1 / 11

Type-I Electrical Services Status and Plans

Type-I Electrical Services Status and Plans. Jason Nielsen Santa Cruz Institute for Particle Physics University of California, Santa Cruz. U.S. ATLAS ITk Pixel Workshop September 6, 2019. Introduction. Type-I services are part of on-detector services activity

lwhite
Télécharger la présentation

Type-I Electrical Services Status and Plans

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Type-I Electrical ServicesStatus and Plans Jason Nielsen Santa Cruz Institute for Particle Physics University of California, Santa Cruz U.S. ATLAS ITk Pixel Workshop September 6, 2019

  2. Introduction • Type-I services are part of on-detector services activity • In international project: L3 activity coordinators are T. Flick, J. Nielsen • In US ATLAS project: L3 manager is M. Hance, IC is J. Nielsen • Other Type-I services contacts: S. Eisenhardt (EC), ?? + D. Alvarez (OB) • Scope is all electrical services running from PP0 to PP1 (except Env. Monitoring) • LV module power • HV sensor bias • LV MOPS (née DCS controller) power • CANbus DCS data • Temperature interlock • Low-power command line (to be discussed) • Electrical services follow SP chain via inner system PP0 U.S. ATLAS ITk Pixel Workshop-- 2019-09-06

  3. Type-I Connector Baselines • At PP0 • Samtec UMPT power blades • carries LV in PP0 design • >12 A, > 1500 VDC • Samtec TLH/SLH strip (2mm) • Carries HV, DCS, Tilock in PP0 design • Sneaks underneath twinax bundle • Open to other options on PP0 • At PP1 • Petr Sicho’s studies of custom connector (Glenair) • We need to be able to crimp the 36 AWH solid HV wires and 16 AWG stranded LV wires at PP1 • Or we will need another cable termination board U.S. ATLAS ITk Pixel Workshop-- 2019-09-06

  4. U.S. ATLAS ITk Pixel Workshop-- 2019-09-06

  5. U.S. ATLAS ITk Pixel Workshop-- 2019-09-06

  6. Grounding & Shielding Considerations • Proposal to use CANbus shield as low-impedance tie between PP0 and PP1 • In other parts of the G&S document, “low transfer impedance” defined as 50 mΩ/meter, but that is a shielding performance quantity • DC impedance requirement is <10Ω • All we need is the spiral-wrap foil shield of the CANbus pair • Measured in our 3-m prototypes to have R<1Ω (includes drain wire helping connect wraps) U.S. ATLAS ITk Pixel Workshop-- 2019-09-06

  7. Cable Specifications and Vendors • Bare copper requirement (vs. silver-plated) is a challenge for small-gauge wires • Low-voltage power: 16 AWG (7/24) or 18 AWG (7/26) TWP, thin PEEK • Product from Dacon for 250-μm PEEK wall • High-voltage sensor bias: 36 AWG solid TWP, quad-dipped Kapton (25-μm) • Stock from MWS, as for IBL. Mechanical stripper to remove insulation, tested to 3kV • I would like to know about the IBL experience and switch to 32 AWG for build • VMOPS, interlock: 32 AWG () TWP, thin PEEK • Product from New England Wire with 115-μm PEEK wall. Impedance uncontrolled for this TWP. • CANbus: 32 AWG () TWP, thin PEEK, Al/Kapton foil shield • Product from New England Wire with 300-μm PEEK wall, designed for 100-Ω impedance • No silver, no polyester -- whew! • Low-voltage cables all rated to 300 V, not 1000 V • Need six weeks for final delivery of materials U.S. ATLAS ITk Pixel Workshop-- 2019-09-06

  8. Design of Termination Region • Prototype cable termination board designs exist, with footprint about 3 times as large as the SLH connector, 2 times as large as the UMPT terminal. • Experience with prototype testing boards gives confidence in connector stability in board-to-board connection; right-angle connectors may become available • Need to look at reducing termination board size in very tight PP0 physical space • The connector design and heterogeneous bundle suggest a cable termination board solution at the PP0 interface (and perhaps at PP1) • In the ”dual-ended” PP0 design we have two separate sub-bundles U.S. ATLAS ITk Pixel Workshop-- 2019-09-06

  9. Electrical Tests • Connector testing: high current and dielectric withstanding voltage • Produced special testing boards for qualifying Samtec connectors • Tested pulling pins, and withstanding voltage increases linearly • Cirris Systems High-Voltage Tester (4250) • Adapter boards designed for bundle -to- termination-board -to- tester or bundle-to-tester • Define tests and store results in PC for any bundle design • We expect the specific tests will be similar to IBL testing procedures • The mix of local and ITk database records is not defined yet • It will be a good chance for us to exercise database design and interfaces U.S. ATLAS ITk Pixel Workshop-- 2019-09-06

  10. Mechanical Tests + Irradiation • Mechanical flexibility tests underway • Temperature cycling (10 full cycles to start, not 420!), followed by visual inspection, bend tests, and withstanding voltage tests • Possible CTE mismatch for PEEK/Cu not a problem because PEEK will slide along Cu • Expect any expansion will be taken up near PP1 because bundles must be constrained in radius along the cable trays • We expect the liquid crystal polymer housing to be very radiation hard • No ATLAS results yet from irradiation campaigns • Gold-plated contacts are the standard; matte tin available for some models • Alignment of the miniature connectors is a challenge • Weld tabs (phosphor bronze) in precision slots may help with some models, but it will be difficult to have a multi-connector termination board U.S. ATLAS ITk Pixel Workshop-- 2019-09-06

  11. Summary • Electrical components are well advanced, good interaction with PP0 • Excellent interaction with vendors • Trying to learn from IBL production experience for assembly procedures • Cable routing needs some work, even if bundle is dominated by twin-ax • On track for delivery of 19-2 prototype, except for unknown ”PP1” interface • Would we consider using a strip detector Glenair connector for prototype? • On-Detector Services PDR is still scheduled for late October • Dependent on finding a solution for Type-I service routing in Outer Barrel • Dependent on giving details of solution for service+cooling routing in Inner System U.S. ATLAS ITk Pixel Workshop-- 2019-09-06

More Related