1 / 23

Rickey Green, PMP Manager of Rail Systems Capital Metropolitan Transportation Authority

Rickey Green, PMP Manager of Rail Systems Capital Metropolitan Transportation Authority Office 512-852-7261 Cell    512-563-4891 Rickey.Green@capmetro.org Eighteen years in the Transportation industry: General Railway Signal                       – Engineering Supply;

matt
Télécharger la présentation

Rickey Green, PMP Manager of Rail Systems Capital Metropolitan Transportation Authority

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Rickey Green, PMP Manager of Rail Systems Capital Metropolitan Transportation Authority Office 512-852-7261 Cell    512-563-4891 Rickey.Green@capmetro.org Eighteen years in the Transportation industry: • General Railway Signal                       – Engineering Supply; • Federal Railroad Administration        – Regulatory; • DMJM+Harris Consultant                        – Transportation Engineering (DART) • Capital Metropolitan Transit Authority  – Public Transit Agency (Austin, TX) Education: • MA       – Transportation Management “with a concentration in security management” (American Public University); • BS        – Multidisciplinary Studies (Rochester Institute of Technology) • PMP     – Project Management Professional certification

  2. PRESENTATION OVERVIEW HISTORY PROJECT DESCRIPTION OPERATING METHODOLOGY SIGNALIZATION

  3. Cars Shipped = 41,000 CMTA Rail System CMTA RAIL LINE UPRR RAIL LINE 162Track Miles Crushed Aggregate LLANO Union Pacific RR UP R.R. AUSTIN JCT. GIDDINGS

  4. Public Referendum • November 2004 • 33 Track Miles • 9 Station Platforms • Single Track • 6 DMU’S • Rail Maint. Facility • 16,000 Sqr. Feet PROJECT OVERVIEW

  5. Passenger Corridor Rail Stations Leander Lakeline Howard Burnet Crestview Highland ntown MLK, JR. Downtown Plaza Saltillo

  6. RAIL MAINTENANCE FACILITY 16000 Square Feet

  7. DMU FLEET (6)

  8. UP FLYOVER

  9. CTC Signal Project • Phased Procurement Process. • Design; • Material Purchase; • Installation; • Design Basis Temporal Separation. • 18 Control Points • 9 Intermediate Signals; • 6 Split Point Derails. I

  10. Signal Instrument House Communications. • DCS Interface; • Cellular Network; • Future Fiber.

  11. Typical Quad Gate System

  12. Grade Crossing Upgrade Project 70 Public Crossings in Passenger Corridor; Project Cost Approximately $ 5 Million; Phased Procurement Process. Design; Material Purchase; Installation.

  13. Grade Crossing Upgrade Project Private Crossings in Passenger Corridor (15); Private Crossing Risk Mitigation. Permanently Close Where Possible; Control Access ; Signalize.

  14. Grade Crossing Treatments Capital Metro Is Proactive Approach to Risk Mitigation; Crossing Markings Upgrade; Signage Upgrade; Community Outreach; Operation Lifesaver; Fencing Program.

  15. Existing Quiet Zones Crystal Falls Avery Ranch Ohelen Wooten Ped Anderson Ln Morrow Lamar Blvd Crestview Wooten

  16. Cedar Quiet Zone Cedar Park • BMC • Brushy Creek • Park St. • Discovery Blvd. • FM 1431 • New Hope Rd. • Blockhouse Rd. Ohelen Wooten Ped Anderson Ln Morrow Lamar Blvd

  17. CMTA PH-4 Quiet Zone • Gracy Farm • MOPAC • Adelphi • Oak Creek • Mc Neil Dr. • Mc Neil Merrill Town • Mc Neil Round Rock Phase 4 Ohelen Wooten Ped Anderson Ln Morrow Lamar Blvd

  18. Cherry Wood Quiet Zone • IH -35 @ 38 ½ ST. • Wilshire Blvd. • 38 ½ ST • Cherry Wood • Manor Rd. • MLK Blvd. • 12 th ST. • Rosewood Ave. • Webberville Rd. Ohelen Wooten Ped Anderson Ln Morrow Lamar Blvd Cherry Wood

  19. Cherry Wood Quiet Zone • 7th ST. • 7th ST. • Pedernales ST. • Robert Martinez • Chicon ST. • Comal ST. • Navasota ST. • Waller ST. • IH-35 4th ST. Ohelen Wooten Ped Anderson Ln Morrow Lamar Blvd Cherry Wood

  20. Final Quiet Zone Map Crystal Falls Cedar Park Avery Ranch Phase 4 Crestview Wooten Ohelen Wooten Ped Anderson Ln Morrow Lamar Blvd Cherry Wood

  21. Final Quiet Zone Map • Quiet Zone Establishment • Jurisdictional Authorities • Board Approval (ILA’s) • City of Austin • Design SSM • Coordination FRA • Extend Current Zones Ohelen Wooten Ped Anderson Ln Morrow Lamar Blvd

  22. Community Outreach Ohelen Wooten Ped Anderson Ln Morrow Lamar Blvd

More Related