1 / 13

Basingstoke Major Improvement Schemes - Enhancing A33 Corridor

Hampshire County Council is undertaking a £10.6 million highway improvement scheme to increase capacity and reduce congestion on the A33 in Basingstoke. The project includes widening approach roads, upgrading roundabouts, improving pedestrian and cycle facilities, and drainage works. The scheme is funded by the Enterprise M3 Local Enterprise Partnership and local contributions.

mariaray
Télécharger la présentation

Basingstoke Major Improvement Schemes - Enhancing A33 Corridor

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Major Improvement Schemes in Basingstoke 1. Overview A340 Aldermaston Road Improvements - complete A33 Popley Way Junction Improvements - complete A33 Thornhill Way A30 Winchester Road Roundabout Improvements – complete A33 Ringway Roundabout Improvements – in progress A33 Crockford Roundabout Improvements – in progress A33 Binfields Roundabout Improvements – in progress A33 Thornhill Way Junction Improvements – starting 2019 A340 Thornycroft Roundabout Improvements – starting 2019

  2. A33 Corridor Improvements, Basingstoke 2. Introduction Hampshire County Council started work in August 2017 to construct a £10.6 million package of highway improvements to increase capacity and help reduce congestion on the A33 in Basingstoke, between the Ringway and Binfields roundabouts. Dyer & Butler are delivering the scheme on behalf of Hampshire County Council and the work is due to be complete in early 2019. The scheme will also help ease congestion in two of Basingstoke’s major employment areas at Chineham and Hampshire International Business Parks, as well as aid any potential expansions and future job creation. Improvements include: • widening the existing approach roads • road widening works on the roundabout • installation of traffic signals on the roundabout • upgrading of existing pedestrian and cycle facilities and connections • drainage works This scheme has been funded by the Enterprise M3 Local Enterprise Partnership and local contributions.

  3. Ringway Roundabout Improvements 3. Works Update Ringway Roundabout Works are nearing completion at Ringway Roundabout with the finished surface, white lines and new roads signs all completed. Top soiling, final clearance works and installation of the traffic lights are due to be completed in the coming months. The traffic management setup will remain largely the same with the requirement for off peak lane closures up until the end of April.

  4. Ringway Roundabout Improvements 4. Progress photos Setting out traffic management Locating existing utility cables Trench for new drainage pipes Levelling new footpath

  5. Ringway Roundabout Improvements 5. Progress photos Night time surfacing work on south bound approach to Ringway Roundabout New tactile paving for new crossing point Setting out traffic management for night time work New footpath

  6. Crockford Roundabout Improvements 6. Works Update Crockford Roundabout Final services diversions are currently taking place and installation of the new traffic signal and street light ducting is progressing well. The current traffic management layout will largely remain the same for the next month, after it will be adjusted to enable works to start on the east traffic island and re-surfacing works to be carried out. Night time lane closures and road closures will be required towards the end of the spring to enable surfacing works to be undertaken. As usual notification will be provided for these closures and appropriate diversion routes will be put in place.

  7. Crockford Roundabout Improvements 7. Progress photos Top soil being removed Crockford Pond being drained New kerbing being laid New surfacing works

  8. Crockford Roundabout Improvements 8. Progress photos Crockford Lane – kerbing completed, drainage works to commence shortly Overview of Crockford roundabout – from the south-east Crockford Lane – footway diversion for drainage works Preparing for new kerbs and drainage

  9. Binfields Roundabout Improvements 9. Works Update Binfields Roundabout Work to divert service pipes and cables will shortly be undertaken to enable road widening to start in the spring. The current traffic management layout will largely remain the same for the next couple of months, after which it will be adjusted to utilise the newly widened areas to enable work to start on the central roundabout itself.

  10. Binfields Roundabout Improvements 10. Progress photos Top soil being removed Roundabout widening and preparation to divert utility cables New kerbs being laid Top soil being removed

  11. Binfelds Roundabout Improvements 11. Progress photos Roundabout widening and preparation to divert utility cables Roundabout widening and preparation to divert utility cables Roundabout widening and preparation to divert utility cables Roundabout widening and preparation to divert utility cables

  12. Environment 12. Ecology and Drainage Crockford Pond has been cleared of debris and silt, and enlarged, to help drain the A33 and Crockford Roundabout. This required the removal of a newt habitat in the summer and autumn months, thereby avoiding the amphibian breeding season of March to June. At Binfields Roundabout the new drainage network will comprise of an underground attenuation system, which during significant rainfall events will hold water and slowly release into an outfall in a controlled way, thereby avoiding potential flooding situations and minimising impacts on the environment.

  13. A33 Corridor Improvements, Basingstoke 13. More Information For more information on this scheme and to keep up to date with progress visit: www.hants.gov.uk/transportschemes Contact us: • Name: Hampshire County Council Strategic Transport • Email: major.schemes@hants.gov.uk • Phone: 0300 555 1388 (0300 555 1390: Minicom) • Address: Economy, Transport and Environment Department, Hampshire County Council, The Castle, Winchester, SO23 8UD • Name: Dyer and Butler Ltd. Ellena Greenfield, Stakeholder Engagement Officer • Email: ellena.greenfield@dyerandbutler.co.uk • Phone: 02380 742 222 • Address: Dyer and Butler Site Office Crockford Lane, Off Carpenters Road, Basingstoke, RG24 9AX

More Related