1 / 31

IRC - Codes Report Energy Efficiency in Housing and Small Buildings

IRC - Codes Report Energy Efficiency in Housing and Small Buildings. May 27 th 2011. Building Envelope. Outline Progress & Schedule Objectives, Functional Statements Application Building Envelope Requirements Insulation Requirements Nominal vs Effective

lilika
Télécharger la présentation

IRC - Codes Report Energy Efficiency in Housing and Small Buildings

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. IRC - Codes Report Energy Efficiency in Housing and Small Buildings May 27th 2011

  2. Building Envelope • Outline • Progress & Schedule • Objectives, Functional Statements • Application • Building Envelope Requirements • Insulation Requirements • Nominal vs Effective • Introduction to Appendix Information • Simple Trade-Off • Validation

  3. Progress • Since November 2010, • the Joint Task Group has held 3 meetings • and its sub-task groups have held over 30+ meetings • 5 teleconferences of the Executive Committee, • 1 meeting of the Commission. • Developing 80 new pages of code

  4. Proposed Project Schedule • SCEEB meeting May.5 – 6, 2011 SCH meeting May.25 – 26, 2011 • 1. batch of PCFs to E&T May.31, 2011 (Appendices) • Optional JTG-EEHSB Jun.16 – Jun.30, 2011 • 2. batch of PCFs to E&T Jun.30, 2011 (Prescriptive) • 3. batch of PCFs to E&T Jul.30, 2011 (Performance) • SC-HSB and SC-EEB Aug.15 – Sep.9, 2011 • Pre-Public Review Sep.12 – Oct.7, 2011 • Resolution of Comments (EC) Oct.10 – Oct.12, 2011 • 2011 Public Review Oct.24 – Dec.16, 2011 • Sub task group meetings Jan.4 – Jan.24, 2012 • Joint Task group meeting Feb.3 – Feb.7, 2012 • SCEEB meeting Feb.15, 2012 SCH meeting Feb.24, 2012 • Post-Public Review Mar.2 – Mar.31, 2012 • CCBFC meeting to approve Apr 20 – Apr.23, 2012 (no ballot) • CCC staff review of draft Jun.27 – Jul.12, 2012 • Publish Interim Changes Dec.20, 2012

  5. Objectives • OE Environment • An objective of this Code is to limit the probability that, as a result of the design or construction of the building, the environment will be affected in an unacceptable manner. • OE1 Resources • An objective of this Code is to limit the probability that, as a result of the design or construction of the building, resources will be used in a manner that will have an unacceptable effect on the environment. The risks of unacceptable effect on the environment due to use of resources addressed in this Code are those caused by – • OE1.1 excessive use of energy

  6. Functional Statements • NECB • F90 to limit the amount of uncontrolled air leakage through the building envelope • F91 to limit the amount of uncontrolled air leakage through the system components • F92 to limit the amount of uncontrolled thermal transfer through the building envelope • F93 to limit the amount of uncontrolled thermal transfer through the system components • F94 to limit the unnecessary energy demand and/or consumption of energy for lighting • F95 to limit the unnecessary energy demand and/or consumption of energy for heating and cooling • F96 to limit the unnecessary energy demand and/or consumption of energy for service water heating • F97 to limit the unnecessary energy demand and/or consumption of energy of electrical equipment and devices • F98 to limit the inefficiency of equipment • F99 to limit the inefficiency of systems • F100 to limit the unnecessary rejection of reusable waste energy

  7. Functional Statements • NBC Part 9 • F90 to limit the amount of uncontrolled air leakage through the building envelope • F91 to limit the amount of uncontrolled air leakage through the system components • F92 to limit the amount of uncontrolled thermal transfer through the building envelope • F93 to limit the amount of uncontrolled thermal transfer through the system components • F94 to limit the unnecessary energy demand and/or consumption of energy for lighting • F95 to limit the unnecessary energy demand and/or consumption of energy for heating and cooling • F96 to limit the unnecessary energy demand and/or consumption of energy for service water heating • F97 to limit the unnecessary energy demand and/or consumption of energy of electrical equipment and devices • F98 to limit the inefficiency of equipment • F99 to limit the inefficiency of systems • F100 to limit the unnecessary rejection of reusable waste energy

  8. Scope and Application • Small non-residential bldgs: • Less than 3000sqft floor area • Applicable to occupancies D, E and possibly F3 NECB

  9. Building Envelope • Scope and Application • Determination of Thermal Characteristics • Calculation of • Areas of Wall and Fenestration • Effective Thermal Resistance of Materials, Components and Assemblies • Continuity of Insulation • Required Thermal Characteristics of • Opaque Assemblies Above and Not in Contact with Ground • Windows, Doors and Skylights • Building Assemblies Below or in Contact With the Ground • Required Level of Airtightness • Construction of Air Barrier Details • Simple Trade-offs for Above-ground Components of the Building Envelope

