An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Maintenance and Accelerator Support RHIC Startup 11

  2. RHIC startup: • Completed last week: • Shielding installation • RHIC roll ups • AtR ACS re-certification • This week: • Completed AtR re-start (beam to W dump). • Complete RHIC re-certification • 4k cool-down • Cold Magnet & power supply checkout

  3. This weeks schedule: • Today: • Restricted Access in all areas of RHIC • Spin flipper DC testing in the 9 o’clock area • RF setup in the afternoon • Some ACS tests (momentary interrupts?)

  4. Schedule Wednesday 1/5 • RHIC ring on RA all day • RF dipole install at 9 o’clock • OPPIS maintenance • Run injectors on alternate source • NO injector access planned at this time • Restore OPPIS injection in the afternoon

  5. Thursday 1/6/11 • RHIC on RA all day • RF testing in the afternoon • RSC checklist items completed • All RHIC areas prepped for Beam activity

  6. Friday 1/7/11 • Sweeps start if Blue ring ready for beam (determined Thursday night) • First areas swept starting at 0800hrs • 2 and 12 IRs last ring areas swept (STAR and PHENIX stay on RA) • Test current limit key after sweeps completed • Sweep experiments after test, begin beam work in evening