1 / 36

Beam Stability WBS U 1.03.02.02 and SPX Diagnostics WBS U 1.03.03.08

Beam Stability WBS U 1.03.02.02 and SPX Diagnostics WBS U 1.03.03.08. Glenn Decker Group Leader APS Accelerator System Division Diagnostics DOE Lehman CD-2 Review of APS-Upgrade 4-6 Decem ber 2012. Outline. Beam Stability Technical Motivation WBS Scope – Beam Stability Staff / Org Chart

korbin
Télécharger la présentation

Beam Stability WBS U 1.03.02.02 and SPX Diagnostics WBS U 1.03.03.08

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Beam StabilityWBS U1.03.02.02andSPX DiagnosticsWBS U1.03.03.08 Glenn Decker Group Leader APS Accelerator System Division Diagnostics DOE Lehman CD-2 Review of APS-Upgrade4-6 December 2012

  2. Outline • Beam Stability Technical Motivation • WBS Scope – Beam Stability • Staff / Org Chart • Requirements • Design • Interfaces • Risks • ES&H • Cost • Schedule • SPX Diagnostics DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  3. Beam Stability Technical MotivationWBS U1.03.02.02 • APS orbit correction system has a lot of out-of-date hardware. • Modernization of select beam position monitoring and feedback systems will benefit the entire APS user community. • With over 15 years of operational experience, the upgrade is tailored to the noise spectrum and lattice specific to APS. DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  4. Beam Stability and SPX Beam Diagnostics Project Scope and WBS Level 4U1.02.03.08, U1.03.02.02, & U1.03.03.08 DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  5. Beam Stability RequirementsWBS U1.03.02.02 • APS-U Beam Stability Physics Requirement Document APS_1428984 • Based on 5% of transverse beam dimensions up to 200 Hz and 10% up to 1 kHz. DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  6. Beam Stability Org ChartWBS U1.03.02.02 DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  7. Existing APS Beam Position Monitoring – One Sector ** * (Bergoz) *PUE = Pickup Electrode ** AM/PM = Amplitude to Phase conversion DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  8. Beam Stability ScopeWBS U1.03.02.02 *Note that GRID XBPM mechanical assemblies are in WBS 1.05.02 Front End Upgrades. DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  9. RF BPM ElectronicsWBS U1.03.02.02.01.01, U1.03.02.02.01.02 nm rms G. Decker, BIW10 DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  10. State-of-the-art Commercial Solution I-Tech Libera Brilliance+WBS U1.03.02.02.01.01 • Noise floor approaching 2 nm / √Hz • Long-term drift 200 nm p-p / 24 hours* • Integrated User FPGA support for feedback system development • Planned for small-aperture insertion device vacuum chambers for best source point control * Guenther Rehm, Diamond Light Source, EPAC 2008 DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  11. BPM Electronics APS BSP-100 Data AcquisitionWBS U1.03.02.02.01.02 • Eight channels/board, 88 MS/sec sampling. Altera FPGA processing. • One second (262144 samples) turn-by-turn beam history for machine studies / fault diagnosis. • Demonstrated noise floor < 10 nm / √Hz. • Used for ongoing broadband BPM upgrade (programmatic). • Planned for Bergoz rf BPM and legacy photon BPM data acquisition upgrade. DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  12. Next-Generation X-ray BPM SystemWBS U1.05.02 GRID-XBPM • Grazing incidence allows access to extremely high beam power (two U3.3 undulators at up to 150 mA). • X-ray fluorescence reduces stray radiation background signals significantly. • Use of two two-pixel (above, below midplane) pinhole cameras allows two independent measures of vertical x-ray beam position. • Inboard / outboard difference provides measure of horizontal beam position. • The upstream position monitor is referred to as the Grazing-Incidence Insertion Device X-ray Beam Position Monitor (GRID-XBPM). • Subject of Bingxin Yang’s talk to follow. PHC = Pinhole Camera IM = Intensity Monitor PS = Photon Shutter EM = Exit Mask DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  13. Real-time Feedback System UpgradeWBS U1.03.02.02.02 Existing System Upgraded System • Maximum 160 BPMs, 38 fast correctors • Sample rate 1.537 kHz • Based on 15-year-old digital signal processors, reflective memory • 3 dB BW = 60 Hz (H), 100 Hz (V) • Maximum approx. 500 BPMs, 70 fast correctors, 250 slow correctors • Sample rate Frev / 14 = 19.4 kHz • Based on extremely high-speed FPGA data protocols • Access to phase detectors, beam tilt monitors supporting SPX • Interfaced to main and SPX low-level rf (LLRF) systems • 3 dB BW > 200 Hz (correctors only), 1 kHz (w/ lord feedback) • Full-time FPGA expert (R. Lipa) hired into Diagnostics Group April 2012 DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  14. Real-time Feedback System Upgrade cont’dWBS U1.03.02.02.02 APS RTFB ESD ICMS APS_1431171 DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  15. First Fast Feedback Simulation Results Raw Horizontal Spectrum Synchrotron Tune Integrated Spectrum 360 Hz from Main RF Feedback Off* Feedback On *Feedback off data derived from measured beam spectrum Director's CD-2 Review of the Advanced Photon Source Upgrade Project 11-13 September 2012

