An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Progress on and Status of theForward Multiplicity Detector Kristján Gulbrandsen Niels Bohr Institute Kristján Gulbrandsen, NBI

  2. Assembly and Transport FMD3 FMD2 CERN Kristján Gulbrandsen, NBI

  3. Arrival and Unpacking • Shipped and unpacked • TPC cleanroom used for testing and verification Kristján Gulbrandsen, NBI

  4. Installation • Case carried to main building • Brought to pit via elevator • Crane put case on scaffolding • Unpacked and carried to IP • Installed in halves around beampipe on temporary support • Cabled up Kristján Gulbrandsen, NBI

  5. Issues • Some readout cables severed during packaging for shipping • Some fixable module damage • Damaged bonding wires • Damaged hybrid connector • HV patch cable connector damaged • Changed to different type connector for FMD2 • Some power cable cross-sections increased • -2V supply for FMD3 had cross-section doubled • Cables for FMD1 and FMD2 quadrupled in cross-section (cables also twice as long) Kristján Gulbrandsen, NBI

  6. Testing • Commissioned using DAQ and Trigger subsystems • HV from CAEN power supply, LV from test power supplies (not CAEN) • Commissioning testing showed noise consistent with lab tests • Some optimization can be performed • Should be done after we have final LV power supplies Kristján Gulbrandsen, NBI

  7. DCS • PVSS control/monitoring of HV, LV, and detector implemented • Some debugging required - HV control has been used • Alexander Kurepin of T0 group collaborating to finish DCS work Kristján Gulbrandsen, NBI

  8. Remaining Tasks • Install FMD2 on June 24 • Finish A-side cabling • FMD2 testing at service chariot - end of July after TPC is in IP • FMD1 is under construction, installation - early October • DCS integration from early August • Commissioning with CAEN LV power supplies (when?) • Install final trigger configuration • Final TTC fiber • Fan-in Fan-out Kristján Gulbrandsen, NBI