An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TE EPC Bulding 245 schedule update LIU Booster Meeting 07-11-2013 Fulvio Boattini TE-EPC

  2. Building 245 Position TE EPC France Limit for edification France-Swiss border Switzerland TE-EPC - Fulvio Boattini

  3. Building 245 TE EPC 900 Original Design With Booster CV integration HVAC HALL 2000 ACDC1 QPS1 DCDC1 MAGNET TEST AREA CONVERTER HALL DummyLoad 1 DummyLoad 2 DummyLoad 3 Trim1(2t) Trim2(2t) Trim3(2t) Converter2 B (8t) Converter3 B (8t) Converter1 B (8t) 1420 ACDC2 QPS2 Converter1 A (19t) Converter3 A (19t) Converter2 A (19t) DCDC2 2100 QPS3 ACDC3 DCDC3 Stairs CAPS ROOM 1 CAPS ROOM 2 CAPS ROOM 3 TE-EPC - Fulvio Boattini

  4. Building 245 TE EPC Original Design With Booster CV integration Need to find another place for Booster2GeV MPS transformers TE-EPC - Fulvio Boattini

  5. Building 245 TE EPC 900 HVAC HALL 2000 ACDC1 QPS1 DCDC1 MAGNET TEST AREA CONVERTER HALL ~60mt DummyLoad 1 DummyLoad 2 DummyLoad 3 1420 ACDC2 QPS2 Transformer MVCB station DCDC2 2100 QPS3 ACDC3 DCDC3 Booster2GeV transformers. Proposed position Stairs CAPS ROOM 1 CAPS ROOM 2 CAPS ROOM 3 TE-EPC - Fulvio Boattini

  6. MPSB Time Schedule TE EPC No ressources Services Integration (EL, CV,..) GS/SE studies and procurement Building construction May 2016 Building Ready April 2017 Start Commissioning on dummy load October 2013 March 2015 FC March 2014 2 weeks System pre-commissioning on PSB magnets Switching cabinets and cabling installation Power converter commissioning on test magnets Power converter Design & specification Market Survey & Call for tender Power converter Design (supplier) Power converter construction Power converter Installation and cold commissioning Power converter commissioning on test magnets June 2014 FC August 2016 2months System final-commissioning on PSB magnets

  7. MPSB Time Schedule TE EPC No ressources Services Integration (EL, CV,..) GS/SE studies and procurement Building construction May 2016 Building Ready April 2017 Start Commissioning on dummy load October 2013 March 2015 FC March 2014 Switching cabinets and cabling installation 3D building model ready by the end of next week EPC & CV generated a document for HSE feedback on safety issues for the building EDMS 1319960 EPC & CV & EL are working on a electrical requirements EPC working on the switching cabinets and cabling installation EDMS 1312226

  8. MPSB Time Schedule TE EPC Building construction May 2016 Building Ready April 2017 Start Commissioning on dummy load 18kV cabinets installation LV cabinets installation. Lights and other services Lights and electrical cabinets installed Old to new MPS switching cabinet installation Overhead Crane installed Air conditioning and cooling pipes installation Cooling installation Cooling and Conditioning operating Fire alarm system installation Fire alarm system installation

  9. MPSB Time Schedule TE EPC No ressources Services Integration (EL, CV,..) GS/SE studies and procurement Building construction May 2016 Building Ready April 2017 Start Commissioning on dummy load 18kV cabinets installation October 2013 March 2015 FC March 2014 LV cabinets installation. Lights and other services Lights and electrical cabinets installed Old to new MPS switching cabinet installation Overhead Crane installed Air conditioning and cooling pipes installation Cooling installation Cooling and Conditioning operating Fire alarm system installation Fire alarm system installation

  10. Bulding 245 schedule update TE EPC THANKS FOR THE ATTENTION QUESTIONS? TE-EPC - Serge Pittet, Fulvio Boattini