NORTH MASON SCHOOLS Bond & Levy Proposals

NORTH MASON SCHOOLS Bond & Levy Proposals. Presentation to the Board of Directors David Peterson, Superintendent July 10, 2008. Facilities: The Need. Unhoused Students & Overcrowding MS/HS. Undersized Core Facilities at NMHS. Lack of Gym Space for PE, Athletics, and Community.

maya
Télécharger la présentation

NORTH MASON SCHOOLS Bond & Levy Proposals

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NORTH MASON SCHOOLSBond & Levy Proposals Presentation to the Board of Directors David Peterson, Superintendent July 10, 2008

  2. Facilities: The Need • Unhoused Students & Overcrowding MS/HS • Undersized Core Facilities at NMHS • Lack of Gym Space for PE, Athletics, and Community • Health & Safety Issues • traffic issues at Belfair • leaky walls/roofs • uncontrolled entries and exits • Age-Related Deteriorization of HMS, NMHS, and Hawkins Gym • Code Deficiencies & Outdated (Outlived) Systems

  3. The Facility Committee Recommendation$58,030,000 • Construct a New Middle School ($37,289,116) • Modernize and Enlarge NMHS ($19,076,663) • Repairs/Upgrades at Elementary Schools ($1,650,449)

  4. The Levy/Budget Team’s Recommendation

  5. Is there a less expensive option? • Modernized and Enlarge NMHS ($23,806,277) • Same as “full” proposal • PLUS -- Add 8 classrooms to NMHS • Repair HMS ($8,772,392) • Repairs/Upgrades at Elementary Schools ($1,650,449) • Same as the committee’s recommendation • Include in levy only highly supported items ($1.76/1000) • Basic Levy Renewal • Curriculum and instructional materials (year 2 and 3) • Technology replacement cycle (extended)

  6. Some Cost Comparisons • New Middle School by 2013 (35-50 year building) $37,300,000 • A. MS Major Renovation by 2013 (15-20 year building) 16,600,000B. New MS in 2030 (escalation @ 5% annually) $89,800,000total cost through 2030 $106,100,000 • A. MS “Patch and Paint” by 2012 $8,800,000B. New MS in 2020 $55,200,000total cost through 2020 $64,000,000

  7. Superintendent’s Recommendation (keep total local tax rate under $3.50) 1. Request a Renewal of the Current Levy, plus • Fund Curriculum Renewal Cycle starting in Year 2 • Fund an “extended” technology replacement cycle (add one year to recommended life cycle) 2. Request a $56 million bond ($1.72/1000): the committee’s recommendation with the following changes: • Assume $1.5 million in state match • Use Grapeview funds to build the Sand Hill covered play area

  8. Superintendent’s Recommendation: Levy

  9. Superintendent’s Recommendation: Bond + Levy

  10. Questions?