1 / 59

Project Management Cost and Schedule Nadine Kurita

Project Management Cost and Schedule Nadine Kurita. ANSI/EIA-748-A Standard for Earned Value Management Systems Organization Planning, scheduling and budgeting Accounting considerations Analysis and management reports Revisions and data management (not covered) EVMS surveillance.

mikasi
Télécharger la présentation

Project Management Cost and Schedule Nadine Kurita

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Management Cost and ScheduleNadine Kurita • ANSI/EIA-748-A Standard for Earned Value Management Systems • Organization • Planning, scheduling and budgeting • Accounting considerations • Analysis and management reports • Revisions and data management (not covered) • EVMS surveillance

  2. Contributers • Patricia Mast (LCLS, Aim Corporation - Deltek) • Jeff Chan (LCLS, Aim Corporation - Deltek)

  3. EVMS Organization Organizational Breakdown Structure (OBS)

  4. EVMS Organization • Work Breakdown Structure (WBS)

  5. EVMS Organization • Responsibility Assignment Matrix • In process

  6. Planning, Scheduling and Budgeting (2) • Earned value performance. LUSI Project Management Cost & Schedule (PMCS) system is based on, • B-Factory Project - 2000 Award for the Program and Project Management • SPEAR3 – 2004 Secretary's Excellence in Acquisition Award • GLAST • LCLS • 60% CAMS previous experience in PEP-II,SPEAR3, GLAST and/or LCLS • System requirements • D.O.E. Order 413.3A “Program and Project Management” • ANSI/EIA-748-A Standard for Earned Value Management Systems

  7. Planning, Scheduling and Budgeting • Documentation • LCLS 1.1-018 Control Account and Work Package Planning • LCLS 1.1-020 Project Schedule • LCLS 1.1-021 Cost Estimating • LCLS 1.1-015 Earned Value Management System Description

  8. Cost Estimate Project Director Chief Engineer CAM PMCS

  9. Detailed Cost Estimate Report (DCE) • Product – sample report

  10. Project Schedule DOE SSO Project Director Chief Engineer CAM PMCS

  11. Project Schedule DOE SSO Project Director Chief Engineer CAM PMCS

  12. Milestone Hierarchy • Defined Level 1, 2, 3 and 4 Milestones • Level 1 controlled by DOE HQ • Level 2 controlled by DOE Stanford Site Office • Level 3 controlled by LUSI Project Director • Level 4 controlled by System Manager • Level 1-3 Milestones are under formal CCB control

  13. Work Authorization

  14. Resource Loaded Schedules Integrate schedules

  15. Accounting Considerations • All financial transactions are documented, approved, and recorded properly in the financial accounting system on a consistent and timely basis in accordance with Generally Accepted Accounting Principles (GAAP) and applicable Cost Accounting Standards. • Actual costs are collected from the financial accounting systems and imported into the EVMS each month. • Actuals are collected in the EVMS in four basic cost elements • Labor • Non-Labor (materials, Subcontracts, etc) • Shops • Travel • Direct and indirect costs are recorded in a manner consistent with the budgets.

  16. Analysis and Management Reports • Documentation • LCLS 1.1-015 Earned Value Management System Description • LCLS 1.1-022 Monthly Status and Reporting