  16. BPM Mechanical Motion SensingWBS U1.03.02.02.03 • Commercially-available capacitive motion sensors have sub-nm resolution. • Mechanical Design using invar supports integrated into GRID support system, pending for insertion device vacuum chamber monitoring. DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  17. BPM Mechanical Motion Sensing Cont’dWBS U1.03.02.02.03 DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  18. Beam Stability Required InterfacesWBS U1.03.02 • Feedback system interface control documents to be written: • Monopulse rf BPMs, Bergoz (narrowband) rf BPMs, Libera BPMs • Existing x-ray BPM electronics • GRID xBPM system data acquisition electronics • Steering corrector power supply controller • EPICS, including enumeration of process variables and their functions • Timing, including the APS event system • SPX diagnostics in sector 5 • Main 352 MHz low-level rf • SPX 2815 MHz low-level rf • The APS machine protection system (MPS) DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  19. Beam Stability RisksWBS U1.03.02 • No major risks • Beam stability could be temporarily degraded. • Single vendor for high-resolution rf BPMs possible concern. • Estimates and designs have been refined since last CD-1 review. • First high-power GRID XBPM tests completed, reducing technical risk substantially. DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  20. Beam Stability ES&HWBS U1.03.02 • Integrated Safety Management System (ISMS) • APS-U Project follows Argonne’s ISMS program requirements • Argonne Integrated Safety Management System (ISMS) Description recently revised and submitted to DOE ASO • Describes framework for integrating ESH requirements with mission objectives • References Argonne LMS procedures which implement specific portions of the ISMS • All electrical safety practices will be adhered to. • Diagnostics has its own designated electrical equipment inspector (NRTL). • The APS work request system will be used for work planning and control. DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  21. Response to Review Committee Recommendations • Machine Advisory Committee – Accelerator Physics 5/18 - 5/19 2012 (MAC 2012) “We recommend using the opportunity of this upgrade to move to an integrated, state‐of‐th­e‐art (orbit feedback) system and not to remain constrained by limitations of existing legacy systems. We caution that this is a significant manpower effort and suggest thinking about collaborations with other light sources (US or elsewhere).” • Response: A cell controller board has been borrowed from NSLS-II for evaluation, and feedback simulation efforts have been initiated in collaboration with NSLS scientists. In addition, a workshop on feedback is being planned. • MAC 2012 “…the beam-based feedback systems for SPX need further thought and detailed simulations. Ideally these systems would be integrated into the overall feedback system.” • Response: The present design is planned to be interfaced to both the main rf and SPX rf systems. • CD-2 Director’s Review 9/11 - 9/13 2012 “The cost estimates for … mechanical motion sensors may benefit from value engineering.” • Response: See next slide … DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  22. Beam Stability Value EngineeringWBS U1.03.02 Antenna • Evaluation of alternative methodologies for mechanical motion sensing are being explored with programmatic funding: • A nano-positioner and capacitive proximity sensor have been procured for evaluation. • The APS-developed BSP-100 data acquisition module is being used in as many applications as possible. Cavity Pickup • An APS-designed LCLS-style cavity BPM with fixed antenna has been constructed. DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  23. Beam Stability and SPX Beam Diagnostics Project Scope and WBS Level 6U1.02.03.08, U1.03.02.02, & U1.03.03.08 DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  24. Beam Stability and SPX Beam Diagnostics Project Obligation ProfileU1.02.03.08, U1.03.02.02, & U1.03.03.08 DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  25. Beam Stability and SPX Beam Diagnostics Summary ScheduleU1.02.03.08, U1.03.02.02, & U1.03.03.08 DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  26. Beam Stability and SPX Beam Diagnostics BOE Contingency U1.02.03.08, U1.03.02.02, & U1.03.03.08 DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  27. Work between CD-2 and CD-3 • Work Remaining for CD-3 • Perform first article GRID XBPM in-tunnel tests. • Finalize GRID-XBPM electronics and data acquisition design. • Complete real-time feedback hardware component selection. • Ramp up feedback simulation efforts in collaboration with BNL. • Perform mechanical motion sensing system mechanical design and prototype. • Finalize all ESDs and ICDs. • Beam Stability Electronic Systems Design Review DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  28. Beam Stability Summary • Beam Stability upgrade preliminary design is complete. • Beam Stability Physics Requirement Document drives • BPM and real-time feedback system design • SPX stability requirements • ID field quality specifications • The cost is $8,292k • We are ready for CD2. DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  29. Other Diagnostics-Related Activities • 1.03.03.08 SPX Diagnostics1.02.01.03.08 SPX0 Diagnostics (descoped)1.05.02.11 Next-Generation X-ray BPM System for HHL1.05.02.12 Next-Generation X-ray BPM System for CU DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  30. SPX Diagnostics Scope of WorkWBS U1.03.03.08 DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  31. Beam Arrival Time MonitorWBS U1.03.03.08.03 • Technology based on existing APS linac s-band phase detector system. • Interface uses APS BSP-100 data acquisition. • Specifications not too demanding – a fraction of the bunch length. DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  32. Beam Arrival Time Jitter Power Spectral Density 60 Hz 360 Hz from Main RF Synchrotron Tune στ= 2.1 ps = rms jitter, 0.3 Hz to 3 kHz στ(ω) = Square Root of reverse-integrated power spectral density Note: the rms bunch length for 24-singlets fill pattern is 33.5 ps. DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  33. Application of Phase Detector to Tilt Measurement* Vertical Bunch Position Phase Detector Output Vertical / Longitudinal Tilt Transient excitation of tilt using a fast vertical kicker** * N. Sereno et al., BIW2012 **W. Guo, PRST-AB 10, 020701 (2007) DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  34. Wire Position Monitor Test StandWBS U1.03.03.08.02 Courtesy of Bob Lill DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  35. High-Resolution Beam Size MonitorWBS U1.03.03.08.01 • High-resolution (9 microns rms) beam size monitor to be installed at unused bending magnet radiation port. • Bandwidth > 1 Hz DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  36. SPX Diagnostics SummaryWBS U1.03.03.08 • New diagnostics have all been demonstrated: • Beam arrival time (BAT) monitor • Wire position monitor • Repurposing of existing s-band phase detectors to direct tilt monitoring • We are ready for CD2 DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

More Related