  10. Building Envelope • Scope and Application • Determination of Thermal Characteristics • Calculation of • Areas of Wall and Fenestration • Effective Thermal Resistance of Materials, Components and Assemblies • Continuity of Insulation • Required Thermal Characteristics of • Opaque Assemblies Above and Not in Contact with Ground • Windows, Doors and Skylights • Building Assemblies Below or in Contact With the Ground • Required Level of Airtightness • Construction of Air Barrier Details • Simple Trade-offs for Above-ground Components of the Building Envelope

  11. Building Envelope • Prescriptive Thermal Requirements • Opaque Assemblies Above & Below Ground • Code: minimum effective RSI • Appendix: nominal R/RSI-values • Windows Doors & Skylights • max. U-values (2010 Energy Star) • min. ER values (not for skylights) • Various Compliance Paths • Insulation levels based on mechanical ventilation (no HRV) @ 2.5 ACH • Insulation levels based on HRV @ 2.5 ACH

  12. Proposed Requirements • Locations by Climate Zone

  13. Insulation Requirements • Nominal vs. Effective Requirements • Nominal = Insulation Value • Effective = Actual Resistance of the Assembly

  14. Insulation Requirements • Nominal vs. Effective Requirements • Nominal = Insulation Value for 2x6 16”oc • Effective = Actual Resistance of the Assembly

  15. Insulation Requirements • Nominal vs. Effective Requirements • Depends on construction • Depends on how much framing is in the wall • 2x6 @ 16” oc = 23% framing = 77% insulation

  16. Nominal Insulation vs. Effective RSI • Example: 2 x 6 construction - 16” on center R6.9 R19 23% 77%

  17. Nominal Insulation vs, Effective RSI • Example: 2 x 6 construction - 16” on center R 1.41 R 1.41 R 19 R 6.9 R 1.13 R 1.13 R 9.44 23% 77% R 21.54 Reff =16.64 RSIeff = 2.93 U = 0.34

  18. Nominal Insulation vs, Effective RSI • Example: 2 x 6 construction - 16” on center • Equation to calculate framing and insulation portion

  19. Nominal Insulation vs, Effective RSI • Example: 2 x 6 construction - 16” on center • Cavity only • R19/20 Nominal = 16.64 R eff = 2.93 RSI eff • R22 Nominal = 17.95 R eff = 3.16 RSI eff • R24 Nominal = 18.74 R eff = 3.30 RSI eff 23% 77%

  20. Nominal Insulation vs, Effective RSI • Example: 2 x 6 construction - 16” on center with ext. ins. R 6.41 R 6.41 R 5 R 19 R 6.9 R 19 R 1.13 R 1.13 R 14.44 23% 77% R 26.54 Reff =22.26 RSIeff = 3.92 U = 0.26

  21. Nominal Insulation vs. Effective RSI • 2 x 6 Cavity only • R19/20 Nominal = 16.64 R eff = 2.93 RSI eff • R22 Nominal = 17.95 R eff = 3.16 RSI eff • R24 Nominal = 18.74 R eff = 3.30 RSI eff • 2 x 6 Cavity with exterior insulation • R19 + R5 = R24 Nominal = 22.26 R eff = 3.92 RSI eff • R22 + R5 = R27 Nominal = 23.82 R eff = 4.19 RSI eff • 2 x 4 Cavity with exterior insulation • R12 + R10 = R22Nominal = 22.24 R eff = 3.92 RSI eff 23% 77%

  22. Simple Trade Off • 3 Options: • Opaque to Opaque • Opaque to Transparent (areas remain the same) • Trade Areas • Applies only to • houses/bldgs with FDWR 15% or less • Max, ce-ling height 7’ 8” • Limitations • Can’t reduce R-Values • below 55% of the R-value for walls and attic roofs • below 60% of the R-values of other opaque assemblies • Does not apply to • heated assemblies • components and assemblies already exempted • below ground assemblies

  23. Building Envelope • Simple Trade Off – Option 1 • Example: Trade Wall against Attic Insulation • Existing Case • Assemblies Area R-value =40.73 W/K • Attic 200 m² 6.99 m²K/W (R40) • Wall 40 m² 3.30 m²K/W (R24) : R ≥ 1.8 m²K/W • Desired Case • Assemblies Area R-value • Attic 200 m² ???m²K/W • Wall 40 m² 2.93 m²K/W (R20)

