RHIC Run-7 Au-Au Operation

RHIC Run-7 Au-Au Operation. Run organization Previous run and expectation for Run7 Start-Up plan Problem areas. A. Drees APEX workshop, Nov 2 nd 2006. RHIC Run organization. Run Coordinator HI Angelika Drees

lanj
Télécharger la présentation

RHIC Run-7 Au-Au Operation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. RHIC Run-7 Au-Au Operation • Run organization • Previous run and expectation for Run7 • Start-Up plan • Problem areas A. Drees APEX workshop, Nov 2nd 2006

  2. RHIC Run organization • Run Coordinator HI Angelika Drees • Run Coordinator PP/other Christoph Montag • Scheduling physicist Kip Gardner • RHIC shift leaders: Bai, Drees, Luo, Montag, Ptitsyn, Kewisch, Zhang, Beebee-Wang, McKay, Satogata • Back-up RHIC shift leaders: Fischer, Montag/Drees, Trbojevic, Pilat • Trainees: Dmitry, Alexei, Guillaume, Eduard • Operations + RHIC specialist (Marr) larger role during set-up, ramp-up, beam-ex Weekly schedule (no maior changes) Monday Scheduling meeting Monday RHIC Weekly meeting Tuesday Time Meeting & Machine-experiments meeting operations analysis meeting (new) varying/Wednesday Beam Experiments Wednesday maintenance day (bi-weekly) daily/varying RHIC run meeting (will have to change time slightly: 9:00 am)

  3. Run 7 Draft Schedule • dry run Nov. 15-17 • RHIC cool down begins Dec. 1 • assume 30 cryo-weeks • assume two mode running: HI + other (d-Au, pp, …) • HI could include low energy run • 1st beam in RHIC (blue) Dec. 8 • set-up in cool-down mode: 10 days • ramp and store development: 1 1/2 weeks • ramp up: 1 week • 12 weeks of physics basic parameters: • 2 experiments • tunes 0.22/0.23 • Brho ~81 Tm • b*: 0.85, 0.85, 5, 7, 5, 5

  4. Expected Luminosity for HI • No. of bunches: likely to increase gradually during the run, maybe up to 111 • ions/bunch: 1.1 109 achieved => we could probably get 1.3-1.5 109 from injectors • transition crossing • vacuum/pressure rise • b*: squeeze to 0.85 m (=> background, collimators …) • time in store: how can we reach 60%? Automation, QLI reduction, PS reliability, weather … • bunched intensity, vertex: stochastic cooling • stochastic cooling: yellow only (blue in testing), will not yet reduce vertex distribution significantly but increase yellow bunched lifetime, 10% L increase?

  5. RHIC Run-4 – Au-Au operation Major achievements Au-Au: • Start-up/ramp-up in 4 weeks (1 week less than planned) • Consistent high bunch intensity from injector(109Au) • Time in store increased to 53% (65% at 31.2GeV/u) • Reliable, almost complete rebucketing into storage rf • Steering and collimator setting time reduced to 10min • Best 7 days delivered 179 μb-1 to Phenix (2x Run-2) • Set-up for 31.2GeV/u run in less than 2 days from W.Fischer, Retreat 04

  6. 60e9 Auintensity, with 45 bunches only! Beam experiments enhancedluminosity designluminosity RHIC Run-4 record week Week 9 Feb to 17 Feb[66% of calendar time in store]=> so we’ve done it before ;) f. W. Fischer, retreat 04

  7. Run4 Emittances and Luminosities (Initial)

  8. Run-7 upgrades/improvements Booster/AGS bunch merge => Brennan, Gardner yellow only work in progress

  9. Cool-Down mode … followed by ramp- and store setup and ramp up intensity (3 weeks total) add some hours to check polarity of re-cabled sextupoles with beam in principle blue could ramp before yellow is ready. begin testing chromaticity measurements/feedback at injection

  10. Gap Cleaning Efficiency • existing data cannot determine 1st or 2nd order • extrapolation allows 1.4 109 ions/bunch with current gap cleaner and debunching rate • no IBS suppression assumed • no cooling • assume a store length of 4 hours before limit of debunched beam is reached • improve gap cleaner? • is in progress • software changes • duty cycle x 10 (looks good so far) • 1.4 109 ions/bunch can probably reached by injectors/tandem

  11. Run-7: ramp, set-up and efficiency • More automation: • Steering small changes compared to run4 • Collimation(small SW changes compared to run4) • Ramp & store orbit correction improved(time saving: machine became reproducible over whole run, can eliminate luminosity optimization, also saves time when exp. magnet configuration is changed) • Gap Cleaning: continuous during the store (no change), good up to 1.4 109 ions/bunch • Automate/Sequence all of the above • ongoing operations analysis meetings throughout the run • Configuration database • Instrumentation: BBQ, tune feedback, BTFs, de-coupling on the ramp