  17. Monthly Status and Reporting Project Director Chief Engineer CAM PMCS

  18. Monthly Status and Reporting Project Director Chief Engineer CAM PMCS

  19. CPR Drilldown (Level 2)

  20. CPR Drilldown (Level 3)

  21. CPR Drilldown (CA Level)

  22. CPR Drilldown (Milestone Level)

  23. CPR Drilldown (Labor Detail)

  24. CPR Drilldown (Cost Detail)

  25. Variance Analysis Form

  26. LCLS PMCS Utilities (The Hammer)

  27. BCWS, BCWP,ACWP Report (SPA)

  28. Obligation Report (OSCUM)

  29. Total Float Report Level 3 milestones

  30. 7. Utility tools for CAMS and management. View Gant charts, plot performance, trending reports, CPR drilldown 4. Actual cost and commitments are collected, via code of accounts, at the 3rd or 4th level of the WBS 1. The cost estimating information was transferred to Primavera for initial budget & obligation time-phasing • 5. Accounting files are transferred electronically to the PMCS group and imported into Cobra. Reconciled every month. 2. Progress information is gathered from the CAMS and input into the scheduling system for baseline variance and critical path analysis 3. Progress information is transferred from the scheduling system into the cost processor for Earned Value calculations 7. Utility tools for CAMS and management. View Gant charts, plot performance, trending reports, CPR drilldown • 6. Technical/Cost/Schedule Baseline changes are controlled and documented through the change control process

  31. Surveillance • Continuous self assessment is performed by the project director, and project controls personnel, who are trained in the correct use of the LCLS EVMS, and are held accountable for proper implementation. • Conduct external audit yearly • LCLS 1.1-024 Surveillance of EVMS

  32. Summary • Consistent with the 32 critical criteria as described in ANSI/EIA-748-A • Applying the existing LCLS documentation for • Planning, scheduling and budgeting • Accounting considerations • Analysis and management reports • Revisions and data management • PMCS staff is from LCLS • CAMS have experience with PMCS – training will continue to ensure compliance with the ANSI standard • Have a detailed resource loaded schedule for CD4a deliverables • Detailed resource loaded schedule for the remainder items in process • Need to work on the interface with partner labs • LUSI staff is ready to baseline the project!

  33. End of Presentation

  34. Execution and Control • Project Office Monthly Reporting Contents • Cost Drill Down Approach • Top Level SPA Chart • Cost Report – WBS Level 2 (C/SSR) • System Level Cost Report – WBS Level 3 • Work Package Detail Cost Report • Detailed Accounting Report • Schedule Drill Down Approach • Top Level Cost Report – WBS Level 2 • System Level Cost Report – WBS Level 3 • Work Package Detail Cost Report • Detailed Schedule Report • Traditional Schedule Analysis • Critical Path, Detailed Baseline Schedule Variance Comparison, Milestone Chart

  35. Revisions and Data Management • Documentation • LCLS 1.1-015 Earned Value Management System Description • LCLS 1.1-019 Change Control

  36. Revisions and Data Management Level 4 up to 100K, system Level 3, project office

  37. CCB Presentations • PBCR presentations to the CCB will address the following; • Background • Problem • Solution • Other Solutions Considered • Stakeholders Review • Other System Managers, Int/Inst, QA, Accel Team, QA, Linac Dept Hd (if applicable) • Impact of this BCR (technical, resources, funding, etc.) • Must this come from contingency? • Any impact to L2 or L3 milestones? • Integrated Schedule Analysis • Impact of not approving this BCR • Affected drawings, parts or requirements • Is there anything else we should know?

  38. Revisions and Data Management

  39. BCR Form

  40. Revisions and Data Management

  41. Approval Thresholds

  42. WBS RBS - BE 1 1 2 2 3 3 4 4 5 5 FUND 1 2 3 Resource Breakdown Structure

  43. Accounting Considerations • Direct and indirect costs can be summarized from control accounts into the WBS without allocation of a single control account to more than one WBS element. • Direct and indirect costs can be summarized by the project’s organizational elements without allocation of a single control account to more than one organizational element. • Indirect costs are applied to each project at the current approved annual rates. • Encumbrances are recognized at the point an approved order is placed. Equipment and material costs enter the general ledger through the accounts payable system. • Retroactive adjustments to previously reported actual costs are prohibited. Adjustments are reported monthly, consistent with GAAP.

  44. More on reporting

  45. Milestone Dictionary

  46. Responsibility Assignment Matrix (RAM)

  47. Corrective Action Log

  48. Estimate at Complete (EAC)

More Related