1 / 25

Joint coordination meeting for the PS Complex 18/10/2018

Joint coordination meeting for the PS Complex 18/10/2018. Update from previous presentation. Linac4 Connection J. Coupard EN-ACE. Facility Coordinators. Connection of the Linac4 Facility Coordinator: Julie Coupard EN-ACE Activity Technical Coordinator: Simon Mataguez BE-OP

meris
Télécharger la présentation

Joint coordination meeting for the PS Complex 18/10/2018

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Joint coordination meeting for the PS Complex 18/10/2018 Update from previous presentation Linac4 Connection J. Coupard EN-ACE

  2. Facility Coordinators • Connection of the Linac4 • Facility Coordinator: Julie Coupard EN-ACE • Activity Technical Coordinator: Simon Mataguez BE-OP • LIU Machine Coordinator (LIU-PSB): Gian Piero Di Giovanni BE-OP • Linac2/Linac3 (out of the L4 connection) • Facility Coordinator: Cristiano Mastrostefano BE-ABP • TSO: Cristiano Mastrostefano BE-ABP • Linac4 (out of the L4 connection) • Facility Coordinator: Luca Timeo BE-RF • TSO: Sebastien Bertolo BE-ABP Collaborative work to ensure the compatibility of activities J. Coupard - Linac4 Connection

  3. Mapping • Upgrade the emittance measurement line LBE • Upgrade and consolidation of the spectrometer measurement line LBS • Removebeam stopper on the PSB injection line BI • Completion of the Linac4 transfer line L4T • Connection of Linac4 to Linac2 transfer line LT (bending magnet LT.BHZ20) • Installation of the new power converters for the transfer lines • New interlock control systems • New switchboard ERD1*7A • New beamloss monitors Consolidation of the transferline LT, LTB • Partial dismantling of the Linac2 J. Coupard - Linac4 Connection

  4. Documents Follow-up with Thomas Birtwistle • Engineering Change Requests • Connection of the LINAC4 to LT.BHZ20 CPS-LJ-EC-0002¦¦ • LT and LTB Transfer Line Magnet Consolidation CPS-LJ-EC-0006¦¦ • Warm Magnet Interlock Controller (WIC) for the LINAC4 Connection to the PS Booster in the Framework of the CONS Project CPS-CIW-ES-0002¦¦ • Installation of New Beam Intensity Transformers in the PSB Injection Lines PSB-BCTF-EC-0002¦¦ • Partial Disassembly of LINAC 2 CPS-LJ-EC-0003¦¦ • Consolidation and upgrade of the power converters of the LT, LTB, LBS and LBE lines PSB-R-EC-0006¦¦ • New ERD1*7A + new power supply infrastructure • Removal of Beam Stoppers BI.STPFA10 and BI.STPSW10 from the BI Line PSB-LJ-EC-0012¦¦ • Removal of LTB.STP10 PSB-LJ-EC-0014¦¦ • Modifications to Vacuum Elements of the LBS Line L3-LJ-EC-0002¦¦ • LBE Line and Infrastructure Upgrade for the Linac4 CPS-LJ-EC-0005¦¦ • New BLMs Installation in the LT, LTB and BI Lines¦¦ J. Coupard - Linac4 Connection

  5. Documents Follow-up with Jean-Pierre Corso • Drawings • L4T/L4Z/L4X Layout : SPLLJ___0005¦¦ Final Configuration • Sector 4.4 : SPLLJLHS0002 ¦¦Current temporary installation of the BSM in L4T (to be removed)  SPLLJLTL0012¦¦Final configuration • Sector 4.5 : SPLLJLTL0029 ¦¦ Current temporary installation for the reliability run with BCT and Dump (to be removed)  SPLLJLTL0013¦¦ Final Configuration • Sector 4.6 : SPLLJLTL0014¦¦ Final Configuration • Sector 4.7 : SPLLJLTL0015¦¦ Final Configuration • Sector 5 : SPLLJLTL0017¦¦ Final Configuration • Sector 6 : SPLLJLTL0019¦¦ Final Configuration • Sector 7 : SPLLJLTL0021¦¦ Final Configuration • LT Layout : PS_LMLTP8001¦¦ Current Configuration (to be partially removed and modified) • Sector 2 : PSBLJ_UI0029¦¦ Differential • Sector 3 : to be produced J. Coupard - Linac4 Connection

  6. Documents Follow-up with Jean-Pierre Corso • Drawings • LTB/LBE/LBS/BI Layout : PS_LMLTB8001¦¦ Current Configuration (to modified) • LTB Layout : PS_LMLTB8002¦¦ Current Configuration (to be modified) • Differential drawings to be produced¦¦ • BI Layout: PS_LMLTB8003¦¦Current Configuration (to be modified) • PSBLJ_UI0007¦¦ Differential • To be produced • PSBLJ_UI006¦¦Differential • !! : temporary configuration with shielding for Linac4 beam tests in 2019 • LBS Layout: PS_LMLTB8004¦¦Current Configuration (to be modified) • Differential drawings to be produced¦¦ • LBE Layout: PS_LMLTB8005¦¦Current Configuration (to be modified) • Differential drawings to be produced¦¦ J. Coupard - Linac4 Connection

  7. Documents Follow-up with Julie Coupard • Work Package Analysis • Connexion du Linac4 pendant LS2 CPS-LJ-IW-0001¦¦ • De-cabling campaigns in the PS Complex CPS-D-IW-0001¦¦ • Cabling campaigns and fibres installation in the PS Complex CPS-D-IW-0002¦¦ • DedicatedProcedures • Linac4 beam test to the new LBE line during LS2 (minutes of meeting in EDMS LIU-PM-MIN-0362)¦¦ • Temporary shielding for the Linac4 beam test in the PS Switch Yard during 2019 • Access Configuration during the Connection of Linac4 (EDMS 2019626)¦¦ J. Coupard - Linac4 Connection

