An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Good Samaritan Medical Center High Density Concrete Placement

  2. Walls • Blockouts around door for borated polyethelene and lead plates • Physics port • Allows staff to check radiation levels in the vault before entering • Sleeve through wall at 45 degrees vertical: Location was critical to prevent radiation leak

  3. Lid shoring • Wet weight of lid = over 1.6 million pounds • Designed by engineer; installation checked by engineer • Fireproofing of beams • Before placement of lid • Use of HD fireproofing to prevent damage by forming and reinforcing activities: No addit’l patching required • OFI – sheet metal cap detail • Allowed for fireproofing of beams before deck was placed

  4. Test run: Checked maximum free-fall of aggregate

  5. Placement High Density Concrete supplied by Central Concrete

  6. Placement continued… • 187.5 CY placed total • 4.5 CY of concrete batched in each 12 CY truck • Rate of placement • Started at 30 minutes per truck or more • Ended at 12-15 minutes per truck

  7. Placement continued …. Central concrete quality control manager onsite: Only person allowed to add chemicals to the mix

  8. Placement continued… Placement of high density concrete required normal size crew

  9. Finished vault • Due to high density, concrete finished with few imperfections, even with minimal vibrating • Maximum deflection of the lid measured at 3/16” • 12.5 hour pour • 14 hour day