1 / 20

TEC pilot run status

TEC pilot run status. CMS Tracker week 2410/03 D. Contardo. Goal : test TEC module production rate capabilities - 15 R6 modules assembled on Brussels Gantry and bonded in Aachen I 15 R7 modules assembled on Lyon Gantry and bonded in Strasbourg

liora
Télécharger la présentation

TEC pilot run status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TEC pilot run status CMS Tracker week 2410/03 D. Contardo • Goal : test TEC module production rate capabilities • - 15 R6 modules assembled on Brussels Gantry and bonded in Aachen I • 15 R7 modules assembled on Lyon Gantry and bonded in Strasbourg • Detailed presentation given at the Gantry and TEC meetings • By O. Bouhali, J.M. Brom, R. Haroutunian, T. Franke

  2. Pilot run for R6 modules Assembly of R6 modules at Brussels Gantry : - 2 real modules (04/09/03): Status valid, presently on DB - 2 dummy modules just before the pilot run: valid - 11 modules between 6/10 and 9/10 (4days): TEC pilot run ended due to a HD crash! 2 positions on 2 plates used 1 plate with leak under sensors (change of kapton thickness)

  3. Distribution of all plate 61 modules: Measured-Nominal (m) Sensor 1 Sensor 2 All positions are good

  4. Measured angles (mdeg) Sensor 1 Sensor 2 Summary of qualification for 13 glued modules : 3 modules glued on plate with leaks out of specifications (plates will be modified) 10 modules within specifications

  5. Bonding and test of R6 modules at Aachen I and III • Modules shipped to Aachen I on 15th of October • powerbonds and first module fully bonded on 16th of October after necessary reprogramming of the bonding machine due to missing fiducials on the pitch adapter • 17th of October: next 3 modules fully bonded • 20th of October: last 6 modules fully bonded • Pitch adapter bonding: no problems • Sensor–sensor bonding: failures (lift-offs) on source bonds (~1% ) preferentially at the end of the bond row (~ strip number 400)

  6. IV Curves • From database • (300V & 450 V) • With powerbond only • Fully bonded

  7. IV Curves II • From database • (300V & 450 V) • With Power Bond only • Fully bonded

  8. Summary Table • Almost no bonding faults (candidates for only 2 opens and 3 channels shorted) • No additional pinholes with respect to sensor tests • Typical duration of a full module test including the preparation of the module in the testbox is about 25 minutes All 8 modules of grade A quality

  9. Cooling Test of 1 R6 module black curves room T before cooling blue curves -20° red curves room T after thermal cycle 5 more modules in the cold box in Aachen with similar fine behaviour

  10. Pilot run for R7 modules Assembly of R7 at the Lyon Gantry : pre-pilot run : one plate of 3 R7 modules pilot run : - 1 plate per day using the 3 R7 modules - 5 consecutive days for production (one R7 plate available at that time) only one noticable problem : an hybrid can’t be picked by vacuum with the bridge (still 3 modules where glued uring the process) Summary : All 18 modules are wihin the specifications

  11. XY precision for sensors Position of sensor markers for the 18 modules compared to their expected position Red boxes have 10µm side and centered on the expected positions.

  12. XY precision for sensors Overall shifts for sensor markers wrt exp. Position in µm X Y

  13. Sensors angular positionning precision Reference axis = frame pins axis a) Initial angle of sensor (m1-m2) on supply plate with reference axis, b) Final angle of sensor (m1-m2) on assembly plate with reference axis c) Angle between sensor : 14 over 15 modules have Dteta < 5m°

  14. Gantry assembly time per plate • With 1 operator : 1h30’ • Preparation : 30’ • - Check sensors and hybrids from DB, Arc test hybrids • Clean frames, Glue 1D label and register module composition in the DB • Put sensors frames and hybrids on plates • prepare glue • Gantry assembly : 30’ • start assembly prog, glue test by eyes, all other gluiing steps • Post-assembly : 30’ • position monitoring after curing • update de la DB • - mounting modules on support plates • - bias glue put by hand • - put modules in transport box and initiate DB transfer. • With 2 operators : 3 types of operation in parallels : 45’

  15. Bonding of R7 modules at Strasbourg 30200020000278 30200020000279 30200020000280 30200020000281 30200020000282 30200020000283 30200020000284 30200020000285 30200020000286 30200020000287 30200020000288 30200020000289 30200020000290 30200020000291 30200020000292 Reception of 15 modules Searching on Data Base : data of Si sensors - I V curves - bad strips

  16. Bonding 6 modules are bonded 1. ARC tests (5' for fast test only, 10' for all tests) : 5’ 2. Bonding of the bias rings for the ARC tests and the IV 15’ curves and bonding of the 11 bonds form Si to Si and 11 bonds from PA to Si. Results : (will be done in the Data Base) 7.0 +/- 0.7 g on Pa – Si 7.0 +/- 0.4 g on Si – Si 3. ARC test and IV 5’ 4. Bonding of the entire Module. 40’ Immediate repair of the obvious unbonded channels. Number of repairs : Si - Si : 12 bonds / 3072 bonds PA - Si : 15 bonds / 3072 bonds 5. ARC test including LED illumination. 30’

  17. I V curves with temperature compensation 30200020000283 30200020000288 Red and blue sensor currents (nA) pink sum of the 2 sensors currents (nA) black our measurements Summary : - Bonding and test time per module 1h30 (test procedure can be reduced) - All bonded modules are good

  18. Conclusions from the TEC pilot run • From the Gantry centers : • - Few problems related to first experience of production run (R6 plates to be adjusted • to final kapton in Brussels) • the full time per plate assembly was measured to be about 1h30, • possibility to do in parallel the preparation tasks and the Gantry gluing when dealing with 2 plates and with 2 operators (reducing the prodution time to less than 1h). • A stable production of 4 plates per day to fulfill nominal needs for a 1 year production should be reached in the coming months. There is clear room for yield improvement to 5 plates if 2 operators are working in parallel. • From the Bonding centers : • - The bonding time including all qualification steps was found to be 1h30 • A nominal rate of 6 modules bonded per day was reached in Aachen and Strasbourg. There are ways for rate improvements (depending on failures, plus reduction of the number of tests in the process). • The present tests of the 16 first bonded modules : ARC read-out and IV curves showed that the modules are of high grade quality. • First 6 modules tested down to -25° with perfect pedestals, noise, pulse shape and no additional dead channels.

  19. Readiness and next months plan for mass production • Tools preparation status : • - Frame assembly jigs are all ready • Bonding jigs are all ready apart for R1, Hambourg will receive R1 prototypes • next week to prepare the jigs • Gantry all plates are there, R1, R2, R4, R7 and R6 plates are commissionned • Plan for next months : • - Finish commissioning of plate R3 and R5 at the Brussels Gantry, study commissioning • of some existing plates on the second gantry for production back-up. • - Commission new design with rigidifiers (successfully tested in Aachen) • simple grooves milled in the plates at the rigidifier position plus test of • procedure on the gantry gluing dummy and real modules. • (still production can start for different geometries with gluing of rigidifiers by hand) • - Built new modules to complete the TEC system test (8R1, 8R2, 7R3, 4R4, 8R5) • (one TEC read-out loop is 2 to 3 petals) • Needs hybrids with pitch (before final version) : • 6 x R1N(6D), R1S(6U), R2N(6D), R2S(6U), R4(4U), R5N(6D), R5S(6U) • 10 x R6(4U), R7(4U)

  20. Ring 7