1 / 31

Limiting Oxygen Concentration (LOC) Work Update

Limiting Oxygen Concentration (LOC) Work Update. Steve Summer Project Engineer Federal Aviation Administration Fire Safety Branch, AAR-440. International Aircraft Systems Fire Protection Working Group Ottawa, Canada July 8 - 9, 2003. LOC Testing – Work Update.

morse
Télécharger la présentation

Limiting Oxygen Concentration (LOC) Work Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Limiting Oxygen Concentration (LOC) Work Update Steve Summer Project Engineer Federal Aviation Administration Fire Safety Branch, AAR-440 International Aircraft Systems Fire Protection Working Group Ottawa, Canada July 8 - 9, 2003 IASFPWG – Ottawa, Canada

  2. LOC Testing – Work Update • Conducted sea level (SL) testing with a J-57 engine igniter • Conducted SL testing with a short duration arc from oil burner transformer • Measured voltage/current at spark gap and calculated energy for both spark/arc generator • Composed report of all data generated to date with the various ignition sources (AR-02/79)—due out shortly IASFPWG – Ottawa, Canada

  3. Facilities – Pressure Chamber IASFPWG – Ottawa, Canada

  4. Facilities – Pressure Chamber • 353 ft3 pressure vessel • Working pressure of 650 psi. • Attached vacuum pump used to evacuate chamber to reduced pressures seen at altitude. • Not capable of simulating temperatures seen at altitude. IASFPWG – Ottawa, Canada

  5. Facilities - LOC Test Article • 9 ft3 simulated fuel tank placed inside of vessel equipped with: • Bottom surface heaters. • 12 thermocouples. • 2 piezoresistive pressure transducers mounted behind sintered porous metal discs. • Interchangeable pressure relief mechanism. • ¼-in. aluminum plate. • Foil diaphragm. • Spark gap. • 2 tungsten electrodes with controllable gap alignment and spacing IASFPWG – Ottawa, Canada

  6. Apparatus – LOC Testing IASFPWG – Ottawa, Canada

  7. Apparatus – LOC Testing IASFPWG – Ottawa, Canada

  8. Ullage Vapor Sampling IASFPWG – Ottawa, Canada

  9. LOC Testing Apparatus • Ignition Sources • 10 kV Oil burner transformer operating at ~30 mA provided both long (~1 second) and short (~0.1 second) arcs • J-57 Engine spark igniter provided a very short (~175 msecond) spark • 3" x 6" x 1" metal block heated by two cartridge heaters to temperature in excess of 1400°F • Energy Measurements • Voltage and current traces were taken using a HV and current probe at the spark gap connected to oscilloscope IASFPWG – Ottawa, Canada

  10. Oil Burner Transformer Voltage & Current Traces IASFPWG – Ottawa, Canada

  11. Test Program • JP-8 LOC Tests • Mass Loading ~ 4.5 kg/m3 • Ambient pressure corresponding to altitudes of 0, 10, 20, 30 and 38 kft • Ullage oxygen concentrations ranging from 21% to below the determined LOC • Tests conducted with two different pressure relief mechanisms • ¼-in. aluminum plate • Ignition = movement of plate • Foil diaphragm • Ignition = rupture of foil IASFPWG – Ottawa, Canada

  12. Test Program (cont.) • Tests conducted initially at all altitudes with long duration oil burner transformer arc (~0.5 J, 1 s) • Subsequent tests conducted with various ignition sources at sea level in effort to determine any variation of LOC with ignition source • Short duration oil burner transformer arc (~0.08 J, 0.1 s) • J-57 Engine igniter spark (~0.5 J, 175 ms) • Hot surface vapor ignition (HSVI) IASFPWG – Ottawa, Canada

  13. LONG DURATION OIL BURNER TRANSFORMER ARC TEST RESULTS IASFPWG – Ottawa, Canada

  14. Aluminum Plate Relief Mechanism IASFPWG – Ottawa, Canada

  15. Foil Diaphragm Relief Mechanism IASFPWG – Ottawa, Canada

  16. IASFPWG – Ottawa, Canada

  17. IASFPWG – Ottawa, Canada

  18. IASFPWG – Ottawa, Canada

  19. IASFPWG – Ottawa, Canada

  20. IASFPWG – Ottawa, Canada

  21. IASFPWG – Ottawa, Canada

  22. J-57 ENGINE SPARK IGNITER TEST RESULTS IASFPWG – Ottawa, Canada

  23. IASFPWG – Ottawa, Canada

  24. IASFPWG – Ottawa, Canada

  25. SHORT DURATION OIL BURNER TRANSFORMER ARC TEST RESULTS IASFPWG – Ottawa, Canada

  26. Short Duration Test Results IASFPWG – Ottawa, Canada

  27. HOT SURFACE VAPOR IGNITION TESTING (HSVI) IASFPWG – Ottawa, Canada

  28. HSVI Testing • Test Setup • Setup was identical to the spark/arc ignition testing. • In place of spark, a 3" x 6" x 1" metal block was heated by two cartridge heaters for use as the ignition source. • Conducted only at sea level conditions. IASFPWG – Ottawa, Canada

  29. HSVI Test Results • At 21% O2, ignition was achieved at a hot surface temperature (HST) of approximately 1350ºF. • A half-dozen other tests were conducted at O2 concentrations ranging from ~11.5 – 14%. • Though some “puffs” of smoke could be seen as the HST approached ~1200º F, no ignitions occurred. • Therefore, HSI within the fuel tank provides no more of a threat than spark ignition. IASFPWG – Ottawa, Canada

  30. Conclusions • LOC at SL through 10 kft is ~12%, increasing linearly through 40 kft to ~14.5% • Little effect seen on SL LOC due to ignition source • Long duration arc: 12% • High powered spark: 12.3% • Short duration arc: 12.9% • HSVI: ?? IASFPWG – Ottawa, Canada

  31. Future LOC Work • Currently working with a very high energy spark (>20 J) • 120 Vac, 400 cycle hard short to ground • Will be placing in the tank within the next week. • To commence testing shortly thereafter. • Technote AR-02/79 due out shortly IASFPWG – Ottawa, Canada

More Related