  8. Integration follow-up vs. schedule • Building 363 • Change DN25 to D125 for the chilled water for b.269 ventilation unit (not demi water circuit?)  Serge Deleval au 363 il y a 3 différents travaux liés à 3 différents projets : • Les travaux de tuyauterie ED venant du linac4 dans le cadre du projet de connexion Linac4 – Booster dont le chef de projet est Gabor. • La pose de nouvelles lignes d’eau glacée allant du 363 au 269 dans le cadre du projet de la nouvelle ventilation du 269 dont je m’occupe. (demande d’intégration pas encore faite) • Le remplacement d’une conduite DN25 par un DN125 dans le cadre du renforcement du circuit d’alimentation en eau déminéralisée de Meyrin dont je m’occupe également. • Interface L2-L4 • Emergency and alarm systems to be installed in Linac2 tunnel  Denis Raffourt Waiting for information from Denis J. Coupard - Linac4 Connection

  9. Linear ScheduleIn Work 2018 Previous version Stop L4 end of week49 Co-activities Smoothing of the Linac4 and L4Tearlier Open Days Magnet consolidations adjusted Cooling activities scheduled later Commissioning before beam test J. Coupard - Linac4 Connection

  10. Linear ScheduleIn Work 2018 New version Co-activities Cabling from 400 Smoothing of the Linac4 and L4T Open Days Commissioning before beam test J. Coupard - Linac4 Connection

  11. Linac4 connection scheduleRemaining open points • Compatibility of the Linac3 consolidation works with respect to the Linac4 connection  Alejandro Martinez Selles (SMB-SE) and Roberto Ales Bozzi (EN-CV) Solution defined with SMB-SE responsible for Linac3 works and Linac4 works • Can we group the transport requests for the dismantling of the Linac2 ? No, only orphan equipment will be managed by Simon • Can we group the containers of waste on site ? Being check by Simon • Organization of the VICs • WSS for single Group activities • Activity Technical Coordinator for multiple stakeholders/co-activities J. Coupard - Linac4 Connection

  12. Detailed schedulehttps://cern.sharepoint.com/sites/Projects-Accelerator-Complex-Schedules/Projects.aspx • Equipment to be removed on LT, LTE and LTL lines (Linac2 side) J. Coupard - Linac4 Connection

  13. Detailed schedulehttps://cern.sharepoint.com/sites/Projects-Accelerator-Complex-Schedules/Projects.aspx • Equipment to be removed on LT, LTB, LBE, LBS and BI lines (PS SWY side) J. Coupard - Linac4 Connection

  14. !! No Information received Detailed schedulehttps://cern.sharepoint.com/sites/Projects-Accelerator-Complex-Schedules/Projects.aspx • Equipment to be installed on L4T (Linac4 side) J. Coupard - Linac4 Connection

  15. !! No Information received Detailed schedulehttps://cern.sharepoint.com/sites/Projects-Accelerator-Complex-Schedules/Projects.aspx • Equipment to be installed on LT, LTE and LTL lines (Linac2 side) J. Coupard - Linac4 Connection

  16. !! No Information received Detailed schedulehttps://cern.sharepoint.com/sites/Projects-Accelerator-Complex-Schedules/Projects.aspx • Equipment to be installed on LBE line (PS SWY) J. Coupard - Linac4 Connection

  17. !! No Information received Detailed schedulehttps://cern.sharepoint.com/sites/Projects-Accelerator-Complex-Schedules/Projects.aspx • Equipment to be installed on LBS line (PS SWY) J. Coupard - Linac4 Connection

  18. !! No Information received Detailed schedulehttps://cern.sharepoint.com/sites/Projects-Accelerator-Complex-Schedules/Projects.aspx • Equipment to be installed on LT, LTB line (PS SWY) J. Coupard - Linac4 Connection

  19. Next Steps • Complete new schedule  J. Coupard and Al. • Confirm sequence of work • Confirm detailed schedule with all Groups • Submit the New LS2 Master Schedule Baseline to the LS2C • Complete all ECRs  Authors and Al. • Contact the Configuration Manager (Thomas Birtwistle for cPS underground, BlancaVazquez de Prada for the cPS surface) • Complete integration studies and drawings (Jean-Pierre Corso: ICL meetings every two weeks – Wednesdays morning) • Complete WPA  J. Coupard and Al. • Complete all actions listed in the document • Complete Access Control sequence  J. Coupard and Al. • Confirmation with BE-ICS / HSE-RP / EN DSO • Complete 2019 Linac4 Beam Test Procedure  J. Coupard and Al. • Complete the inventory • Confirm the power supply with James J. Coupard - Linac4 Connection

  20. Weekly sequence of activities Interface Linac2-Linac4-b.363 Julie Coupard EN-ACE / Simon Mataguez BE-OP In collaboration with Luca Timeo (Linac4) and Cristiano Mastrostefano (Linac2-Linac3)

  21. Next three weeks Beam off Monday 15:00 • IMPACT ? J. Coupard - Linac4 Connection

  22. Week 46from 13thNovember Beam off Monday 15:00 • Removal of the L2 access system • Start removal of the shielding around access system • Installation of the new access door • VIC • Demantelementpoint d'accesLINAC.2 4128 • Depose MAD/PAD et chicane entreeLinac2 4150 J. Coupard - Linac4 Connection

  23. Weeks 47from 19thNovember • Removal of the shielding around access system J. Coupard - Linac4 Connection

  24. Weeks 48from 26thNovember • Install temporary door • Install temporary SUSI access system • Commissioning of the SUSI access system • Arrange the temporary “buffer” area J. Coupard - Linac4 Connection

More Related