  24. Building Envelope • Simple Trade Off – Option 1 • Example: Trade Wall against Attic Insulation • Existing Case • Assemblies Area R-value =40.73 W/K • Attic 200 m² 6.99 m²K/W (R40) • Wall 40 m² 3.30 m²K/W (R24) : R ≥ 1.8 m²K/W • Desired Case • Assemblies Area R-value = 40.73 W/K • Attic 200 m² 7.39 m²K/W (R 42) • Wall 40 m² 2.93 m²K/W (R20)

  25. Building Envelope • Simple Trade Off – Option 2 • Example: Allow 1 decorative Window (2 m² with a U = 2.6) • Existing Case • Assemblies Area R-value =125.5 W/K • Wall 200 m² 3.24 m²K/W (R22) • Window 40 m² 0.63 m²K/W (U=1.6) : R ≥ 0.38 m²K/W : U ≤ 2.6 W/m²K • Desired Case • Assemblies Area R-value ≤ 125 W/K • Wall ??? 3.24 m²K/W (R22) • Window 38 m² 0.63 m²K/W (U=1.6) • Window 2m² 0.38 m²K/W (U=2.6) • Wall???3.43 m²K/W (R24)

  26. Building Envelope • Simple Trade Off – Option 2 • Example: Allow 1 decorative Window (2 m² with a U = 2.6) • Existing Case • Assemblies Area R-value =125.5 W/K • Wall 200 m² 3.24 m²K/W (R22) • Window 40 m² 0.63 m²K/W (U=1.6) : R ≥ 0.38 m²K/W : U ≤ 2.6 W/m²K • Desired Case • Assemblies Area R-value ≤ 125 W/K • Wall 66 m² 3.24 m²K/W (R22) • Window 38 m² 0.63 m²K/W (U=1.6) • Window 2 m² 0.38 m²K/W (U=2.6) • Wall132 m²3.43 m²K/W (R24)

  27. Simple Trade Off • Option 3 Example: Trading Window Area for Reduced Attic Insulation • Existing Case (FDWR = 12%) • Assemblies Area R-value =38.6 W/K • Attic 100 m² 6.99 m²K/W (R40) • Window 18 m² 0.63 m²K/W (U=1.6) • Reference Case (FDWR = 17%) • Assemblies Area R-value =54.31 W/K • Attic 100 m² 6.99 m²K/W (R40) • Window 25 m² 0.63 m²K/W (U=1.6) • Benchmark Case (FDWR = 17%) • Assemblies Area R-value • Attic 100 m² ??? m²K/W (???) • Window 18 m² 0.63 m²K/W (U=1.6)

  28. Simple Trade Off • Option 3 Example: Trading Window Area for Reduced Attic Insulation • Existing Case (FDWR = 12%) • Assemblies Area R-value =38.6 W/K • Attic 100 m² 6.99 m²K/W (R40) • Window 18 m² 0.63 m²K/W (U=1.6) • Reference Case (FDWR = 17%) • Assemblies Area R-value =54.31 W/K • Attic 100 m² 6.99 m²K/W (R40) • Window 25 m² 0.63 m²K/W (U=1.6) • Benchmark Case (FDWR = 17%) • Assemblies Area R-value =54.31 W/K • Attic 100 m² 3.92 m²K/W (R22) • Window 18 m² 0.63 m²K/W (U=1.6)

  29. Reaching ERS 80 • Validation • In Progress using HOT2000 V 10.5 • Preliminary Results • Modeled All 11 houses • … without HRV • 2 Climate Zones • Addressing Issues • Slab-on-grade • Cathedral ceiling • Not reached ERS 80 • Implications will be communicated to the CCBFC

  30. Reaching ERS 80 • Energy improvement • From ERS 72 to 78 • Reduction in total energy use: 29% • Reduction in space heating alone: 41% • From ERS 72 – ERS 80 • Reduction in total energy use: 35% • Reduction in space heating alone: 53% • From ERS 78 – ERS 80 • Reduction in total energy use: 9% • Reduction in space heating alone: 18% (Based on 6500 houses in NRCan Ecoenergy database, not energuide homes and not retrofited. Built 2005 to 2010)

  31. Reaching ERS 80 • Discussions on how to close the gap from current proposal • Options for reaching ERS 80 (with 2.5 ACH) • 19.2” or 24” framing for min requirements • Exterior insulating sheathing on the walls • 94% efficiency furnaces (etc) • HRV mandatory • Higher HRV efficiencies • Grey water heat recovery • Basement insulation, • Addressing insulation under floors (crawl spaces, walk-outs) • Options for reaching ERS 80 with 1.5 ACH • blower door test mandatory

More Related