OPERATION AND MAINTANENCE

OPERATION AND MAINTANENCE. EMS / SCADA System Installed under SR-ULDC scheme at SRLDC. EMS / SCADA System. Contractor – M/s. GE-Harris Contract Value – Rs 148 Crores Commissioned – Jan 2002 Under commercial operation – 1 st July 2002 Under warranty upto 30-06-2004

morrison
Télécharger la présentation

OPERATION AND MAINTANENCE

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. OPERATION AND MAINTANENCE EMS / SCADA System Installed under SR-ULDC scheme at SRLDC

  2. EMS / SCADA System • Contractor – M/s. GE-Harris • Contract Value – Rs 148 Crores • Commissioned – Jan 2002 • Under commercial operation – 1st July 2002 • Under warranty upto 30-06-2004 • Under paid warranty from 01-07-04 to 30-06-05 • Under extended paid warranty from 01-07-05 to 30-06-06 • Contract price of maintenance (during paid warranty) - $ 8,28,716 [ Volume I of on-shore services] - Rs 1,94,50,000 Total Rs 5,67,42,220/- (considering 1$ = Rs 45)

  3. Present Maintenance support under Extended Paid Warranty from GEH • Non-Comprehensive • Available spares being used for replacement. • Specific time-frame to attend problem is not defined. • No deduction for delay in attending reported problem. • More than 50 Field Problem Reports (FPRs) pending as on date.

  4. WHY MAINTENANCE CONTRACT REQUIRED BEYOND 01-07-2006 ? • CRITICALITY OF DATA • ULDC DATA NOW HAS COMMERCIAL IMPACT POST ABT – HENCE HIGH UPTIMES ARE A MUST • ONLY 27 OF THE 215 RTUs REPORT TO RSCC – REST ARE REPORTING TO SEBs – HENCE SEBs/TRANSCO NEED TO BE A PART OF THE AMC • STATE ESTIMATOR AND RTNA RESULTS WOULD BE DEPENDABLE ONLY IF DATA AVAILABILITY IS HIGH • OBSOLESCENCE • OPERATING SYSTEM (AIX 4.3.2), DATABASE (SYBASE 11.9.2),RAID BOX (MTI) :- MODELS/VERSIONS ARE OBSOLETE OR HAVE REACHED END-OF-LIFE/SUPPORT • ICCP ENGINE (ONE), HUB (CABLETRON) :- COMPANIES ARE NOT EXISTING TODAY OR HAVE BEEN TAKEN OVER • GROWING SYSTEM NEEDS • ADDITION OF NEW DATA TYPES • INTEGRATION WITH NEW IEDs • CUSTOMISATION OF MODULES TO ADAPT TO REQUIREMENTS • OTHER REQUIREMENTS (LIKE DATA EXTRACTION FOR MoP) • UNPRECEDENTED EVENTS • DATABASE CORRUPTION • FAILURE OF CRITICAL MODULES • ENTIRE XA SYSTEM CRASH

  5. OPTIONS BEFORE US • GO WITH M/S GE FOR A COMPREHENSIVE MAINTENANCE SUPPORT. • ISSUES • M/S GE IS QUOTING VERY HIGH :- Rs 10.4 CR/YEAR! • NO PENALTY FOR NON AVAILABILITY. • HARDWARE TO BE PROVIDED BY CUSTOMER. • DETAILED SPECIFICATIONS AND QUOTE SHEET PREPARED BY SRLDC AND SENT TO M/S GE – THEY ARE YET TO QUOTE FOR THE SAME. • EXPLORE ALTERNATIVES WITH NELCO / HONEYWELL :- M/S GE’S INDIA CONTRACTORS FOR XA • ADVANTAGES • AMC WOULD BE COST EFFECTIVE • EXPERTISE AND MANPOWER AVAILABLE WITH BOTH PARTIES • OUR SPECIFICATIONS CAN BE IMPOSED • SOME PROPRIETARY SPARES WOULD STILL BE REQUIRED FROM GE • POSSIBILITY OF BACK TO BACK SUPPORT AGREEMENT WITH GE FOR SPECIALISED SERVICES MAY BE EXPLORED • DIS-ADVANTAGES • CUSTOMISATION AND SOURCE CODE CHANGES MAY NOT BE POSSIBLE • EXISTING BUGS WOULD STILL BE THERE

  6. OPTIONS BEFORE US • EXPLORE THE POSSIBILITIES WITH A THIRD PARTY LIKE CDAC • PRESENT STATUS • NELCO AND HONEYWELL APPROACHED AND EXPLORATORY DISCUSSIONS WERE HELD • BOTH PARTIES EXPRESSED WILLINGNESS FOR TAKING UP ENTIRE SCOPE OF WORK • CDAC WAS ALSO APPROACHED AND ARE DOING A PRELIMINARY FEASIBILITY STUDY