1 / 25

CFAC Review – Title II Design Status

CFAC Review – Title II Design Status. Ove Dyling Assistant Director for Design Conventional Facilities NSLS-II Conventional Facilities Title II Design Status May 8, 2008. Agenda. Design Status Site & Utilities Ring Bldg Structural Ring Building Architectural Ring Building Mechanical

morrison
Télécharger la présentation

CFAC Review – Title II Design Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CFAC Review – Title II Design Status Ove Dyling Assistant Director for Design Conventional Facilities NSLS-II Conventional Facilities Title II Design Status May 8, 2008

  2. Agenda • Design Status • Site & Utilities • Ring Bldg Structural • Ring Building Architectural • Ring Building Mechanical • Design Management Activities

  3. Site & Utilities Design Revisions • Finished Floor Elevation • CD2 Finish Floor Elevation 70’-0” • Present Finish Floor Elevation 74’-0” • Process DI Water System • Relocated Cooling Tower to inside ring • CD2 design de-centralized distribution system • Present design centralized distribution system • Enlarged Cooling Tower Pump Building • Geotechnical • CD2 exploration program • Completed 16 borings • Present exploration program • Completed 75 additional borings

  4. Overall Floor Plan

  5. Ring Building Structural Design Revisions. • Expanded Steel width from 67’-0” to 77’-0” • Optimized concrete slab thickness • Experimental Hall from 18” to 15” • Storage Ring floor from 33” to 27” • Lowered finish floor elevation in storage ring • CD2 1’-4” above Experimental Hall • Presently 8” above Experimental Hall • Finalized top of building steel footing foundation below Storage Ring slab at 20”

  6. RING SLAB Thickness Optimization ( to 27”)Service Building Slab Elevation Effect of slab thickness in 4-50 Hz range: 39” 2.62 nm 33”  2.85 nm 30”  2.97 nm 27” 3.00 nm

  7. Assessment on Column/Footing Interaction Explored the following Options: Footing top @ 20” below mat bottom Footing top @ 36” Footing top @ 72” Footing bottom flush with mat bottom Recommendation: DESIGN with 20-inch separation between bottom of ring slab and top of footing

  8. Detailed Models used in optimizing column footing depthOptimization was based on: Wind Loads and Vibration Transmission

  9. Detailed Models used in optimizing column footing depth

  10. Detailed Models used in optimizing column footing depth

  11. Architectural Design Revisions. • LOB design program deferred to 2010 • Provide Toilet cores if LOB not constructed • Provide all future utility connections to LOB in Ring Building • Design for possible two stories • Design to accommodate future access corridor • Aligned Service Buildings with center of LOB’s • Rotated lattice 22.5 º clockwise • Long Beam lines • Added lowered exterior access corridor • Stairs, Mechanical and ADA lifts between long beam lines

  12. Std Access Corridor By-pass Corridor Extended Experimental Floor Stair, ADA Lift and Material Lift Ramp

  13. 7’-1” 2’-6” Elevation Through Corridor At Beamline

  14. Elevation Through Corridor Between Beamlines

  15. Architectural Design Revisions Cont. • Service Building • Eliminated super doors • Reconfigured entrance labyrinth to Storage Ring • Provide removable shielding blocks to Storage Ring • Eliminated Elevator and provided crane access to second floor • Provided elevated slab on ground level to reduce vibration • Operation Center • Relocated control room to existing NSLS • Computer Room, telephone /data and UPS rooms remain • Future 3rd floor offices relocated to near front entrance as future alternate design

  16. Architectural Design Revisions Cont. • Booster Building • Provided mezzanine to accommodate HVAC units and DI Water Systems • Revised labyrinth for tunnel entry • Revised injection transport region • RF Building • Expanded one bay to accommodate future RF cavities • Expanded mezzanine level to accommodate equipment/Control Room • Finalizing Compressor Building, Helium yard, and Liquid Nitrogen supplementary tank

