Case study. Impact of on energy saving . Eng : Fayez Badr fayez.badr@giz.de # 01229007111 senior advisor Water and wastewater management programm (WWMP)

keelty
Télécharger la présentation

Impact of on energy saving

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Technical Sustainable Management Egyptian Approach to Raising Management Standards in the Water Sector Case study Impact of onenergy saving Eng: Fayez Badr fayez.badr@giz.de # 01229007111 senior advisor Water and wastewater management programm (WWMP) Giz-Egypt 8 May 2014

  2. Definition of Technical sustainable management program(TSMegypt) It is an Egyptian programm aims to enhance water services to reach to the international standard • Definition of Neighborhood day : • It is a forum for the stakeholders of the TSMEgyptfacilities to discuss challenges,and knowledge transfer • This programm highlighted energy saving of O&M cost

  3. Case studies on energy saving as an impact of TSM-Egypt certificate 1- Balaqse WWTP 2- QahaWWTP

  4. 1- Balaqs WWTP Basic data Location: Cairo-Egypt Area:85 Acr Design flow:600.000m3/d Treatment technology: conventional activated sludge Year of operation :1992 Year of certification: 2011 Power factor: 0.83

  5. Impact of installation of power factor capacitors bank • 1-Claim of power factor • The annual power factor penalty = 150.000€ • total claims in 14 year =150.000×14=2.100.000 € • 2- Saving calculation: • Installation cost of the capacitors bank =500.000 € • Life time of the capacitors bank =14 year • Annual penalty =150.000 € • Pay pack = 3.3 year • Annual saving in 14 year = • 2.100.000-500.000÷14=114.000 €

  6. Power factor before and after installation of capacitors

  7. Max demand • Definition • it is a penalty add to the monthly electrical bill If the • facility consumed electricity more than the contracted power • Measurement • The electric company install peak load meter, to measure it • the potentiometerof the meter moves after 15 min of consumption to be add for the next extra Contracted consumption.

  8. Max demand • Calculation • Momentaryconsumption considers as an annual consumption not momentary consumption. • penelty • cost of the contracted KW= 0.29 pound • Cost of KW=21 pound • i.e. 72 times

  9. Peak load meter

  10. Impact of TSM-Egypt certificate on power saving • Balaqs WWTP get rid of the annual max demand penalty which was 50.000 €/year after application of the following programms: • SOPs through: • Pumps operation • Operate the electric generator during peak load period • Apply an Interactiveoperational plan of the electrical equipment. • Apply routine maintenance plan • Training

  11. 1- QAHA WWTP Basic data Location: Qaluobya -Egypt Area:6 Acre Design flow:10.000m3/d Actual flow :4500 m3/d Treatment technology: activated sludge (extended aeration-Kruger technology ) Year of operation :2004 Year of certification: under citification

  12. Plant Lay out

  13. Impact of modification of operation plan • The plant have two trains, both of them was in service although • it is receives half of the design flow • Action: • Stop one of the trains to be a stand by • Component of the train • 4 rotating brushes -45 Kw/each • Beside modify the operating time of the RAS& WAS pumps • from 12 hour to 8 hour /day

  14. Electric Power bills analysis