An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SEM and BTV renovation E. Bravin, BI-LIU review, 3 October 2013

  2. Specifications • Consolidation of SEM (CPS) and BTV (SPS) consists of replacing the obsolete electronics with new one • CPS SEM new design in common with LINAC4 • SPS BTV deploy the system used in the CPS and LHC since many years • No new specifications, the system will have performances equal or better than old system • New SEM electronics covers and extends the intensity range of the old electronics

  3. Status of Development • SEM • Design finished • Electronics cards ready • Installation started • BTV • No new design needed • Electronics cards available since long time • New (tube) cameras ready

  4. Installation and Commissioning Plan • SEM • Whole PS complex upgraded simultaneously • All machines have the same priority • Hardware commissioning foreseen before startup 2014 followed by commissioning with beam • Grid for septum 42 (LS2) ? • BTV • Routine operation, hardware check sufficient to validate the new systems • BA80 cabling not done in LS1

  5. Budgetary Requirements • BTV SPS • ~50 kCHF 2013/2014 Cabling • ~30 kCHF 2014/2017 Cameras and spares • Difficult to procure VIDICON tubes, it may become much more expensive to maintain tube cameras • BTV PSB • BI.MTV30 (L4C), BT.MTV10 and BT.MTV30 move (2GeV) 85k 2014, 10k 2015, 13k 2018 • SEM CPS • Project “finish” end 2013 (old consolidation budget) • Cabling/installation for L3 delayed to 2014 • 88k foreseen for 2014 (most already used in 2013) • Budget for grid in septum 42 to be defined