1 / 38

Conduct of a Lien Action

Conduct of a Lien Action. Duncan W. Glaholt. Pineau v. Kretschmar. 5 Lessons. Lesson # 1. Do not ask a Toronto Lien Master to order a Settlement Meeting. Why? Lien masters in Toronto do not order settlement meetings under s. 60(1). The first “lien pre-trial” in

keilah
Télécharger la présentation

Conduct of a Lien Action

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Conduct of a Lien Action Duncan W. Glaholt

  2. Pineau v. Kretschmar 5 Lessons

  3. Lesson # 1 Do not ask a Toronto Lien Master to order a Settlement Meeting

  4. Why? Lien masters in Toronto do not order settlement meetings under s. 60(1)

  5. The first “lien pre-trial” in Toronto is supervised by the lien master

  6. It is considered a more effective procedure than an unsupervised settlement meeting

  7. Lesson # 2 Do not ask a master to fix a day for trial, without obtaining a judgment of reference

  8. Why? • Without a judgment of reference, a lien master has no jurisdiction to make such an order under s. 60(2) fixing a day, time and place for the trial of a lien action. • A master has no jurisdiction to make an order that deals with the scheduling of trials on the Toronto judges’ trial list

  9. Lesson # 3 Never, ever fail to properly comply with s. 37(1)

  10. Why? Under s. 37(1) of the Act, if within two years after the date of issuance of the statement of claim, the action, or an action in which the lien may be enforced, has not been set down for trial, or an order has not been made fixing a trial date under s. 60(2), the lien expires, and a motion may then be brought, without notice, to declare the lien expired under s. 46

  11. Notes: A judgment of reference under s. 58(1) is not an order fixing a trial date. In order for the clock to stop ticking for the purposes of s. 37(1), an order under s. 60(1) is required.

  12. “What we have here is a failure to communicate” Warden, Cool Hand Luke

  13. “What we have here is a failure to communicate” Warden, Cool Hand Luke Lesson # 4: Do not ignore previous Court orders and ask for the same relief again

  14. “What we have here is a failure to communicate” Warden, Cool Hand Luke Why? Because it shows the Master that (a) you don’t know the file; or (b) you think the Master doesn’t. Neither is good.

  15. Lesson # 5 Do not file material (pre-trial memoranda for example) that are not used in Toronto

  16. Why? • Pre-Trial Memoranda and Briefs are used and required for settlement conferences in case managed actions under Rule 77. • R. 77 does not apply to construction lien actions or to pre-trial conferences in non-case managed actions under Rule 50, which rule also does not apply to construction lien actions. • Pre-Trial memos are not used or required in Toronto construction lien actions.

  17. The Proper Procedure to Bring a Toronto Lien Action to Trial

  18. Proper Procedure # 1 If the premises are within the City of Toronto, the action must be commenced by the issuing of a statement of claim in the Toronto office of the Superior Court of Justice.

  19. Proper Procedure # 2 Pleadings are to be exchanged according to sections 53, 54, 55 and 56 of the Construction Lien Act.

  20. Proper Procedure # 3 Counsel has to elect whether the case is to be tried by a judge or by a master.

  21. Proper Procedure # 4 If counsel wants a master to hear the case, a judgment of reference must be obtained under s. 58

  22. Proper Procedure # 5 The form of the judgment of reference is mandated by Ont. Reg. 175, R.R.O. 1990, s. 2(16) and Form 16.

  23. Proper Procedure # 6 A judgment of reference is not an order fixing a trial date for the purpose of s. 37(1)

  24. Proper Procedure # 7 Once a judgment of reference has been obtained, a motion must be made to a master, without notice, to have a date, time and place fixed for the trial of the action. This date will be known as the “first construction lien pre-trial”. It is, in fact, the first day of trial.

  25. Proper Procedure # 8 The party that obtained this order must serve a notice of trial and a copy of the order on all persons listed in s. 60(2), i.e. mainly any other lien claimants and those with a registered interest in the property.

  26. Costs

  27. Facts • The master invited submissions on costs. • Both defendants sought costs from the plaintiff. • The plaintiff sought costs from its former solicitors. Costs

  28. Argument # 1 • With regard to the expiry under s. 37, counsel for the defendants should have known that the lien had expired on June 18 and should have moved shortly thereafter to have the lien declared expired under s. 37 and 46 of the C.L.A. • If this had been done, then the lien action would have been dismissed, and none of the subsequently incurred costs would have been incurred. Costs

  29. Master Sandler’s Decision • On these facts, this argument does not work. • In a normal s. 37/ s.46 case, it would. Costs

  30. Argument # 2 • s. 86 was a complete code; • R. 57 was inconsistent and therefore did not apply (s. 67(3)); • s. 86 required real misbehavior Costs

  31. Master Sandler’s Decision • Section 86 (1)(b), both (i) and (ii), and rule 57.07 (1) are not inconsistent. • They are mutually reinforcing of one another. • They stand together to cover all the different scenarios that can arise in the problematic conduct of a lien action. • R. 57.07 (1)(c) authorizes the court to order the solicitors to pay the costs personally Costs

  32. Discussion Points • Remedial provisions are liberally construed, punitive provisions are narrowly construed. Q: Is s. 86 remedial or punitive? 2. Compare R. 57 to s. 86: Q: Is the bar in R. 57 not set lower? Q: Are the remedies not broader? Q: Do you think they are “consistent” or not? 3. Q: Now that we have Pineau, what is the “least expensive course” in s. 86? A: You cannot wait. Either move under s. 46 or forfeit claims to subsequently incurred costs.

  33. THE END

More Related