1 / 8

HiRadMat : report from WG2 – WANF dismantling

HiRadMat : report from WG2 – WANF dismantling . Agenda. Activities carried out in Week 1 Planning for Week 2 WANF cleaning : preparation T1 dismantling : news. Activities carried out in Week 1. MCA and TCX blocks. January 08, 2010. Forklift shielding in progress.

kioshi
Télécharger la présentation

HiRadMat : report from WG2 – WANF dismantling

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HiRadMat: report from WG2 – WANF dismantling Agenda S. Evrard • Activities carried out in Week 1 • Planning for Week 2 • WANF cleaning : preparation • T1 dismantling : news.

  2. Activities carried out in Week 1 MCA and TCX blocks January 08, 2010 S. Evrard Forklift shielding in progress

  3. Activities carried out in Week 1 B846 pit reconnaissance January 08, 2010 S. Evrard Two doors opened by Fire Brigade Crinoline ladder seems to be OK

  4. Activities carried out in Week 1 Cabling January 08, 2010 S. Evrard 3 cables pulled for door interlocks and patrol box Red telephone cable still missing Lighting power cable already available : additional TL’s in late January

  5. Activities carried out in Week 1 Furet dismantling and electrical cupboard refurbishment January 08, 2010 S. Evrard Work in progress FURET on the floor Cerap will clean it on Monday

  6. Co-activities in January 2010 Planning in week 2 EN-HE EN-CV Contractor EN-HE GS-ASE, IT-CS EN-HE EN-HE: T1 : MCA + Tax blocks EN-HE: furet removal EN-HE: Electrical cabinet refurbish. January 08, 2010

  7. WANF cleaning January 08, 2010 S. Evrard ENDEL SCTN best offer out of 4 companies enquired (all contacted): Work procedure transmitted today by Endel Analysis in progress with DG-SCR Work preparation (safety courses, access requests, equipment on site,…) on Thursday 14 and Friday 15 Work in Week 3 (18  22 January)

  8. T1 dismantling : news January 08, 2010 S. Evrard Location of remaining beam pipe defined (Thanks to V. De Jesus)