An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Tampa Electric Company2009 Hurricane Season Preparation Regan Haines Director, Energy Delivery May 6, 2009

  2. Hurricane Preparedness Briefing • Multi-prong approach • System Infrastructure • Coordination • Pre-Storm Preparation Tampa Electric Company - 2009 Hurricane Season Preparation

  3. System Infrastructure • System Hardening • Wood Pole Inspections • Ten Point Plan Initiatives • Three Year Storm Hardening Plan 2007-2009 Tampa Electric Company - 2009 Hurricane Season Preparation

  4. System Infrastructure • Distribution System • Wood Pole Inspection Program – Approx. 39,000 each year • Includes Wind Loading Analysis • Reinforcements & Repairs Tampa Electric Company - 2009 Hurricane Season Preparation

  5. System Infrastructure • Transmission System – 26,000 poles system-wide • Above Ground Inspections • Groundline Inspections • Includes Wind Loading Analysis • Repairs Tampa Electric Company - 2009 Hurricane Season Preparation

  6. System Infrastructure • Storm Hardening – Ten Point Plan Initiatives • Vegetation Management • Transitioning to a three year tree trim for all feeders and laterals • 30% increase in trimming for 2009 • Critical Transmission circuits patrolled semi-annually Tampa Electric Company - 2009 Hurricane Season Preparation

  7. System Infrastructure • Storm Hardening – Ten Point Plan Initiatives • Joint Use Audit • 100% of system has been audited 2007-2008 • Plan to begin next audit in 2010 • Completed Implementation of new GIS • Participate in Joint Research Projects with PURC • Forensics Tampa Electric Company - 2009 Hurricane Season Preparation

  8. System Infrastructure • Three Year Storm Hardening Plan • Distribution construction standard - NESC Grade B • Extreme Wind Pilot Hardening Projects • Saint Joseph’s Hospital • Port of Tampa Tampa Electric Company - 2009 Hurricane Season Preparation

  9. System Infrastructure Tampa Electric Company - 2009 Hurricane Season Preparation

  10. System Infrastructure • Three Year Storm Hardening Plan • Convert Overhead Distribution Interstate Crossings to Underground • Completed conversion of Lois Ave 4kV • Network protectors inspected, tested, and repaired Tampa Electric Company - 2009 Hurricane Season Preparation

  11. System Infrastructure • Three Year Storm Hardening Plan • Transitioned Underground Construction Standard to Stainless Steel • Pilot Submersible Switchgear and “Storm Secure” Break Away OH Services Tampa Electric Company - 2009 Hurricane Season Preparation

  12. Coordination • Planning and Coordination with Governmental Agencies • Hurricane planning with Emergency Operation Centers • Hillsborough County, City of Tampa, City of Temple Terrace, City of Plant City, City of Oldsmar, Pinellas County, Polk County, Pasco County • Coordination with the Tampa Bay Regional Planning Council and Hillsborough County Hazard Mitigation Group Tampa Electric Company - 2009 Hurricane Season Preparation

  13. Coordination • Planning and Coordination with Governmental Agencies • Participation in Storm Preparedness Workshops • US Coast Guard Tabletop • City of Tampa Mock Storm Exercise • Hillsborough County Mock Storm Exercise • City of Tampa Mass Casualty Exercise Tampa Electric Company - 2009 Hurricane Season Preparation

  14. Pre-Storm Preparation • Conducted mock storm circuit patrol training • Review and order storm material inventory • Conduct mock storm exercise • Updated Storm damage model • Reviewed, updated and exercised disaster recovery plans • Reviewed, updated and synchronized circuit priorities with Hillsborough County EOC • ED Mock Storm Exercise • May 14, 2009 - • ED Call-out Group • VP ED and direct reports • Functional ED departments • Customer Service • Corporate Communications • Emergency Management • IT, Telecom, Treasury Tampa Electric Company - 2009 Hurricane Season Preparation

  15. Summary • Inspections & Repairs • Vegetation Management • Storm Hardening Plans • Improved Coordination • Training & Pre-Storm Season Activities • Ready for 2009 Storm Season Tampa Electric Company - 2009 Hurricane Season Preparation