An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Sharyland Atlas-Driver Load Integration Project – EIR update RPG Meeting

  2. Background • Sharyland Cap Rock/ERCOT load Interconnection Points • Colorado City interconnection (eastern) through Oncor’s Morgan Creek – China Groove 138 kV line • Triangle (western) interconnection through Oncor’s Stanton East – Midland East 138 kV line • Both SU-Gardendale and SU-East Midland load served radial • SPP Transmission Constraints & ERCOT Load Transfer • Previously ERCOT studied approx. 205 MW of load transfer (in 2014) related to evaluate the SU-SPP load transfer (at the request from PUCT related to Docket No. 39070) • The latest total projected load is approx. 417 MW by 2017 (including West Texas Oil/Gas load growth) • PUCT imposed a 150 MW limit on Sharyland’s SPP load • Transfer of incremental new load at DRIVER substation • Load at Driver will be served radial initially (currently filed for CCN) RPG Meeting

  3. Study Area RPG Meeting

  4. Map – Driver Substation RPG Meeting

  5. Reliability needs • Need for additional point of Interconnections • Closing the lines to Stiles and SU-Midland results in N-1 violations • 417 MW transfer (from SPP) requires additional point of interconnections to the ERCOT grid • ERCOT is currently reviewing different alternatives to serve the future load growth RPG Meeting

  6. Questions? March 12, 2010 RPG Meeting