1 / 26

Building Work Committee Renovation & Expansion Project Presentation March 7, 2009

Mason School District. Building Work Committee Renovation & Expansion Project Presentation March 7, 2009. THE TEAM. Mason School District Building Committee Mary McDonald Bob Bergeron Fred Greenwood Bob Hemmer Bernie O’Grady The Jordon Institute Energy Consultants Paul Levelle

Télécharger la présentation

Building Work Committee Renovation & Expansion Project Presentation March 7, 2009

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Mason School District Building Work Committee Renovation & Expansion Project Presentation March 7, 2009

  2. THE TEAM

  3. Mason School DistrictBuilding Committee Mary McDonald Bob Bergeron Fred Greenwood Bob Hemmer Bernie O’Grady The Jordon InstituteEnergy Consultants Paul Levelle Kirk Stone Daniel V Scully Architects Daniel Scully Katie Cassidy Sutherland The Jordon InstituteConstruction Managers John Gaston David Bryson Other Key Contributors Mark Richardson George & Catherine Schwenk, The Mason Congregational Church NH DOE & lots of on-lookers! …

  4. TODAY’S OBJECTIVES

  5. To Provide Information • How We Got Here : Needs Assessment & Design Themes • What it looks like : Building Plans Overview • Estimated Cost • Schedule • To Answer Questions • Your thoughts, questions, ideas & overall Feedback • Prepare for March 12th Vote

  6. How We Got Here • Withdrawal from Mascenic School District • Creation of Mason School District • Create Curriculum • Build a Staff • Find a "Home" for students • What We Considered • Building a New School for K thru 12 • Build a New Building for K thru 5 • Utilize Existing Buildings for K thru 5 • Add on to Existing Building for K thru 5

  7. Proposed : Site Modification Town Hall Existing School Parsonage Old Road School Lot Line Adjustment Relocation of Parsonage Lot

  8. REQUIRED Life & SafetyADA AccessFire EgressNH Dept. of EducationStructural Repair Fire Detection UpgradeBuilding Code Upgrade

  9. REQUIRED Minimum SpaceNH Dept. of EducationBuilding Code

  10. REQUIRED KindergartenNH State Mandate

  11. REQUIRED 5th GradePossible Due to Expansion of ExistingSpace to Required Minimum

  12. REQUIRED Administration SpaceREQUIRED CafeteriaPrincipalSuperintendentStaff RoofConference RoomCafeteriaKitchen

  13. REQUIRED Physical Ed

  14. Computer /ArtExpansionUtilized forComputer / MediaRoom and Art RoomIf Population Bubble OccursIt Can Be Utilized As A Larger Grade Classroom

  15. School / TownShared SpaceExpanded Space Can Be UtilizedFor School Music SpaceShared With The Town It CanBe Utilized AS A Meeting Space, Function Hall, Etc.

  16. Proposed Floor Plan

  17. Proposed – Ariel Top View

  18. Proposed : Front Elevation

  19. Proposed : Birdseye Front

  20. Proposed : Birdseye Back

  21. Schedule Outline Mason School District Bond Appropriation March 12, 2009 Lot line & Site finalization - Parsonage relocated June 2009 Ground Breaks for Addition July 2009 School Starts – Classrooms & Mechanical Room Complete Admin & SPED in Temps August 2009 Addition Complete June 2010 Renovation of Administration & Building Connection August 2010 Temporary Classrooms removed August 2010 Building Project Completed September 2010 High Performance Certification December 2010 / January 2011

  22. BUDGET

  23. Estimated Cost & Potential Aid Architectural / Engineering Design$ 577,109Site / Construction$3,886,425Total Bond Appropriation$4,274,534TOTAL DOES NOT DEDUCT NH AID (30%) TOTAL DOES NOT DEDCUCT GRANT PROPOSALS TOTAL DOES NOT DEDUCT ECONOMIC STIMULUS OPPORTUNITIES (Possibly as high as 5+%)

  24. How Will This Effect My Taxes

  25. What Your Vote Will Do • YES • Will have the project proceed as presented. • (The action that the Building Committee Endorses) • NO • Will stop all present projects. • Require us to resubmit a plan to the NH Dept. of Ed. • If plan does not meet their approval, they take over the process. • Possible closing of school and require us to tuition K thru 5. • Loss of NH State funding possible. • Loss of Federal Funding. • Present debt due to Mascenic due in full this year. • Tax impact will be significantly higher. • Cost of sending our children to school may be significantly higher. • (This action is NOT endorsed by the Building Committee)

  26. QUESTIONS & DISCUSSIONS

More Related