NCTD/SANDAG Project Update Capital Improvement Program

RELATED TO AGENDA ITEM W1. NCTD/SANDAG Project Update Capital Improvement Program. Bill Prey, P.E., LOSSAN Corridor Director San Diego Association of Governments. Current Rail Projects. 19 projects now in development 11 funded through construction $ 467 million in funding

keiji
Télécharger la présentation

NCTD/SANDAG Project Update Capital Improvement Program

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. RELATED TO AGENDA ITEM W1 NCTD/SANDAG Project UpdateCapital Improvement Program Bill Prey, P.E., LOSSAN Corridor Director San Diego Association of Governments

  2. Current Rail Projects • 19 projects now in development • 11 funded through construction • $467 million in funding • $915 million estimate cost at completion • Schedule currently funded through 2016

  3. North Coast Corridor Program

  4. In Design: Batiquitos Lagoon Double Track Batiquitos Lagoon Double Track $3 million Funded through preliminary engineering 2.7 miles of second track Anticipated to reach 60% design Feb. 2015

  5. In Design: Elvira to Morena & SD River Bridge Elvira to Morena Double Track $78.7 million 2 miles of second track in City of San Diego Construction start 2015 San Diego River Bridge $9.4 million Realignment of bridge 0.9 miles of second track San Diego River Bridge Elvira to Morena

  6. Near Construction: Sorrento Valley Double Track Sorrento Valley Double Track North of Sorrento Valley Station $34 million 1 mile of second track Construction startLate 2013/Early 2014 Sorrento Valley Double Track

  7. Near Construction: San Onofre Double Track San Onofre to Pulgas Double Track Camp Pendleton area Longest stretch of double track 4.2 miles $38 million Construction start Fall 2013

  8. Near Construction: Los Peñasquitos Lagoon Los PeñasquitosLagoon Bridge Project $25 million Recipient of $14 million TIGER grant from US DOT 4 wooden bridges to be replaced with concrete bridges Construction begins mid-2014 for one year

  9. Near Construction: Oceanside Transit Center Platform Improvement Project $19.5 million Add third track and new platform Constructionstart TBD Level boarding considerations Oceanside Transit Center

  10. In Construction: Santa Margarita River Bridge Santa Margarita River Bridge North of Oceanside $41 million 0.8 miles Deck now replaced Est. completion April 2014 Sorrento to Miramar 1 Tecolote Crossover

  11. In Construction: Sorrento to Miramar Phase 1 Sorrento to Miramar Double Track Phase 1 South of Sorrento Valley Station $44 million 1.4 miles Estimated completion January 2014

  12. Near Completion: Tecolote/Washington Crossovers Tecolote/Washington Street Crossovers Facilitates trains passing north of Downtown San Diego $11 million Tecolote: Completed September 2013 Washington: Completion slated in October 2013 Tecolote Crossover Washington Crossover

  13. Near Completion: San Luis Rey Transit Center San Luis Rey Transit Center New bus transit center $9 million SANDAG construction completion October 2013 NCTD communications work through early 2014 Bus operations to begin in February 2014 Santa Margarita River Bridge Sorrento to Miramar 1

  14. Other SANDAG Initiatives • Station Parking Prioritization Study • Santa Fe Depot Study – in support of Convention Center COASTER station • Level Boarding Analysis

  15. LOSSAN Coastal Rail Corridor Capital Improvement Projects QUESTIONS & ANSWERS More Information: KeepSanDiegoMoving.com/LOSSAN 15