BUILDING INSPECTION WORKSHOP. Excavation & Readiness To Construct Footings. AGENDA. Notification Project Review Undisturbed Soil Minimum Depth Compacted Fill & Part 4 Designed Footings/Foundations Form Layout & Setbacks Footings Precautions Waterproofing Termite Control. Notification.

kim
Télécharger la présentation

BUILDING INSPECTION WORKSHOP

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BUILDING INSPECTION WORKSHOP Excavation & Readiness To Construct Footings Presented by:The Special Investigation Team and Piero B. Cannistra, Supervisor/Trainer

  2. AGENDA • Notification • Project Review • Undisturbed Soil • Minimum Depth • Compacted Fill & Part 4 Designed Footings/Foundations • Form Layout & Setbacks • Footings • Precautions • Waterproofing • Termite Control

  3. Notification • Notification to Building Inspection Division: ResFax • Telephone#: 905-475-4850 • Fax# 905-415-7501 • Notification of Inspection Request must be before 1:00pm to receive a next day inspection • Reports do not substitute for inspections performed by the Building Standards Department building inspection staff

  4. Permit drawings on site E02 Ensure changes made to permit drawings are incorporated into project Frost Protection Plan during cold weather to avoid freezing of the soil & concrete Not permitted to displace water within the footing with concrete pouring Pour footings continuously, if not possible provide a proper joint with 2 reinforcement bars E22 Project Review

  5. Undisturbed Soil9.12.2.1 • The Town of Markham Building Standards service level: • Is limited to a visual inspection of the excavation • For conducting prescribed inspections does NOT include testing to determine the bearing capacity of soil for compliance with the building code ‘ The builder, owner and the person to whom this permit is issued to, shall assure themselves, that the soil bearing capacity of supporting the loads imposed from the proposed building and that the Town of Markham may not b relied on to certify soil properties’ • Footings on solid, clean & unfrozen ground E12, E14, E15, B0820 • 9.12.1.3 • Geotechnical engineer confirming design net bearing pressure of soil • Excavation free of standing water E08, E25 • 9.12.1.2 • Bottom of excavation free of organic material E09 • 9.12.1.1 • Professional engineer report where high ground water level is suspected or water at the bottom of the excavation cannot be accounted for

  6. Minimum Depths • Elevation of footings are minimum 1.2 m below finished grade level & provide the proper frost protection cover E16 • Ensure depth of footings has accounted for drains serving rear yard catch basins & that the drains don’t undermine the footings or are within the angle of repose E17 • Excavation inspection of deck post footings required

  7. Compacted Fill & Part 4 Designed Footings/Foundations • Submit professional geotechnical engineer reports: • Confirming compacted granular fill • Confirming compacted fill capable of supporting the net bearing pressure • Part 4 designed footings/foundations, i.e. Piles, grade beams, etc. (28), (27)

  8. Form Layout & Setbacks • Footing form layout in accordance with permit plans E18, B0830, B0840 • If setbacks are suspect , a survey from an Ontario Land Surveyor (O.L.S.) will be required E19

  9. Confirm size, depth and design of strip footings E18 Column pad thickness greater than strip footings E20 Stepped footings have proper vertical rise & horizontal distance between risers E21 Reinforcement has been placed at the location where drains pass under the footings E23 Sleeves used in forms for weeping tiles E24 Footing thickness conforms to permit plans Bottom of excavation within the footing forms is cleaned of loose debris, soil & water E06 Angle of repose of the soil critical for existing footings and are affected by new excavations, the footings & foundations must be designed by a professional engineer E07 Footings

  10. Precautions • Watch for excavation damage to services & adjacent property, including public property • Fencing & hoarding installed when constructing adjacent to an occupied property E29

  11. Waterproofing • Consider the cause of wet conditions, if waterproofing is required; submit a report from a professional engineer E30, (2)

  12. Termite Control • Certain areas of Markham are termite infested, check with your building inspector for required termite control action to be taken E31