1 / 9

First to Curtail – Last to Curtail Examples December 1 - 2, 2010

First to Curtail – Last to Curtail Examples December 1 - 2, 2010. BA 1. - Firm Service purchased from BA 1 to BA 3 No Seams Agreement Firm Flow BA 1 to BA 3 Flow goes in Last to Curtail for a constraint on BA 1 or BA 3 systems. BA 2. On the Path – Last to Curtail. BA 3. BA 4. BA 1.

melba
Télécharger la présentation

First to Curtail – Last to Curtail Examples December 1 - 2, 2010

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. First to Curtail – Last to CurtailExamples December 1 - 2, 2010

  2. BA 1 • - Firm Service purchased from BA 1 to BA 3 • No Seams Agreement • Firm Flow BA 1 to BA 3 • Flow goes in Last to Curtail for a constraint on BA 1 or BA 3 systems BA 2 On the Path – Last to Curtail BA 3 BA 4

  3. BA 1 • - Firm Service purchased from BA 1 to BA 3 to BA 4 • No Seams Agreement • Firm Flow BA 1 to BA 3 to BA 4 • Flow goes in Last to Curtail for a constraint on BA 1, BA 3 or BA 4 systems BA 2 Wheel Through– Last to Curtail BA 3 BA 4

  4. BA 1 • Intra BA Service sold in BA 2 • No service sold through BA 3 • Seams Agreement between BA 2 and BA 3 • Flow goes in Last to Curtail for a constraint on BA 2 or BA 3 systems BA 2 Parallel Flow Seams Agreement 2 BAs – Last to Curtail BA 3 BA 4

  5. BA 1 • Firm Service purchased from BA 1 to BA 2 • No Service sold through BA 3 • Seams Agreement between BA 2 and BA 3 • Flow goes in Last to Curtail for a constraint on BA 1, BA 2, or BA 3 systems BA 2 Parallel Flow with Seams Agreement – Last to Curtail BA 3 BA 4

  6. BA 1 • Firm Service purchased from BA 1 to BA 2 • No Service sold through BA 3 • No Seams Agreement with BA 3 • Parallel Flow through BA 3 • Flow goes in First to Curtail for constraint on BA 3 system and Last to Curtail for constraint on BA 1 and BA 2 systems BA 2 Parallel Flow 3 BAs – First to Curtail BA 3 BA 4

  7. BA 1 • Intra BA Service Sold • No Service sold through BA 3 • No Seams Agreement with BA 3 • Parallel Flow through BA 3 • Flow goes in First to Curtail for constraint on BA 3 System and Last to Curtail for a constraint on BA 2 system BA 2 Parallel Flow 2 BAs – First to Curtail BA 3 BA 4

  8. BA 1 • GTL identified as Firm on BA 1 • Seams Agreement with BA 2 • Parallel flow through BA 2 • Flow goes in Last to Curtail for Constraint on BA 1 or BA 2 BA 2 Generator Priority – Last to Curtail BA 3 BA 4

  9. BA 1 • GTL identified as Firm on BA 1 • No Seams Agreement with BA 2 • Parallel Flow through BA 2 • Flow goes in Last to Curtail for constraint on BA 1 system and First to Curtail for a constraint on BA 2 system BA 2 Generator Priority – First to Curtail BA 3 BA 4

More Related