1 / 11

C. Noshi/RASC, Kyoto Univ.

AIV (Assembly, Integration, Verification) for BepiColombo MMO Payoads Y. Kasaba, T. Takashima, H. Hayakawa (JAXA/BepiColombo Project Office). MMO Mercury Magnetospheric Orbiter. C. Noshi/RASC, Kyoto Univ. Overall Schedule (Mar 2006). ESA JAXA both. Now!!.

malia
Télécharger la présentation

C. Noshi/RASC, Kyoto Univ.

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. AIV (Assembly, Integration, Verification) for BepiColombo MMO Payoads Y. Kasaba, T. Takashima, H. Hayakawa (JAXA/BepiColombo Project Office) MMO Mercury Magnetospheric Orbiter C. Noshi/RASC, Kyoto Univ.

  2. Overall Schedule (Mar 2006) ESA JAXA both Now!! MMO-STM at ESTEC (by ESA plan) MMO-FM at ESTEC (by ESA plan) Launch 2013.8B Definition phase [old Ph-A/B] ESA MMO&MCS STM test ITT Implementation phase [old Ph-B/C/D] Integrated Test & AIV RFP MMO-STM 2009.5M Is it OK? Install of STM 2008.8E Install of FM 2010.3B Env. Test 2010.7B-9E “EM” & “Sub-system level reviews” can be negotiable each by each. MMO-EM 2010.6B MMO-FM 2011.9B Mercury orbit 2019.8 ~ 2years Payload Selection Component Dummy QR 2011.8E STM test 2008.8E AIV 2010.11B-2011.7E AO 2008.7M-2009.5E @JAXA/ESTEC Sub-Env test 2010.7B-9E CDR 2009.6E MIC/EIC 2010.3B-6B PDR 2007.12E PRR 2005.3B FM(Ph.C/D) PM (Ph.B) JAXA (ISAS) Technical study Pre-PM2 Pre-PM1 PRR=Preliminary requirements Rev. PDR=Preliminary Definition Rev. CDR=Critical Design Rev. QR=Qualification Rev. (Calendar year)

  3. STM Schedule (Mar 2006) <Mile Stone> Payload STM: submission to System 2008 8E MPPE, MSASI (Hood only?), WPT-S, MEFISTO-S, MAST Payload STM test should be done by 2008 Aug. MMO-STM test in ISAS will be end in 2009 May.

  4. EM Schedule (Mar 2006) <Mile Stone> Payload EM integration test schedule is TBD PWI: from 2007 Oct. ?? MGF: from 2008 Feb. ?? Others: from 2008 May ??

  5. Software Schedule (Mar 2006) <Mile Stone> Software development does not have major milestones. Parts related to EM test will be synchronized to the System.

  6. FM Schedule (Mar 2006) <Mile Stone> Payload FM: submission to System 2010 March Payload FM: Environment test 2010 7B-9E There might be no chance to remove payloads at ESTEC.

  7. EM Schedule for MDP (Mar 2006) ~Plan: 13 weeks ~ (FM: less) MDP/Instrument tests by “Emulators with SpW” ? MDP/Instrument tests by “Emulators with SpW” ? Integration test plan for MDP-2 (& MDP-1) with PWI & MGF Details will be discussed in PWI local meeting in Kanazawa in this week.

  8. Definition of the Schedule, Test location, and Responsibility/Members Definition of the procurement items from each team to each team Definition of the test items in Component-level test in MDP-level test in System-level test Definition of the Test environment in Component-level test in MDP-level test in System-level test Action Items in 2006FY It will be defined as “MMO Payload Test Plan” (Draft version is in I-IRD etc.) by JAXA/BepiColombo Project Office. Please discuss in each team, and clarify your Action Items & Request to System / Other teams in CDD and/or Progress report.

  9. EM/FM: Test Configuration Concept Spacewire Ether etc. PC Sensor SpaceCube etc. Board/unit level test @ each institution GPIB etc. Signal Generator MDP level test @ ISAS / MHI etc. Ether etc. Spacewire Spacewire SpaceCube etc. PC Sensor MDP / MDP emulator GPIB etc. Signal Generator System level test @ ISAS (/ ESTEC / Launch site) Ether etc. Spacewire IEEE1553B? TM/TC Ground System PC Sensor MDP > DMC (TLM only!) GPIB etc. Signal Generator

  10. SpaceCube: present status • SpaceWire Analyzer on SpaceCube • Under development, Finished until October (distribution or purchase : after Oct. with soft) • Analyzer will be distributed by MMO-project with SpaceCube • GSE • Using SpaceCube with SpaceWire Analyzer • Middle ware (User I/F) will be define next year SpaceWire Analyzer on SpaceCube RMAP packet content 001101110111 Sensor with SpW I/F SpW TLM COM PC RS232 RMAP Target RMAP HOST

  11. Mini-PC with VGA, USB, Ether, CF-I/F SpW port : 3 ports OS : T-kernel (TRON) Language : C (C++ ?) Development : Cross-Compiler on Linux SpW I/F : special API for SpW I/F prepared SpW user program : Sample program that is to read and wite SpW packet attached. If necessary, user can develop programs using APIs for SpW. Space-Cube (TBC) for GSE

More Related