An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. THE PORTUGUESE EXPERIENCE WITH “EU” FUNDING MECHANISMS

  2. I. – BENEFITS AND RESULTS OF THE “EU” FUNDING (mostly Cohesion Fund) FOR THE RAIL NETWORK IN PORTUGAL ●Amount of support for the period 1993 / 2006 1993 / 2000: 800 Million Euros ( 40 % CF) 2000 / 2006: 980 Million Euros ( 90 % CF) ● Taxes of support - CF: 80 % - ERDF: 50% - TEN-T: Studies: 50% ; Works: maximum 10 %

  3. ●Main lines upgraded - Beira Alta Line: 200 Kms from West (near Coimbra) to East (border with Spain and then through to Paris) - North Line: 330 Kms from Lisbon to Oporto (renewal still underway) - South Line to the Algarve: around 300 Kms from Lisbon to the Algarve - Douro Line (near Oporto): a section of 40 Kms - Minho Line (near Oporto): a section of 30 Kms - Beira Baixa Line (central connection to Beira Alta): a section of 150 Kms (Works still underway)

  4. ●Kms of line upgraded Nearly 1 000 Kms ●Kms of new line constructed 30 Kms ●Nature of the investments and improvements - Renewal of the track for higher speeds - Doubling and quadruplicating some sections - Strengthening and construction of new bridges and viaducts - Electrification - Electronic signalling, automatic speed control and telecommunications - Elimination of level crossings - Freight terminals

  5. ●Main objectives - Better transport supply with greater quality and comfort - Decrease in travel times - Increase in speed - Increase in capacity and liability - Increase in safety - Operational costs reduction and increase in productivity ●Increases in speed, safety and capacity - Increases in speed to 120/140 Kms /H and up to 220 Kms /H in the main itineraries - Reductions in travel times of around 20~30 % - Increase in safety by the closure of level crossings, construction of viaducts, new signalling and automatic speed control - Increase in capacity by duplicating and quadruplicating some sections and installing new electronic signalling

  6. II. – CONDITIONS REQUIRED AND MAIN RESTRICTIONS ▪ Lines must be included in the “Trans European Network” ( for CF and DG TREN) ▪ Environmental evaluation concluded and approved by the environment Authorities ▪ Some of the works must have been already commited ▪ Compatibility with EU politics ▪ EIB approval, if it is the case ▪ Consistent Cost/Benefit analysis ▪ Complete description of the works, credible calendar and accurate estimation and discrimination of costs per nature (components) and category ▪ Definition of physical indicators ▪ Availability of funding in the fraction attributed to the Member State

  7. III. – DIFFICULTIES WITH ● Approval of the applications - addicional information and documents - questions about the cost/benefit analysis - calendars - cost estimates - period of eligibility ● Monitoring and reporting - claims - biannual reports - specific reports

  8. ● Closure of the processes - formal acceptance of the works - complete portrait of the project life - consistency and coherence of all the information provided - definition of the final costs and evaluation - final costs of the contracts

  9. IV. – MAIN PROBLEMS AT PRESENT ● Public procurement and tendering - international advertisement in the JOCE and previous announcement, stating the financing fund - enough publicity - obedience to the principles of “transparency” of the procedures, “free market” rules and “non discrimination” - non acceptance of procedures by “direct negociation” - amount of addicional works

  10. ● Environment - fulfilement of all the phases of the evaluation of impacts and approval by the environment authorities - implementation of the minimization measures of the impacts ● Calendars - progress of the works - claims - reports - final claim - final report ● Audits - several types - several entities