  17. RF Compressor Building Qualitative assessment completedQuantitative assessment under study Isolation joint

  18. Mechanical Design Revisions Cont. • Fire Protection • Developed Fire Protection strategy for the Experimental Hall to receive waiver of $150,000,000 max loss potential limitation • Eliminated separation walls in Experimental Hall • Requested waiver for two hour separation between Experimental Hall and LOB’s and Service Bldgs in lieu of 3hr • Waiver approved but required additional redundancy for water supply, sprinklers and HSSD throughout • Process Utility Loads • Was a moving target however it is now finalized (final rev)

  19. NSLS-II Process Utility Loads 425 598 2,596 CHW TWR * PCHW/PW split TBD 375* 518 613 157 1,640 50 80 182 300 1,240 970 30 1,160 35 580 300 2,275 1,740 Average AC Power Average Load kVA kW • Injector • Linac • Booster • BRF • xprt lines • SR Inst • Diag & Cntl • Vacuum • Interlocks • IDs • SR PS • Magnet PS • PS Cntls • SR • Magnets Cable Loss PCHW PW HVAC • SR RF • Cryo • SR RF • Controls • Klystrons • Loads • SR Vac • System • Absorbers • Chamber • Expt’l • Instr’t • Absorbers • Expt’l • Instr’t • Controls • Equipment • Acc. Loads Al ~ 1 MW transfers with electron beam Stays in SR RF in an upset condition

  20. Mechanical Design Revisions Cont. • Storage Ring Tunnel • Added return air ductwork to assure temperature stability and meet smoke evacuation requirements • Temperature Stability modeling of the tunnel relative to earth berm and Experimental hall has been performed and determined to be within design parameters • Experimental Hall • Relaxed temperature stability to +/- 1 C - eliminated VAV boxes • Able to reduce beamline utility services by utilizing some services from storage ring tunnel (GN2, DI PCW) • Distributed return air to accommodate fire smoke exhaust

  21. Mechanical Design Revisions Cont. • Process Water Systems • Revised from de-centralized system to centralized system • Centralized system located in Cooling Tower pump building • DI water system will be primary-secondary piping arrangement

  22. Title II Design Management • Changes to design have used up available float for T-II • HDR agreed to maintain design delivery date of 8/25 • Required change to intermediate milestones • LOB design deferred to 2010 • Beamline support requirements will be better defined • A/E can focus on Ring Building design • Scope is frozen, only changes essential to Key Performance Parameters • A/E using added resources from other offices • Floor plans set, & all utility & process loads finalized (final rev)

  23. Title II Design Management cont’d • Additional Design Scope • HDR is designing Central DI Process Cooling Water Plant • Scope transferred from ASD • Integrates tower water and DI PCW – long term operational savings • A/E Design to Cost Clause • Changes to scope/cost are being assessed and will be incorporated in revised Design to Cost Target for A/E • A/E still accountable for construction budget and to perform V/E • Issue is complicated by influence of volatile market and role of independent estimate provided by CM

  24. Ring Building Package Scope • Ring Bldg Package Base Bid • Ring building w/ all site utilities but w/o LOBs • Beamline utilities to 60% of Ring • Exterior long beamline access corridor at LOB1-2 • Add Alternates • Extend Beamline Utilities remaining two pentants • Redundant Electrical Feed. • Shield Doors at all Ratchet Wall openings. • Clearstory windows at Ring Building. • Exterior wall panels at LOB (needed only if LOB not built) • Exterior access corridor LOB 2-3 • Exterior access corridor LOB 3-4 • LOB Package • 2 full LOBs, one shelled LOB • Lavatories and wall closure as needed for complete bldg

  25. Title II Design Schedule • Original Title II Scheduled Milestones • Title II Design 30% Review Submittal Feb. 15 • Title II Design 60% Review Submittal May 15 • Title II Design 90% Review Submittal July 15 • Title II Design 100% Review and Bid Issue Submittal Aug. 25 • Revised Title II Schedule Milestones • Title II Design 30% Review Submittal Feb. 15 Completed • Title II Design 50% Review Submittal May 19 • Title II Design 80% Review Submittal June 23 • Title II Design 100% Review and Submittal Aug. 25 • Title II Design Bid Issue Submittal Sept 29th

More Related