1 / 11

Information Technology Project Briefing

Information Technology Project Briefing. January 2011. Agenda. Web Re-Architecture Wireless Enhancement Electronic Policy Orchestrator (EPO) Lab and Classroom Upgrades Adobe Site License UITS Update Questions/Comments. Web Re-Architecture. Major Milestones to Date

kin
Télécharger la présentation

Information Technology Project Briefing

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Information Technology Project Briefing January 2011

  2. Agenda • Web Re-Architecture • Wireless Enhancement • Electronic Policy Orchestrator (EPO) • Lab and Classroom Upgrades • Adobe Site License • UITS Update • Questions/Comments

  3. Web Re-Architecture • Major Milestones to Date • Q2 2008 Complete Project Mission, Vision, Goals & Prepared for RFI / RFP • Q3 2009 Completion of RFP Process & Vendor Selection • Q3/Q4 2009 Discovery Meetings, Immersion Sessions, Information Collection • Q4 2009 Commence Project with Campus-Wide Stakeholder Meetings • Q1 2010 Demise of BigBad Inc (Selected vendor partner) • Q2 2010 Replacement of BigBad with Viridian Spark and Re-Scope of Project Strategy • Q2 2010 Completion of Website Strategy & Brief • Q3 2010 Complete Website Architecture • Q3 2010 Complete Usability Testing • Q3 2010 Evaluation of and Final Selection of Content Management System (CMS) • Q3 2010 Complete off-site Hosting Agreement for Initial Development Region • Q4 2010 Complete Homepage & Template Designs • Q4 2010 Gain Approval of all Designs (18 Templates) • Q4 2010 Create Designs for Public Consumption and Review • Q4 2010 Stakeholder Presentation of Designs and Content Phase “Kick-Off” • Q4 2010 Commence Content Phase • Q1 2011 Commence CMS Development Phase

  4. Web Re-Architecture • Major Milestones in Progress/Planned • Q1 2011 Commence Content Inventory Review/Assignments of Key Contributors • Q1 2011 Assignment of Resources to Sub-Projects & Tasks • Q1 2011 Selection of Top 60 Pages of Content Completion by Viridian Spark • Q1 2011 Departmental Content Focus Meetings (17+ Departments/Colleges) • Q1 2011 “Writing for the Web” Trainings (Jan 19, 20, 21) • Q1 2011 Development of all Templates in CMS, Technical Capabilities • Q1 2011 Commence “Physical” Hosting Review and Strategy for Go Live • Q1 2011 New Modules/Revamp/Develop and Workflow into CMS • Q1 2011 Commence creation of “Story Telling” (Videos/Interviews/Photography) • Q1 2011 Complete “Train the Trainer” Sessions, Live use of CMS and Content Entry • Q1/Q2 2011 Delivery of Deployment Kit and Establishment of Operational Environment • Q2/Q3 2011 Source “Content Entry” Team(s) • Q2/Q3 2011 Content Entry into CMS (All Departments/Colleges Mission Critical Data) • Q2/Q3 2011 Go Live (the “Big Bang”) • Q3/Q4 2011 Post Deployment Ongoing Sub Projects and Tasks

  5. Web Re-Architecture • UMB Staff Concurrent Projects, Tasks, & Focus Q1/Q2/Q3 2011 and Beyond • Course Catalog / Course Wizard / Course Listings Development • Existing Work Order (non Business Critical) Moritorium • Conversion of Current Web Based Applications (Legacy) and New Applications • Imbedded Analytics (Google) • Integration of R25 / 25 Live Calendars Segmented by Departments / Colleges • Conversion of new and / or Pre-Existing Sites Currently awaiting new CMS • Forms Review & Integration • CMS Administrator Role Establishment • Hosting, Monitoring, and Revision Control Software Implementation • Style sheets, Templates, Development Standards, Online & Classroom Trainings & Programs • Rebuild & Expansion of Mobile Site • Conversion of Online Directory & IT Web Site • Ecommerce Investigation / Cybersource/ HOP • Federation and Shibboleth • Establishment of Overall Governance Model

  6. WIRELESS ENHANCEMENT TIMELINE 55 WAPs campus-wide. Replaced all 55 with N-enabled more powerful WAPs. 60Mbps Internet dedicated to wireless. 25 WAPs distributed on campus. Bluesocket in Campus Center. Shared bandwidth for wireless. 96 WAPs currently. See distribution below. Increased bandwidth to 90Mbps dedicated wireless. Staff &Faculty wireless network (1/28) 2005-2009 7/10 8/10 9/10 1/11 6/11 30 additional WAPs to be installed and fill coverage gaps (126 total) Installed campus packetshaper. Dedicated 60Mbps of 260Mbps pipe to wireless. ENAC put in production. Average of 1400 simultaneous wireless users per day. Break down of current APs per building (96 total): Admin:  5 CCTR:  17 Clark: 1 Healey: 15 McCormack: 17 Public Safety: 1 Science:  25 Wheatley: 15 4,163 different devices (12/10 busy day avg): 1,540 - Windows devices 1,293 - iphone/ipod/itouch devices 975    - Mac devices 90      - HTC touch 89      - Blackberries 29      - Andriods 32      - linux 16      - Symbians 99      - Misc (PSP, Tablet, etc.)

  7. EPO Server(Enterprise Policy Orchestrator) • The EPO server is in place and is currently being populated with systems from across campus • This system provides us with the following: • An up-to-date Anti-Virus System • An Endpoint Encryption solution for laptop and other devices that could be storing sensitive data • A Data-Loss-Prevention modules that searches out and reports sensitive data such as account numbers, SSN’s, etc.

  8. Lab and Classroom Upgrades • Purple, Gold and ACL – New Computers • Software – Windows 7, Office 2010, Acrobat Professional; with Adobe CS 5 coming in Summer • GRC – Network Upgrade • Green – Research Computer Lab • Classroom Upgrades (3) - Tec 1 & Tech 2 • Seminar/Classrooms (10) – McCormack & Wheatley • 55” LCD Monitor

  9. Adobe Site License • Adobe Acrobat Pro – Requested by Faculty & Staff • A UMass System Wide Site License • Includes: • Photoshop, Illustrator, Bridge, InDesign, Dreamweaver, Flash, Acrobat & Fireworks • Training & Support • Overview + 6 Topics • Collaboration • Graphic Design, Quinn Graphics • Graduate Studies, Web Services

  10. UITS/Boston Initiatives

  11. Questions/Comments

More Related